Alien Metals Limited (AIM: UFO) has noted that joint venture partner GreenTech Metals Limited has announced mobilisation plans for a significant drilling programme at the Munni Munni PGE-Cu-Ni Project and Whundo Cu-Zn-Au Project in Western Australia's West Pilbara. The programme, approved by GreenTech's board, comprises approximately 4,750 metres of reverse circulation drilling and 3,560 metres of diamond drilling, with a drill rig expected to arrive on site in late July 2026. Alien retains a 30% interest in the joint venture, free carried to feasibility study completion, alongside a 10% stake in GreenTech's issued share capital.

Key Points

  • Alien Metals Limited (AIM: UFO) holds 30% free-carried interest in Munni Munni and Whundo projects through GreenTech Metals joint venture
  • First drill rig mobilisation scheduled for late July 2026, with second rig to follow heritage clearance completion
  • Board-approved exploration programme totals approximately 8,310 metres of drilling (4,750m RC and 3,560m diamond)
  • Government co-funded FLEM geophysical survey commencing early July 2026 across 8.2km² with A$100,000 government funding contribution
  • Heritage survey scheduled for 10 August 2026 to clear additional drill locations and access routes
  • Metallurgical workstreams focused on copper-PGE sulphide characterisation with results expected in August
  • Alien holds 37.9 million GreenTech shares representing approximately 10% of GreenTech's issued capital

Drill rig mobilisation and phased programme strategy

GreenTech Metals has contracted a drill rig for mobilisation to the Munni Munni and Whundo projects in late July 2026, marking a significant advancement in the exploration of these Western Australian mineral assets. A second drilling rig is expected to commence operations following completion of additional heritage clearances, enabling a staged approach to the approved exploration programme.

The phased mobilisation strategy allows initial drilling to commence immediately from existing cleared drill pads at Munni Munni whilst ensuring efficient equipment utilisation as additional drilling areas receive heritage approval. This approach demonstrates operational flexibility, as drilling at Whundo will focus on testing extensions to known high-grade copper-gold mineralisation and collecting material for metallurgical testwork to support future resource updates.

Approved exploration drilling specifications

The board-approved exploration programme comprises approximately 4,750 metres of Reverse Circulation (RC) drilling and 3,560 metres of diamond drilling (DD), totalling approximately 8,310 metres of drilling across both projects. The programme includes wider-diameter diamond holes specifically designed to collect metallurgical composite samples, reflecting the company's focus on advancing metallurgical understanding alongside geological exploration.

Initial drilling at Munni Munni will be undertaken from existing cleared drill pads, prioritising operational efficiency and minimising delays pending heritage approvals for additional locations. The inclusion of larger-diameter diamond holes within the programme indicates GreenTech's commitment to generating material suitable for comprehensive metallurgical testwork, which will inform future resource estimation and scoping study activities.

Fixed-Loop Electromagnetic survey targeting basal mineralisation

A Government co-funded Fixed-Loop Electromagnetic (FLEM) survey is scheduled to commence in early July 2026, covering approximately 8.2 square kilometres across 56.4 line kilometres using four large transmitter loops with 75-metre station spacing. The survey has been specifically designed to identify conductive bedrock targets associated with potential copper sulphide mineralisation along the largely untested basal contact of the Munni Munni intrusion, a priority exploration target.

The total survey cost is estimated at approximately A$200,000, with the Western Australian Government's Co-funded Geophysics Programme providing A$100,000 of this funding. Survey results are expected to assist in refining drill targeting ahead of the planned drilling programme, potentially identifying additional high-priority drill targets within the basal contact zone. This geophysical work represents targeted technical advancement of the asset base prior to the commencement of drilling activities.

Heritage survey to unlock additional drilling locations

An eight-day heritage survey is scheduled to commence on 10 August 2026, designed to clear additional drill locations and access routes across the Munni Munni mineralised footprint and priority basal contact target areas. This survey programme forms a critical component of the overall mobilisation strategy, enabling the second drilling rig to commence operations on additional cleared locations.

