Invinity Energy Systems plc (AIM: IES), a manufacturer of vanadium flow batteries, has announced that its technology has been selected by Ofgem to progress under Window 1 of the UK Long Duration Energy Storage (LDES) Cap and Floor Scheme, following the regulator's publication of its "minded-to decisions" on 26 June 2026. The inclusion relates to the Frontier Legacy project, a 520 MWh scheme in which Invinity's vanadium flow battery technology is expected to play a significant role alongside zinc-halide battery technology. Ofgem specifically cited the inclusion of Invinity's vanadium flow battery technology as a key Factor in reaching its minded-to decision — a validation the company describes as significant. Investors will be watching progress towards financial close, which the company says it is working to achieve over the coming months, whilst acknowledging that no assurance can be given that it will be reached in the form currently envisaged.
Key Points
- Company: Invinity Energy Systems plc (AIM: IES), a global vanadium flow battery manufacturer
- Ofgem has published "minded-to decisions" for Window 1 of the UK LDES Cap and Floor Scheme, including the Frontier Legacy project which incorporates Invinity's technology
- Frontier Legacy has a total capacity of 520 MWh, expected to be split approximately equally between Invinity's vanadium flow battery technology and zinc-halide battery technology
- Ofgem specifically referenced Invinity's vanadium flow battery technology as a key factor in its minded-to decision
- The company will work with Frontier Power to progress towards financial close; management retains high confidence but no assurance of completion has been given
- Investors should monitor progress towards financial close and any further updates from Ofgem on the Cap and Floor Scheme
Ofgem's Minded-To Decision and What It Means for the Frontier Legacy Project
On 26 June 2026, Ofgem published its "minded-to decisions" for Window 1 of the UK Long Duration Energy Storage Cap and Floor Scheme. Among the projects included was Frontier Legacy, a 520 MWh energy storage scheme in which Invinity's vanadium flow battery technology is expected to feature alongside zinc-halide battery technology. The announcement states that the expected split between the two technologies is approximately equal, though the company did not disclose precise megawatt-hour allocations for each technology within the project.
A minded-to decision from Ofgem represents a significant regulatory milestone. It signals the regulator's intention to support a project under the Cap and Floor framework, which is designed to de-risk Investment in long duration energy storage by providing a floor on revenues and a cap on excessive returns. Whilst a minded-to decision is not the same as a final determination, its publication marks a meaningful step forward for projects seeking to reach financial close under the scheme.
Ofgem's Specific Recognition of Invinity Vanadium Flow Battery Technology
One of the most notable elements of the announcement is Ofgem's specific reference to Invinity's vanadium flow battery technology as a key factor in reaching its minded-to decision for the Frontier Legacy project. Invinity's announcement states that the company views this as "yet another key validation" of its technology and its role in delivering vital long duration energy storage capacity to the UK grid and globally. The regulator's explicit citation of a particular technology provider within a scheme decision is relatively uncommon and may carry weight with investors assessing the commercial credibility of Invinity's offering.
The company has long positioned its vanadium flow battery platform as a technically differentiated product. Unlike lithium-ion batteries, the company states that its Endurium VFBs do not wear out, cannot catch fire, and are engineered for operation over 30 years or more. The regulator's acknowledgement of Invinity's technology within a formal scheme decision process may serve to reinforce those commercial claims in the eyes of potential customers, partners, and investors.
The UK LDES Cap and Floor Scheme: Structure and Strategic Importance
The UK LDES Cap and Floor Scheme is a government-backed mechanism designed to stimulate private investment in long duration energy storage infrastructure. By guaranteeing a minimum Revenue floor and capping upside returns, the scheme aims to reduce the Financial Risk associated with deploying novel storage technologies at scale — a barrier that has historically constrained LDES deployment in the UK. Ofgem administers the scheme, and Window 1 represents the first cohort of projects to progress through the selection process.
Invinity's announcement notes the company's belief that projects specifying its technology represent clear alignment with the UK's Industrial Strategy, given the potential to support domestic Supply chains, enhance energy security, and grow a UK Manufacturing base for long duration energy storage. The company manufactures its batteries in the UK and Canada, positioning it as a domestically relevant supplier at a time when supply chain resilience is a stated policy priority for the UK government.
The Path to Financial Close and Key Conditions Investors Should Understand
Invinity has stated that it will work to support Frontier Power in advancing the Frontier Legacy project towards financial close over the coming months. Chief Executive Officer Jonathan Marren is quoted in the announcement as viewing Ofgem's decision positively, describing it as underlining continued progress for the Business both in the UK and globally. However, investors should note the accompanying caveat: the company has explicitly stated that, whilst management retains a high degree of confidence, there can be no assurance that financial close will be achieved in the form currently envisaged, if at all.
This is a standard but important disclosure for a project at this stage. A minded-to decision from Ofgem does not constitute a binding commitment, and financial close involves a range of further conditions, including project financing, contractual agreements, and final regulatory confirmation. The company did not disclose a specific target date for financial close, nor did it provide details of the anticipated contract value or revenue contribution to Invinity should the project proceed as currently envisaged.
