Cadence Minerals plc (AIM: KDNC) has announced that DEV Mineração S.A. completed hot commissioning of the Azteca processing plant at the Amapá Iron Ore Project in Brazil within 30 days of the 45-day window permitted by the Amapá State Environmental Secretariat (SEMA/AP). Commissioning and Installation Licence compliance reports were filed with SEMA/AP on 29 October 2026, completing the submissions required for the Azteca Operating Licence application. The Operating Licence remains pending, and commercial operations and first shipments are subject to its grant. Investors will be watching closely, as the company's unchanged target of approximately 380,000 tonnes per annum of approximately 65% Fe concentrate depends on regulatory approval and access to higher-grade feed.

Key Points

  • Cadence Minerals plc (AIM: KDNC) holds a 36.2% equity interest in Pedra Branca Alliance Pte Ltd, which owns 100% of DEV Mineração S.A., the owner and operator of the Amapá Iron Ore Project in Brazil
  • DEV completed hot commissioning of the Azteca processing plant in 30 days of a 45-day SEMA/AP consent window, with 164 operational items checked
  • Approximately 6,200 wet tonnes of feed were processed and approximately 2,800 wet tonnes of concentrate produced, representing approximately 45% mass recovery; assay results are pending
  • Investors should watch for the Operating Licence decision, assay and optimisation testwork results expected within four to six weeks, and bridge completion ahead of targeted first shipment before year end

Azteca Plant Processes 6,200 Wet Tonnes During 30-Day Commissioning Run

Hot commissioning at the Azteca plant ran from 23 September to 23 October 2026 on weekdays, comprising two days of water-only tests followed by feed trials. Over approximately 160 operating hours, feed averaged approximately 40 wet tonnes per hour — roughly one third of the plant's operational feed capacity of approximately 110 tonnes per hour — which fell within the permitted 25%–50% commissioning range. Water-supply leaks and a failed pump motor cost approximately five days during the run; both issues have since been repaired. The plant is currently undergoing planned maintenance covering identified repairs and improvements, and DEV is finalising haulage, port handling and related contracts ahead of commercial operations.

Commissioning Ran on Lower-Grade Feed as DEV Prioritised Operating Licence Filing

The Azteca plant uses magnetic separation followed by gravity spirals. Previous testwork announced on 28 July 2026 confirmed this flowsheet produces approximately 65% Fe concentrate from design-grade feed grading approximately 48% Fe, at approximately 53% mass recovery and 72.8% iron recovery. However, access works to the higher-grade feed area had not been completed, so DEV commissioned on lower-grade accessible material to avoid delay to the Operating Licence application. Commissioning concentrate grade is not yet known, and assay results are pending from an accredited laboratory in Belo Horizonte. Management stated that mass recovery is expected to move towards the approximately 53% recorded in July 2026 testwork once design-grade feed is used.

Optimisation Testwork Brought Forward Using SEMA/AP Licence Review Period

Cadence disclosed that optimisation testwork on higher-intensity magnetic separation has been brought forward to make use of the Operating Licence review period. This work, funded from the optimisation allocation of the September 2026 fundraising, will assess whether iron and mass recovery can be increased. An on-site XRF laboratory has been approved and budgeted by DEV, expected to be operational by the end of November 2026, enabling feed and product iron grades to be returned within hours during operation. An additional dewatering screen to reduce product moisture and transport cost has also been approved, with installation timing to be confirmed on contract award.

Bridge Refurbishment and Operating Licence Grant Remain Key Gates to First Shipment

As at 30 October 2026, contractors had refurbished approximately one third of the timber deck of the Pedra Branca do Amapari bridge, with the walkway and fencing completed. Bridge completion is targeted before first road haulage begins. The company's stated aim remains a first commercial shipment before the end of 2026, subject to Operating Licence grant, feed access, plant performance and logistics readiness. As at 31 May 2026, Cadence's total investment in the Amapá Project was approximately US$16.1 million. The Amapá project hosts a JORC-compliant Mineral Resource of 276.2 million tonnes at 38% Fe, and the production target of approximately 380,000 tonnes per annum of approximately 65% Fe concentrate remains unchanged.