Aminex plc has announced that all parties to the Ntorya gas development in Tanzania have agreed a revised implementation programme following a meeting convened by the Tanzanian Ministry of Energy on 26 August 2026. The new schedule sets out near-term operational milestones including a well workover, well testing, and the drilling of a newly planned well, with first gas targeted for December 2026. The agreement represents a significant step forward after Aminex had previously issued a Notice of Dispute on 21 August 2026. Investors will be watching closely as the company and its joint venture partners move to execute the accelerated programme.

Key Points

  • Aminex plc (AEX) — Ireland-headquartered upstream oil and gas company with operations in Tanzania
  • All parties agreed a revised Ntorya gas development schedule at a meeting facilitated by the Tanzanian Ministry of Energy on 26 August 2026
  • Key milestones: NT-1 workover in October 2026, NT-2 testing in November 2026, NT-Central drilling in December 2026, first gas targeted December 2026
  • Investors should watch for formal Joint Venture approval under the Joint Operating Agreement and further updates on the Notice of Dispute

Tanzanian Ministry of Energy Rejects Operator's Delay Proposal, Confirms Accelerated Ntorya Timetable

The Tanzanian Government, represented at the meeting by the Ministry of Energy, the Petroleum Upstream Regulatory Authority (PURA), and the Tanzania Petroleum Development Corporation (TPDC), declined to approve a proposal by operator ARA Petroleum Tanzania Limited (APT) that would have extended and delayed the project timetable. Instead, all parties agreed to a revised schedule that brings forward operational activity. The announcement states that the NT-1 well workover is scheduled for October 2026, NT-2 well testing for November 2026, and drilling of the newly planned NT-Central well for December 2026, with first gas from NT-1 and NT-2 also targeted for that month.

NT-Central Well Added to Programme Alongside Previously Planned Chikumbi-1 Drilling

A notable development within the revised programme is the inclusion of the NT-Central well, previously earmarked for a later phase of field development. Following a change of management at ARA Petroleum LLC and a technical reappraisal of the Ntorya project, APT had proposed substituting NT-Central for the Chikumbi-1 well (CH-1), with CH-1 deferred. Under the schedule now agreed by all parties, NT-Central will be drilled first in December 2026, with CH-1 to follow thereafter, meaning both wells are retained within the programme rather than one replacing the other.

Ntorya-to-Madimba Pipeline Confirmed On Track and APT Funding Verified for Full Programme

The announcement confirms that the Ntorya to Madimba pipeline will be completed in time to receive first gas from the Ntorya field in December 2026, a logistical requirement for the development to proceed on schedule. APT also confirmed to all meeting attendees that it holds all necessary funds to carry out the revised development programme. The parties agreed that APT should execute planned activities in accordance with the revised schedule and without unnecessary delay, with the programme now proceeding through the formal Joint Venture approval process under the Joint Operating Agreement.

Aminex Views Agreement as Progress Toward Resolving August 2026 Notice of Dispute

Aminex, through its wholly owned subsidiary Ndovu Resources Limited, holds its interest in the Ntorya field via the Ruvuma Production Sharing Agreement. The company considers the agreement to represent important progress toward resolving the matters that gave rise to its Notice of Dispute, announced on 21 August 2026. Executive Chairman Charles Santos acknowledged the constructive role played by the Ministry of Energy's Permanent Secretary for Petroleum, Dr James Mataragio, in facilitating the meeting. The company stated it will provide further updates on the Notice of Dispute as appropriate, leaving investors to monitor developments as the formal JV approval process advances.