Aminex Plc has published an operational update on its Ntorya gas development in Tanzania, confirming that its subsidiary Ndovu Resources Limited and joint venture partner ARA Petroleum Tanzania Limited have approved revised work programmes and budgets for 2026 and 2027. The joint venture has sanctioned gross expenditure of up to US$75 million across the remainder of 2026 and 2027, spanning multiple wells and pipeline infrastructure. The update outlines a detailed sequencing of well testing, drilling, and production milestones that investors will be monitoring closely over the coming months.
Key Points
- Aminex Plc (AEX) — Irish-listed upstream oil and gas company focused on Tanzanian gas development
- Joint venture approves gross expenditure of up to US$75 million for the Ntorya gas development across the remainder of 2026 and 2027
- First gas from Ntorya-2 targeted for December 2026; Ntorya-3 spud scheduled for December 2026 with first gas expected September 2027 if successful
- Investors should watch the signing of the gas processing unit contract and the drilling rig contract, both expected in October–November 2026
Ntorya-2 Testing and Gas Processing Unit Contract Ahead of December 2026 First Gas
Bridge plug removal and testing of the Ntorya-2 well is scheduled to commence in November 2026, with production into the Ntorya-Madimba pipeline targeted for December 2026. The announcement states that necessary flowlines will be constructed in parallel and completed prior to production commencing. Separately, the contract for the supply of the gas processing unit is expected to be signed later in September 2026. These near-term contract signings represent concrete operational milestones that the market will be watching as Aminex moves towards its first gas target.
Ntorya-1 Wellhead Maintenance to Determine Whether a Rig Workover Is Required
Wellhead maintenance and slickline operations on Ntorya-1 are scheduled to begin in October 2026. The company states that the results of these operations will determine whether further intervention, including a rig-operated workover, is necessary. Should a workover be required, it would be carried out immediately after drilling of the Ntorya-Central well, which the announcement says would delay gas production from Ntorya-1 to December 2027. This contingency introduces a degree of scheduling risk that investors should factor into their assessment of the overall development timeline.
Ntorya-3 Drilling Contract at Advanced Stage with Spud Planned for December 2026
Negotiations to contract a drilling rig for the Ntorya-Central location are described as being at a very advanced stage, with the contract expected to be signed in October 2026 and the well — designated Ntorya-3 — scheduled to spud in December 2026. If successful, first gas from Ntorya-3 is targeted for September 2027. Following completion of NT-3 operations, the joint venture retains the option to drill up to two further appraisal and development wells at the Ntorya-East and Ntorya-West locations on a back-to-back basis, subject to NT-3 results.
Ntorya-Madimba Pipeline Approximately 95% Complete as TPDC Confirms Progress
The Ntorya to Madimba Pipeline is scheduled for completion in December 2026 and will transport gas to the Madimba Gas Processing Plant. Tanzania Petroleum Development Corporation has confirmed that approximately 95% of pipelaying and infilling is complete, with connection and metering works at Madimba ongoing. Executive Chairman Charles Santos stated the company remains focused on maintaining current momentum and delivering first gas in December, characterising the provisional 2027 programme as providing a clear pathway for further early drilling beyond first production into the broader Ntorya field development.