Gresham House Energy Storage Fund plc (LSE: GRID), the UK's largest listed fund investing in utility-scale battery energy storage systems, has published a trading update ahead of its half-year results to 30 June 2026. The company reported a 15.8% increase in NAV per share to 131.30p, driven primarily by the revaluation of 397MW of projects now under construction. Portfolio revenues rose 9.5% year-on-year to £34.7 million, while EBITDA climbed 14.5% to £23.5 million, with half-year results due on 23 September 2026.
Key Points
- Gresham House Energy Storage Fund plc (LSE: GRID)
- NAV per share rose 15.8% to 131.30p as of 30 June 2026, up from 113.34p at 31 December 2025
- H1 2026 portfolio revenues of £34.7mn and EBITDA of £23.5mn; three projects totalling 397MW now in construction; 777MW additionally conditionally acquired
- Investors will be watching the Ofgem final cap and floor award for Ocker Hill, expected Autumn 2026, and the 23 September interim results publication
NAV Jumps 15.8% to 131.30p as 397MW Pipeline Projects Move to DCF Valuation
The primary driver of GRID's NAV increase was the revaluation of three pipeline projects — Cockenzie, Monets Garden, and Elland 2 — onto a discounted cash flow basis, having previously been held at cost. This revaluation alone contributed 14.33p of the total 17.96p per share NAV increase. An additional 2.34p came from cash generated by the portfolio net of debt costs. The company noted that the remaining 777MW of conditionally acquired pipeline projects will continue to be held at cost until they enter construction, expected in mid to late 2027, representing what the announcement describes as further potential upside to NAV.
Cockenzie, Monets Garden and Elland 2 Reach Financial Close with £141mn Senior Project Finance
The three projects reaching financial close in May 2026 secured £141 million in senior project finance, covering approximately 70% of project costs. The announcement also confirmed that export credit agency-backed facilities — described as the first of their kind in the UK BESS market — were secured to fund half the battery cost for Cockenzie and Monets Garden. Target energisation is H2 2027 for Monets Garden and Elland 2, and H1 2028 for Cockenzie. Strategic joint-venture partner Summit Transition Partners, a joint venture between Sumitomo Corporation and TPK Holdings, acquired 25% stakes in all three projects at a premium to development rights cost.
Growth Plan Equity Requirement Cut Sharply from £300mn to £25mn as EBITDA Target Set at £141mn
GRID's revised Growth Plan, incorporating the 480MW Rayleigh project and the expanded 1,174MW pipeline, targets an annualised EBITDA run rate of £141 million once fully operational — modestly below the previous £150 million target — but requires significantly less equity capital from the company, falling from approximately £300 million to approximately £25 million. Planned augmentations on the existing portfolio have been reduced from 1.5GWh to 350MWh across eight assets in 2026, removing around £180 million of capital expenditure. The Alternative Revenues strategy, which generated £23 per MWh after fees during its trial phase against an expected £5–10 per MWh at scale, is targeting at least 20MW of commercial capacity by end of 2026.
Ofgem's Provisional Cap and Floor Award for 145MW Ocker Hill Project Awaits Final Confirmation
On 26 June 2026, Ofgem provisionally included GRID's Ocker Hill asset in its list of projects set to receive 25-year cap and floor contracts under the UK Government's long-duration energy storage scheme, in a 145MW / 1,160MWh eight-hour configuration. A final award is expected in Autumn 2026. If confirmed, the award would introduce long-term, Government-backed, index-linked revenues into the portfolio — a meaningful development for investors focused on revenue visibility. The 1,174MW of total new projects, if delivered, would more than double GRID's current operational capacity, though construction and energisation timelines carry inherent execution risk.