Cadence Minerals plc (AIM: KDNC) has announced that refurbishment of the Azteca processing plant at its Amapá Iron Ore Project in Brazil has advanced from 77% to 87% weighted physical completion. The update confirms the programme is now precisely on plan, with the 31 August 2026 completion target unchanged. The company also confirmed no lost time injuries or reportable safety incidents during the reporting period, a positive operational note ahead of the anticipated commissioning phase.
Key Points
- Cadence Minerals plc (KDNC), listed on AIM
- Azteca plant refurbishment advanced from 77% to 87% weighted physical completion, now matching the planned progress rate
- 49 of 64 identified activities are complete; 31 August 2026 completion target is unchanged; Cadence holds a 36.2% equity stake with a total investment of approximately US$16.1 million as at 31 May 2026
- Investors should watch for confirmation of commissioning commencement and receipt of the Operating Licence (Licença de Operação) from SEMA/AP
Electrical Installation and Key Processing Circuits Drive Progress at Azteca
The announcement highlights several processing circuits now fully complete, including the hopper/feed system, transfer conveyor, screen, and process tank. Electrical installation has advanced materially, rising from approximately 43% to 69% completion and is now in line with plan — having been identified as the principal execution focus in Cadence's previous update. The spiral concentrator stands at approximately 64% complete against a planned 50%, indicating it is running slightly ahead of schedule, while piping is approximately 88% complete against an 85% target.
Magnetic Separation Identified as the Principal Remaining Workstream to Close
With 49 of the 64 identified activities now complete, magnetic separation has emerged as the primary outstanding processing workstream, currently at approximately 75% completion. Two related activities, including technical handover, remain outstanding. Management's immediate priorities also include completion of outstanding water piping works, tank measurement and handover, the remaining spiral concentrator workstream, and final electrical connection activities. The announcement states that CEO Kiran Morzaria, a qualified engineer, has reviewed and approved the technical content disclosed.
Operating Licence Remains a Critical Condition Before Azteca Can Begin Commercial Shipments
Commercial operations and shipments from Azteca are subject to successful commissioning and receipt of the Operating Licence (Licença de Operação) from the State of Amapá Environmental Authority, known as SEMA/AP. The company's announcement states that the Operating Licence workstreams are progressing as expected alongside refurbishment completion. The previously granted Installation Licence authorises the current refurbishment and installation works. Cadence notes that bridge, road, and Tailings Storage Facility works referenced in earlier announcements remain separate from the Azteca refurbishment scope.
Amapá Project Scale and Cadence's 36.2% Stake Underpin the Strategic Significance
The broader Amapá DR Iron Ore Project hosts a JORC-compliant mineral resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe. A Pre-Feasibility Study published in December 2024 indicated a post-tax NPV of US$1.97 billion over a 15-year mine life. Azteca is intended as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings, designed to generate early cash flow. Cadence's total investment stands at approximately US$16.1 million for its 36.2% equity stake.