Cadence Minerals plc (AIM: KDNC) has announced that refurbishment of the Azteca processing plant at its Amapá Iron Ore Project in Brazil is complete, with mechanical completion achieved on 4 September 2026. All eight plant systems are now finished, and cold commissioning is scheduled to begin next week. Commercial operations and shipments remain subject to successful commissioning and receipt of the Brazilian operating licence, known as the Licença de Operação, making that regulatory milestone a key watchpoint for investors.

Key Points

  • Cadence Minerals plc (AIM: KDNC) holds a 36.2% equity interest in the Amapá Iron Ore Project in Brazil
  • Mechanical completion of the Azteca processing plant was achieved on 4 September 2026, with all eight plant systems confirmed complete
  • Cadence's total investment in the Amapá Project was approximately US$16.1 million as of 31 May 2026
  • Investors should watch for completion of cold, wet, and hot commissioning stages, and grant of the Brazilian operating licence before commercial operations can begin

Azteca Advances from 48% Completion in July to Full Mechanical Completion in September 2026

The announcement states that Azteca advanced from approximately 48% completion on 2 July 2026 to full mechanical completion on 4 September 2026, representing a significant acceleration in the refurbishment programme. All eight plant systems — comprising the hopper and feed system, transfer conveyor, screen, process tank, magnetic-separation circuit, piping, spiral concentrator, and electrical system — are now complete. The company also confirmed that no safety incidents were recorded during the reporting period, which the disclosure suggests reflects disciplined project execution through the final phase of works.

Cold, Wet and Hot Commissioning Sequence Now Under Way at Amapá's Azteca Plant

Cold commissioning, which involves testing completed equipment, electrical distribution, and control systems without ore, is scheduled to start next week. Wet commissioning will follow, introducing process water and trial material through the wet circuit. Hot commissioning — involving limited processing of run-of-mine material to tune plant grade and recovery — will commence once applicable regulatory requirements are met. Any concentrate produced during hot commissioning will be stockpiled rather than sold. The company was clear that commercial operations and shipments remain dependent on both successful commissioning and grant of the Operating Licence from SEMA/AP.

Brazilian Operating Licence Remains the Critical Regulatory Gate for Amapá Commercial Production

DEV Mineração S.A., the owner and operator of the Amapá Project in which Cadence holds its interest via a 36.2% stake in Pedra Branca Alliance Pte Ltd, has submitted its application for the Operating Licence to SEMA/AP. The previously granted installation licence authorised the refurbishment works now completed. Cold and wet commissioning are permitted under existing approvals, but hot commissioning and commercial operations cannot proceed until the Operating Licence is granted. This regulatory dependency represents a company-specific risk that investors will be monitoring closely.

Azteca Targets 380,000 Tonnes Per Annum as First Cash-Flow Platform for Amapá Redevelopment

Azteca is intended to process existing tailings to produce approximately 380,000 tonnes per annum of approximately 65% Fe concentrate, generating early cash flow to support broader project development. The wider Amapá project hosts a JORC-compliant mineral resource of 276 million tonnes at 38% Fe, with a pre-feasibility study published on 3 December 2024 citing a post-tax NPV of US$1.97 billion over a 15-year mine life at 5.5 Mtpa. Azteca's successful commissioning would represent the first operational milestone in that longer-term redevelopment strategy, subject to regulatory and commissioning conditions being met.