Cora Gold Limited (AIM: CORA.L), the West African gold developer focused on south Mali, has announced that Mali's Council of Ministers approved the first interim renewal of the Sanankoro II exploration permit at a meeting held on 21 August 2026. The 84.11 sq km permit forms a core component of Cora's proposed 100 sq km mining permit area at its flagship Sanankoro Gold Project. The renewal marks a meaningful procedural step forward as the company works to consolidate all five contiguous permits under a single mining permit, enabling construction of the Sanankoro Gold Mine to commence.

Key Points

  • Cora Gold Limited (AIM: CORA.L) — West African gold developer, Mali and Senegal
  • Mali's Council of Ministers approved the first interim renewal of the Sanankoro II exploration permit on 21 August 2026
  • The permit covers 84.11 sq km; Cora is pursuing a proposed 100 sq km mining permit at Sanankoro; the project holds a Probable Reserve of 531 koz at 1.13 g/t Au
  • Investors should watch for renewal of the Bokoro II and Kodiou exploration permits, completion of the FEED process, and progress on the formal mining permit application

Sanankoro II Permit Renewal Advances Cora's Mali Mining Permit Reshaping Exercise

The Sanankoro II exploration permit was originally awarded on 2 March 2021 and covers an area of 84.11 sq km within the Yanfolila Gold Belt in south Mali. Its renewal is described by the company as part of an ongoing permit reshaping exercise designed to consolidate all mining infrastructure under a single mining permit area. Chief Executive Bert Monro stated in the announcement that the renewal represents "a significant step towards being awarded a mining permit for Sanankoro," with the next stage requiring the renewal of the Bokoro II and Kodiou exploration permits, both of which were affected by Mali's November 2022 moratorium on permit issuance.

Mali Moratorium History and March 2025 Partial Lifting Shape Cora's Permitting Timeline

Mali's government suspended the issuance of mining sector permits on 28 November 2022, directly impacting Cora's ability to renew several exploration permits and apply for new ones. On 15 March 2025, the moratorium was partially lifted, allowing the mining administration to process permit renewal applications and transitions from exploration to mining phase — though new permit issuances and exploration permit transfers remain restricted. The Sanankoro II renewal is therefore the first to benefit from this partial reopening, with the Bokoro II and Kodiou permits representing the remaining outstanding regulatory steps before Cora can formally progress its mining permit application.

FEED Process and US$120 Million Gold Stream Position Sanankoro for Construction

In parallel with permitting, Cora disclosed that its Front-End Engineering Design (FEED) process, announced on 26 May 2026, is making progress alongside an active drill programme targeting deposit extensions and near-mine greenfield targets. The FEED process is described as a key milestone enabling decisions on long lead items and potentially compressing the project's delivery timeline once a mining permit is received. Cora also secured a binding US$120 million gold stream in April 2026 that, alongside existing equity, is stated to fully fund Sanankoro's development through to production, according to the announcement.

Sanankoro's 2025 Definitive Feasibility Study Highlights and Remaining Regulatory Risk

Cora's 2025 Definitive Feasibility Study reported a Probable Reserve of 531 koz at 1.13 g/t Au, a post-tax IRR of 98%, a post-tax NPV of US$365 million, and all-in sustaining costs of US$1,623 per ounce, based on a gold price of US$1,623 per ounce. Investors will be monitoring whether the Malian government proceeds with timely renewal of the Bokoro II and Kodiou permits, as these remain essential before the reshaping exercise can be completed and the 100 sq km mining permit application formally advanced. Country-specific regulatory risk in Mali remains a key factor for the project's construction timeline.