The scheduling of the heritage survey following initial rig mobilisation reflects a coordinated approach to project development, ensuring that heritage considerations are addressed systematically whilst maintaining exploration momentum. Results from the FLEM geophysical survey conducted in July are expected to inform the identification of priority basal target areas for clearance during the August heritage survey, creating a logical progression from geophysical targeting to heritage clearance to drilling commencement.

Metallurgical workstreams advancing copper-PGE concentrate development

Ongoing resource re-estimation and metallurgical workstreams continue to advance, with particular focus on copper-dominant mineralisation and the production of a copper-PGE (Cu-PGE) concentrate. Current metallurgical studies remain focused on demonstrating the suitability of conventional flotation techniques whilst expanding the programme to better characterise the copper-PGE sulphide assemblage and define processing parameters required to produce a marketable Cu-PGE concentrate.

The expanded emphasis on copper reflects current market conditions and ongoing discussions with potential offtake partners, suggesting that GreenTech is positioning the project to capitalise on current commodity price environments. Results from the metallurgical programme are anticipated during August 2026 and are expected to support net smelter return parameters for incorporation into the updated Mineral Resource estimate and an initial Scoping Study, representing a direct link between exploration drilling, metallurgical testwork, and project development advancement.

Mineral resource re-estimation programme timeline

Work continues on the planned Munni Munni Mineral Resource re-estimation, with geological modelling and metallurgical testwork progressing in parallel with the exploration programme. The timing of results from the metallurgical programme in August 2026 is designed to enable incorporation of key findings into the updated resource estimate, linking exploration and metallurgical outcomes directly to formal resource definition.

The integration of metallurgical results into the resource re-estimation process, followed by an initial Scoping Study, represents a systematic approach to advancing the project from exploration through to preliminary feasibility assessment. The announcement states that results from the metallurgical programme are expected to support net smelter return parameters for the updated resource estimate, indicating that market-based valuation parameters are being incorporated into resource definition.

Alien Metals' strategic interest and free-carry position

Alien Metals Limited retains a 30% interest in the Munni Munni and Whundo joint venture, held on a free-carry basis to completion of a bankable feasibility study. This structure provides Alien with exposure to the exploration and development upside of both projects whilst limiting capital requirements during the pre-feasibility stage, allowing the company to focus capital allocation on other projects within its portfolio.

Additionally, Alien holds 37.9 million shares in GreenTech Metals Limited, representing an approximate 10% interest in GreenTech's issued share capital. This dual participation structure—comprising both direct project interest and equity participation in the operator—provides Alien with exposure to value creation across multiple dimensions as the projects progress through exploration and development phases.

Project context and mineral resource background

The Munni Munni PGE-Cu-Ni Project is described as one of Australia's largest platinum group metal systems, hosting a historic resource of 2.2 million ounces of PGM (comprising palladium, platinum, and rhodium) and gold. The project is located in the West Pilbara region of Western Australia, an established mining jurisdiction with established export infrastructure and established operational experience in mineral extraction and processing.

The Whundo Cu-Zn-Au Project represents a secondary focus within the current drilling programme, with the announcement indicating that initial drilling will prioritise high-priority copper-gold extension targets. The announcement indicates that both projects represent advanced precious and base metal assets, reflecting Alien Metals' strategic positioning across multiple commodity exposures within the Pilbara region.

Investor considerations and next milestones

Investors in Alien Metals may be watching several key milestones in the coming months. The commencement of the FLEM geophysical survey in early July 2026 will provide early indications of geophysical targeting success, with survey results expected to refine drilling priorities. The mobilisation of the first drill rig in late July 2026 will mark the beginning of active exploration drilling, whilst the August heritage survey will determine the pace at which additional drilling locations become available.

The anticipated August 2026 release of metallurgical results represents a critical juncture for project value assessment, as these results will inform net smelter return parameters and support the preparation of an initial Scoping Study. The completion of the updated Mineral Resource estimate following incorporation of metallurgical results will provide formal updated resource definition for the Munni Munni project, a significant milestone in project advancement. Investors should monitor announcements from GreenTech Metals for detailed results from these programmes, which may inform Alien Metals' own disclosures regarding the joint venture assets.