Cornish Metals plc (AIM: TIN), a mineral exploration and development company focused on its wholly owned South Crofty tin project in Cornwall, has published unaudited interim results for the six months ended 30 June 2026. The company reported a loss after tax of £5.5 million, up from £3.5 million in the equivalent prior period, driven by interest accrued on its US$210 million senior secured bond and shareholder debt facilities. The results cover a period of significant financing activity and accelerating on-site construction progress, with the company targeting first production of tin concentrate in mid-2028.

Key Points

  • Cornish Metals plc (AIM: TIN)
  • The company placed an oversubscribed US$210 million senior secured bond in May 2026 and secured up to approximately £52 million in bridging debt facilities from its two largest shareholders
  • Bond proceeds of US$215.8 million remain in escrow, conditional on completing an equity fundraising of at least US$161 million; cash at 30 June 2026 stood at £12.0 million
  • Investors should watch for completion of the equity raise required to release bond proceeds and the targeted final investment decision

US$210 Million Senior Secured Bond and £52 Million Shareholder Facilities Secured to Fund South Crofty Construction

The US$210 million senior secured bond, which settled on 21 May 2026, carries a fixed coupon of 13.5% per annum, a six-year tenor, and is callable at the company's option after three years. Bonds were issued at 98% of nominal amount and mature at 103.5%. Separately, the National Wealth Fund and Vision Blue Resources, the company's two largest shareholders, provided debt facilities of up to approximately £52 million carrying interest at 13.0% per annum. Tranche 1 drawdowns, totalling £21.1 million and US$13.7 million respectively, were completed during the period, with a second uncommitted tranche drawn post period-end. The bond proceeds remain in escrow pending satisfaction of conditions precedent, most critically the equity raise of at least US$161 million.

South Crofty Mine Dewatering Reaches 360 Metres Below Surface for First Time in Over 28 Years

A key operational milestone was achieved during the period, with mine dewatering progressing through the fully commissioned New Cook's Kitchen mid-shaft pump station at approximately 360 metres below surface — the first time this level has been dewatered in more than 28 years. Dewatering is on track to reach the 400-level, approximately 730 metres below surface, in the first half of 2027. Shaft refurbishment has resumed below the pump station, process plant excavation reached approximately 50% completion by period end and approximately 80% post period-end, and Front-End Engineering Design for the process plant was completed with Detailed Engineering now underway, both led by Ausenco.

Tin Spot Price of US$56,600 Per Tonne Drives Revised Post-Tax NPV Estimate of Approximately £550 Million

Tin prices remained robust through the period, with a spot price at 30 June 2026 of approximately US$56,600 per tonne, significantly above the US$33,900 per tonne assumption used in the company's updated Preliminary Economic Assessment announced on 29 September 2025. Adjusting for spot metal prices and exchange rates at the period end, the post-tax NPV6% of South Crofty is estimated at approximately £550 million, compared with £180 million under PEA assumptions. The company notes that South Crofty hosts the highest-grade known tin Mineral Resource not currently in production globally, with annual production expected to reach approximately 4,700 tonnes of tin-in-concentrate in years two to six.

Going Concern Uncertainty Remains as Equity Fundraising of at Least US$161 Million Still Required

The directors have prepared the interim financial statements on a going concern basis but acknowledge material uncertainties. The group has no current revenue source and the release of the US$215.8 million held in escrow is contingent on completing an equity raise of at least US$161 million. Cash and cash equivalents at 30 June 2026 were £12.0 million, falling to a reported £14.5 million at 22 September 2026 after the second tranche drawdown, excluding escrow balances. Net cash used in investing activities increased to £23.3 million from £9.8 million in the prior period, reflecting accelerating construction expenditure. The directors expressed confidence in securing financing but noted no certainty as to its quantum, terms, or timing.