Kavango Resources plc (LSE: KAV, VFEX: KAV.VX), the Southern Africa-focused metals exploration and gold development company, has announced the successful energisation of a new one megavolt-ampere transformer at its Hillside Gold Project in Zimbabwe. The upgrade, completed on 19 November 2026, increases total installed transformer capacity from 250kVA to 1.25MVA — a fivefold increase — and will supply grid electricity directly to the site. The development is expected to improve power supply stability and reduce energy costs, supporting the company's broader strategy to scale gold processing operations at Hillside.
Key Points
- Kavango Resources plc (LSE: KAV, VFEX: KAV.VX)
- New 1MVA transformer successfully energised on 19 November 2026, raising total installed transformer capacity at Hillside from 250kVA to 1.25MVA
- Grid electricity will now supply underground operations and the proof-of-concept carbon-in-leach plant; 500kVA backup generation provides additional resilience
- Investors should watch for further updates on the expansion of gold processing capacity following the commissioning of the 50 tonne per day plant announced on 2 November 2026
Fivefold Transformer Capacity Increase Powers Hillside's Underground Operations and CIL Plant
The energisation of the new 1MVA transformer on 19 November 2026 raises Hillside's total installed transformer capacity from 250kVA to 1.25MVA. The upgraded infrastructure connects the Hillside Gold Project directly to Zimbabwe's national grid, supplying electricity to both underground operations and the proof-of-concept carbon-in-leach plant on site. Chief Executive Officer Jasper Musadaidzwa stated that the fivefold increase in capacity will enable direct grid supply, with expected improvements in power stability and reductions in energy costs. The company did not disclose specific cost savings or revised operating cost figures in the announcement.
Zimbabwe's 325 Consecutive Days Without Load Shedding Underpin Grid Reliability at Hillside
A notable country-level context supports the timing of this infrastructure investment. As at 10 November 2026, Zimbabwe's Minister of Energy and Power Development reported to Parliament that the country had experienced 325 consecutive days without load shedding due to insufficient power supply. This backdrop strengthens the rationale for Kavango's decision to increase reliance on grid electricity at Hillside. Separately, the company retains 500kVA of backup generation capacity to maintain operational continuity during any interruptions to the national grid supply, providing an additional layer of resilience for processing activities.
Power Upgrade Follows Commissioning of Hillside's 50 Tonne Per Day Gold Processing Plant
The transformer energisation forms part of a broader infrastructure buildout at Hillside. On 2 November 2026, Kavango announced the successful commissioning of a 50 tonne per day gold processing plant at the project. The additional electrical capacity is intended to support the company's stated strategy of developing efficient and scalable gold production operations, with the announcement indicating plans to expand processing capacity further. The company has confirmed it will provide further updates as development progresses, though specific timelines, capital expenditure commitments, and production targets were not disclosed in this announcement.
Operational Risks Remain as Kavango Pursues Larger-Scale Production at Hillside
Whilst the infrastructure milestone is operationally significant, the announcement sets out a range of risks that investors should consider. These include the reliability and cost of grid electricity supply in Zimbabwe, changes in electricity tariffs, technical and operational risk during the ramp-up of processing facilities, funding risk, and commodity price exposure. Political, regulatory, and country risk specific to Zimbabwe, as well as foreign exchange and currency convertibility risk, are also cited. The company notes that no assurance can be given that the anticipated benefits of the power upgrade, including improved stability or reduced unit operating costs, will be realised.