Galileo Resources Plc (AIM: GLR) has published results from a multi-phase drill programme at its Molefe copper project in Zambia, confirming mineralisation continuity and extending the strike length by approximately 380 metres to an updated estimate of 1,310 metres. The programme, conducted under the terms of a collaboration agreement with Jubilee Metals Group PLC, comprised 23 holes totalling 1,851.5 metres across two distinct objectives. A mine development plan and schedule have been submitted to Jubilee for consideration, targeting an oxide copper reef of approximately one million tonnes at grades of at least 1.30% total copper.

Key Points

  • Galileo Resources Plc (AIM: GLR) operates the Molefe copper project in Zambia in partnership with Jubilee Metals Group PLC
  • 23 drill holes completed — 9 for mineralisation continuity testing and 14 for condemnation purposes — totalling 1,851.5 metres
  • Strike length extended from 930 metres to approximately 1,310 metres; peak intercept of 2.97% TCu over 3.10 metres recorded at MNKDD021
  • Investors will be watching Jubilee's response to the submitted mine development plan and any decision on advancing to production

Molefe Drill Programme Confirms Copper Continuity Across 23 Holes and 1,851.5 Metres

The completed drill programme at Molefe comprised two distinct components. Nine holes totalling 552.6 metres were drilled to test mineralisation continuity and tenor along the eastern limb of the ore zone, while 14 condemnation holes totalling 1,298.9 metres evaluated areas earmarked for future infrastructure including waste dumps, a processing plant, and tailings facilities. The announcement states that condemnation drilling successfully identified areas within the licence boundary suitable for these infrastructure elements, enabling detailed planning to advance. Galileo noted the drilling results, combined with in-pit sampling, are specifically focused on supporting a mining schedule and do not constitute a resource estimate under any recognised standard.

Peak Intercepts at MNKDD021, MNKDD027 and MNKDD029 Underpin Ore Zone Assessment

Among the highlighted mineralised intercepts, borehole MNKDD021 returned 2.97% total copper over 3.10 metres, MNKDD027 returned 1.24% total copper over 10.5 metres, and MNKDD029 returned 1.51% total copper over 12.5 metres. Additional intercepts included MNKDD024 at 0.87% total copper over 13.0 metres and MNKDD033 at 0.84% total copper over 11.1 metres. The technical information was reviewed, verified, and approved by Colin Bird, a Chartered Engineer and Fellow of the Institute of Materials, Minerals and Mining with more than 40 years of hard rock mining experience, serving as the announcement's qualified person.

Mine Schedule Submitted to Jubilee Targets One Million Tonnes of Oxide Copper Reef

Galileo has provided Jubilee Metals with a mine development plan and schedule supported by the condemnation and continuity drilling outcomes. The schedule targets an oxide copper reef of approximately one million tonnes at grades of at least 1.30% total copper. This includes approximately 240,000 tonnes at 1.45% total copper within the immediately targeted pits 2 and 3. The announcement notes that the eastern extension of the mineralisation, which contributed to the updated 1,310-metre strike length estimate, has not been incorporated into the current mine schedule, potentially representing additional optionality for future development consideration.