GreenRoc Strategic Materials Plc (AIM: GROC), an AIM-quoted developer of critical mineral projects in Greenland, has provided an operational update confirming three significant milestones across its Amitsoq Graphite Project and active anode material pilot plant in Denmark. The purification line equipment for its Hørsholm pilot plant departed Florida on 12 August 2026, Phase III drilling at Amitsoq has returned substantial graphite intersections from all three completed holes, and collaboration with the European Investment Bank InvestEU Advisory Hub is now under way. The update signals meaningful near-term progress towards a Pre-Feasibility Study and battery-grade graphite production in Europe.

Key Points

  • GreenRoc Strategic Materials Plc (AIM: GROC) — AIM-quoted UK developer of the Amitsoq Graphite Project in Greenland
  • Purification line equipment shipped from Sepor Inc's Florida premises on 12 August 2026, expected to arrive in Hørsholm, Denmark by end of September 2026
  • Phase III drilling has completed three holes, all returning significant graphite ore intersections, including a 21.3m true thickness in hole AM_DD_043
  • Investors should watch for completion of Phase III drilling, initiation of the Pre-Feasibility Study, and further EIB market analysis outputs

Purification Line Equipment Departs Florida for GreenRoc's Hørsholm Pilot Plant

On 12 August 2026, most of the equipment required for the purification line at GreenRoc's active anode material pilot plant was packed into containers at Sepor Inc's premises near Fort Lauderdale, Florida, for shipment to Denmark. The consignment includes reactor tanks, rinse tanks, slurry pumps, baking ovens, a fume scrubber, drying ovens, and dispenser tanks for chemicals. The equipment was developed by Sepor, founded in 1953, in accordance with instructions from GreenRoc and its technical advisory partner, ProGraphite GmbH. Delivery to Hørsholm is expected by the end of September 2026, representing a tangible step towards producing battery-grade active anode material in Europe.

Phase III Drilling at Amitsoq Returns Significant Intersections Extending Known Mineralisation

Three drill holes have now been completed during Phase III drilling at the Amitsoq deposit, all of which have returned significant graphite ore intersections. Hole AM_DD_039 intercepted the Lower Graphite Layer with 9.7m true thickness. AM_DD_040 intercepted the Upper Graphite Layer at approximately 36m depth with 4.8m true thickness and the Lower Graphite Layer at approximately 93m depth with 9.2m true thickness. The third hole, AM_DD_043, intercepted the Lower Graphite Layer at approximately 137m depth with a true thickness of 21.3m. The announcement states these results extend known mineralisation further north from drilling conducted in 2021 and 2022, reinforcing the scale of the deposit, which holds a combined JORC Resource of 23.05 million tonnes at an average grade of 20.41% graphite.

EIB InvestEU Advisory Hub Delivers First Draft Market Analysis for Integrated Mine-to-AAM Business Case

Following an agreement announced on 17 June 2026 and an initial meeting held in late July 2026, the European Investment Bank has presented GreenRoc with a first draft market analysis and a draft economic model covering the integrated graphite mine and active anode material processing plant business case. The model draws partly on GreenRoc's existing Preliminary Economic Assessment for Amitsoq and the Pre-Feasibility Study for the AAM plant, supplemented with updated market pricing data for graphite concentrate and graphite AAM products. The Amitsoq Project was designated an EU Strategic Project in June 2025 and holds a 30-year Exploitation Licence granted by the Government of Greenland in December 2025.

Pre-Feasibility Study Initiation and September Equipment Delivery Among Near-Term Catalysts

The announcement states that geotechnical measurements at Amitsoq are proving more time-consuming than anticipated, though the field team is confident all drilling and data acquisition needed to initiate the Pre-Feasibility Study later in 2026 will be completed. Investors may be watching for confirmation of full Phase III drilling completion, the formal launch of the PFS, and delivery and commissioning of the purification line at Hørsholm. GreenRoc holds a EUR 5.2 million loan facility from the Export and Investment Fund of Denmark and up to DKK 10,448,826 (approximately £1.2 million) in Danish government EUDP funding to support its ongoing work programme.