Global LDES Market Context and Invinity's Growth Outlook
In the announcement, Jonathan Marren provides commentary on the global stationary energy storage market, citing figures from the Benchmark Q2 2026 Battery Energy Stationary Storage Forecast. According to those figures, 393 GWh of grid-scale energy storage is expected to be installed globally in 2026, representing year-on-year growth of 49%. Of that total, 8.3 GWh — equivalent to approximately 2% — is expected in the UK, whilst 58 GWh (15%) is forecast for the United States and 19 GWh (5%) for Europe excluding the UK.
The figures provide context for understanding the relative scale of the UK LDES opportunity within a rapidly expanding global market. Invinity's CEO describes the cap and floor programme as "a significant national step" in the context of this growth environment. The company also states that it is seeing what it describes as significant traction in the UK and global commercial and industrial sectors, as well as the data centre sector, both directly and through industrial partners. The company therefore says it "remains extremely positive about its prospects for growth," though no specific financial guidance or revenue forecasts were provided in the announcement.
Invinity's Technology Positioning Against Competing Storage Solutions
The Frontier Legacy project is notable for combining two distinct battery chemistries — vanadium flow batteries and zinc-halide batteries — within a single 520 MWh project. Invinity's announcement does not comment on the rationale for this combined approach or on the relationship with the zinc-halide technology provider, but the pairing suggests that project developers may be exploring complementary technologies to optimise performance characteristics across different operating profiles.
Invinity describes its vanadium flow battery technology as a "trusted and safer alternative to lithium-ion batteries," emphasising characteristics such as non-flammability, scalability, and longevity. The company's products are described as being designed for heavy-duty, high throughput applications and engineered for a 30-year operating life. These features are particularly relevant in the context of the LDES scheme, which targets storage Assets capable of operating over extended durations — typically four hours or more — to provide grid stability and support renewable energy integration.
Alignment With UK Industrial Strategy and Domestic Manufacturing
Invinity has explicitly linked its participation in the LDES Cap and Floor Scheme to the UK government's Industrial Strategy, stating its belief that projects specifying Invinity technology support domestic supply chains and enhance energy security. The company manufactures its batteries at facilities in the UK and Canada, giving it a credible basis for this claim. At a time when the UK government is seeking to develop resilient domestic manufacturing capacity in strategic sectors, Invinity's positioning may be relevant to policy discussions around procurement and industrial support.
The announcement does not provide details of the specific UK manufacturing facilities involved in the Frontier Legacy project or the anticipated number of jobs or economic output associated with its delivery. However, the company's emphasis on domestic manufacturing aligns with a broader industry narrative around the UK's ambition to build a domestic clean energy supply chain, which is increasingly relevant to institutional investors applying environmental, social, and governance criteria to their portfolios.
Inside Information Designation and Regulatory Disclosure
Invinity has designated the content of this announcement as inside information under the Market Abuse Regulation (EU) No. 596/2014 as retained in UK law via the European Union (Withdrawal) Act 2018. This designation indicates that the board considers the Ofgem minded-to decision and its implications for Invinity to be material non-public information that required prompt disclosure to the market. The announcement was published on 26 June 2026 via the Regulatory News Service.
The MAR designation underscores the company's view of the commercial significance of the Ofgem decision. Investors and analysts monitoring Invinity's progress will be aware that inside information disclosures of this nature are subject to strict regulatory requirements, and the prompt publication via RNS reflects the company's compliance obligations. The immediate share price impact was not clear from available public information at the time of writing.
Invinity's Broader Commercial Momentum Across C&I and Data Centre Sectors
Beyond the LDES Cap and Floor Scheme, Invinity's CEO highlights what the company describes as significant traction in the commercial and industrial (C&I) and data centre sectors, both directly and through industrial partners. The announcement does not provide specifics on the contracts, partners, or revenue associated with this activity, but the mention alongside the LDES milestone suggests the company is seeking to communicate diversified Demand across multiple market segments.
The data centre sector is of particular interest given the rapid growth in electricity demand associated with artificial intelligence infrastructure and Cloud Computing. Long duration energy storage is increasingly being evaluated as a means of providing backup power and grid services for large, energy-intensive facilities. Invinity's ability to secure traction in this sector, if confirmed through future commercial announcements, could represent a meaningful additional revenue channel alongside grid-scale projects supported by regulatory frameworks such as the LDES Cap and Floor Scheme.
What Investors Should Monitor as the Frontier Legacy Project Advances
For investors in Invinity Energy Systems, the key near-term milestone to watch is progress towards financial close on the Frontier Legacy project. The company has provided no specific timeline beyond "the coming months," and has been transparent that there is no guarantee financial close will be achieved in the form currently envisaged. Any further communications from Ofgem regarding the Cap and Floor Scheme, including a move from minded-to decision to final determination, would represent a significant update.
Investors may also wish to monitor whether Invinity announces additional projects or partnerships arising from the increased visibility that comes with Ofgem's explicit recognition of its technology. The company's commentary on global market growth and its traction in the C&I and data centre sectors suggests management is seeking to broaden its commercial pipeline beyond the LDES scheme. Future trading updates, contract announcements, or progress reports on financial close will be watched closely by the market as the company works to translate regulatory validation into commercial revenue.




Please wait processing your request...