Cadence Minerals plc (AIM: KDNC) has announced that refurbishment of the Azteca processing plant at its Amapá Iron Ore Project in Brazil reached 97% weighted physical completion as of 22 August 2026, outpacing the planned 95% and representing a ten-percentage-point advance from the 87% reported on 10 August 2026. In parallel, Brazilian operating company DEV Mineração S.A. has formally submitted its application for the Azteca operating licence to the Amapá State Environmental Secretariat. The programme continues to target full completion by 31 August 2026, with integrated commissioning the next phase before commercial operations can begin.

Key Points

  • Cadence Minerals plc (AIM: KDNC)
  • Azteca plant refurbishment at the Amapá Iron Ore Project reached 97% weighted physical completion as of 22 August 2026, ahead of the 95% planned
  • 58 of 64 identified activities completed; electrical installation advanced from approximately 69% to 95%, ahead of the 87% planned; operating licence application submitted to SEMA/AP
  • Investors will be watching for confirmation of refurbishment completion by 31 August 2026, progress through integrated commissioning, and grant of the operating licence

Azteca Refurbishment Advances to 97% with Electrical Installation Now Ahead of Schedule

As of 22 August 2026, 58 of the 64 identified refurbishment activities at the Azteca plant had been completed. Electrical installation, previously identified as the principal execution constraint, advanced from approximately 69% to 95% against a planned figure of approximately 87%, moving that workstream ahead of schedule. Core processing systems including the hopper/feed system, transfer conveyor, screen and process tank are fully complete. Magnetic separation and piping stand at approximately 99% and 98% respectively, while the spiral concentrator reached approximately 85% completion, above the planned 78%.

Remaining Close-Out Work and 31 August 2026 Completion Target at Amapá

The six outstanding activities include three close-out items — the magnetic separation technical handover, the water piping technical handover and remaining electrical panel work — alongside completion of the spiral concentrator and final equipment connections. The company states that management is focused on closing these specific items. Cadence continues to target 31 August 2026 for full completion of refurbishment works. The announcement also confirmed no lost-time injuries or reportable safety incidents were recorded during the reporting period, which the company notes as part of its execution discipline.

DEV Mineração Submits Operating Licence Application to SEMA/AP

DEV Mineração S.A., the Brazilian operating company in which Cadence holds an indirect 36.2% equity interest via Pedra Branca Alliance Pte Ltd, has formally submitted its application for the Azteca operating licence (Licença de Operação) to the Amapá State Environmental Secretariat. The application is now subject to technical review, which may include requests for additional information and a site inspection. Grant of the operating licence remains a regulatory prerequisite before commercial operations and shipments can commence, representing a key risk factor for the project timeline.

Amapá Project Scale and Cadence's US$16.1 Million Investment Position

The Amapá DR Iron Ore Project hosts a JORC-compliant mineral resource of 276 million tonnes at 38% Fe and proven and probable ore reserves of 195.8 million tonnes at 39.34% Fe. An updated pre-feasibility study published on 3 December 2024 indicated a post-tax NPV of US$1.97 billion over a 15-year mine life, targeting 5.5 Mtpa of 67.5% Fe direct reduction grade concentrate. The Azteca plant specifically targets approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. As of 31 May 2026, Cadence's total investment in the project stood at approximately US$16.1 million.