Ampeak Energy Limited (AMP) has published its unaudited interim results for the six months ended 30 June 2026, reporting revenues of £2.2 million, down from £3.5 million in the comparable period, and a pre-tax loss of £4.7 million. The Edinburgh-headquartered developer, builder and operator of sustainable energy projects attributed the revenue decline primarily to reduced electricity generation from its MeyGen tidal stream array following turbine servicing works. Investors will note that after the period end, JB Energy acquired a 24.7% equity stake in AW1 Storage Holdings Limited for £7.8 million, with Ampeak retaining a controlling 50.6% interest.
Key Points
- Ampeak Energy Limited (AMP) — Singapore-incorporated, AIM-quoted sustainable energy developer operating principally from Edinburgh
- Revenues fell to £2.2m in H1 2026 (H1 2025: £3.5m); pre-tax loss of £4.7m broadly in line with the prior period loss of £4.6m
- JB Energy acquired 24.7% of AW1 Storage Holdings for £7.8m post period-end; cash at 30 June 2026 stood at £3.6m
- Investors should watch progress on securing further Group funding and the timeline for AW1 commencing operations
MeyGen Tidal Array Generation Drops to 4.4GWh After Turbine Servicing
MeyGen, described in the announcement as a world-leading tidal stream project, generated 4.4GWh during the six-month period to 30 June 2026, compared with 7.9GWh in H1 2025. The reduction followed offshore works completed in December 2025, which resulted in one turbine, TTG1, returning to shore for servicing. Three turbines remained operational throughout the period. Tidal segment revenues fell to £2.0 million from £3.2 million in the prior period, with segment EBITDA declining to £0.9 million from £2.3 million. The announcement states the team continues to work towards redeployment of the serviced turbine.
AW1 Battery Storage Project Attracts £7.8m JB Energy Investment Post Period-End
Construction of the AW1 Battery Energy Storage project progressed throughout the first half of 2026, with the announcement describing it as a transformational project for the Group. Following the period end, JB Energy acquired a 24.7% equity interest in AW1 Storage Holdings Limited for £7.8 million, while Ampeak retained a controlling 50.6% interest. The company states this transaction reinforces the asset's value while strengthening liquidity. Ampeak is also progressing plans to expand AW1's capacity from 2 hours to 4 hours upon completion, and separately advancing the AW2 and Mey BESS projects, though National Grid connections reform has introduced uncertainty around connection timelines.
Operating Costs Fall to £3.7m but Funding Remains a Board Priority
Group operating costs reduced to £3.7 million from £4.6 million in H1 2025, partly because the prior period included a non-recurring £0.8 million downward adjustment to the value of the AW1 land sale. Employee costs also fell to £1.8 million from £2.0 million. Cash and cash equivalents stood at £3.6 million at 30 June 2026, compared with £5.3 million at 30 June 2025. The announcement explicitly states that securing further funding remains an important Board priority. Going concern disclosures reference a parent company guarantee to Scottish Enterprise of £3.8 million and potential repayment of historical grant funding of £4.1 million as identified risk factors.
Uskmouth and MeyGen Pipeline Underpin Ampeak's Strategy to 2035
Beyond AW1, the announcement highlights planning-consented projects at Uskmouth Sustainable Energy Park and MeyGen as platforms for future growth. Corporate costs and estate maintenance fees at Uskmouth remained steady at £0.9 million. The Board's stated strategy, described as Building a Sustainable Future to 2035, targets Ampeak's transformation into a leading developer, owner and operator of sustainable energy infrastructure generating long-term, predictable cashflows. The company identifies growing UK and Ireland demand for large-scale battery storage, driven by renewable energy expansion and digital infrastructure growth, as a structural tailwind, while acknowledging that funding markets remain challenging.