Mendell Helium plc (LON: MDH), the AIM-quoted helium production company operating in Kansas, USA, has published a detailed operations update covering its Rost 1-26 and Rost 2-26 production wells and the Brobee saltwater disposal asset in Fort Dodge. The announcement outlines a series of infrastructure upgrades, equipment deliveries, and well interventions completed across all three assets. Chief Executive Nick Tulloch confirmed that, subject to completion of utility grid connection, de-watering operations at both Rost wells are expected to commence by mid-August 2026, positioning the company to move toward full dual-well gas production.

Key Points

  • Mendell Helium plc (LON: MDH) — helium producer operating in Fort Dodge, Kansas, through wholly owned subsidiary M3 Helium
  • De-watering at both Rost 1-26 and Rost 2-26 expected to commence by mid-August 2026, subject to final grid connection and power energisation
  • Wellhead helium concentrations at Rost 1-26 remain stable at approximately 5.1%; Rost 1-26 fluid handling capacity upgraded to up to 900 barrels of water per day
  • Investors will be watching for confirmation of utility connection completion, commencement of de-watering, and early gas flow rates from Rost 2-26

Brobee Saltwater Disposal Well Exceeds Expectations at 10,000 bpd Permitted Capacity

The Brobee disposal well delivered a standout result during operational testing, operating under a maximum surface vacuum of 30 inHg — confirming superior permeability within the targeted Arbuckle formation and sub-hydrostatic formation pressure. This means fluid is drawn into the formation by pure gravity flow, eliminating the need for active surface pumping pressure previously required by the company. The removal of surface pumping is expected to reduce power consumption, lower equipment wear, and cut operating costs per barrel. Permitted for up to 10,000 barrels of water per day, Brobee is designed to service both Rost wells and carry scalable capacity for future regional development wells across the Fort Dodge area.

Rost 1-26 Perforations Doubled and Surface Pump Upgraded to 640 Unit for 900 bpd Capacity

At Rost 1-26, the technical team doubled the open perforation interval to 4 feet, a measure intended to increase fluid production rates and subsequently accelerate gas liberation from the reservoir. The existing 320 surface pumping unit, capable of handling 400–500 barrels of water per day, has been demobilised and replaced with a larger 640 unit scheduled for imminent installation, raising total surface water handling capacity to up to 900 barrels per day. A sand-tolerant pump assembly has also been installed to extend operational pump life by 6–12 months. All workover activity was completed using an on-site rig, avoiding additional mobilisation and demobilisation costs. Wellhead helium concentrations remain stable at approximately 5.1%.

Halliburton ESP and High-Capacity Power Infrastructure Delivered to Rost 2-26 Ahead of De-Watering

For Rost 2-26, Mendell Helium has finalised and delivered to site an optimised Halliburton Electrical Submersible Pump and a high-specification Variable Frequency Drive unit featuring 24/7 remote digital telemetry. The system allows the engineering team to monitor real-time downhole conditions — including pressure, temperature, and motor performance — and adjust parameters remotely without site intervention. A new high-capacity electrical supply and transformer are currently being installed by the local utility provider to power the ESP, surface processing, and helium purification facilities. Downhole installation and de-watering are scheduled to commence immediately following grid connection, with both Rost wells targeted to begin de-watering by mid-August 2026.

Surface Purification Improvements Planned as Mendell Helium Targets Higher-Grade Helium Delivery

Alongside production ramp-up, the company states it is continuing to assess improvements to its surface operations with the goal of removing waste products — primarily nitrogen and hydrocarbons — from the gas stream to deliver a more purified helium gas product to its offtaker. The announcement states this work will be ongoing for several months and will be carried out in conjunction with production development at the Rost wells. M3 Helium currently uses two leased tube trailers for deliveries to its offtaker. The company also holds additional leases in the Fort Dodge area capable of supporting up to eight new production wells, as well as interests in five producing wells within the Hugoton gas field in south-western Kansas.