Oriole Resources PLC (AIM: ORR), the AIM-quoted gold exploration and development company focused on Central and West Africa, has announced positive metallurgical testwork results for its 50%-owned Bibemi gold project in north-eastern Cameroon. Testing conducted by ALS Ltd. Australia confirmed that ultra-fine grinding of flotation concentrate delivers overall gold recoveries broadly comparable to the pressure oxidation route assumed in the current Preliminary Economic Assessment, while offering meaningful operational advantages. An updated PEA incorporating this alternative flowsheet is anticipated later this quarter, making the update a near-term catalyst investors may be watching closely.
Key Points
- Oriole Resources PLC (AIM: ORR) is an AIM-quoted gold exploration and development company operating in Cameroon and Senegal
- Metallurgical testwork by ALS Ltd. Australia confirmed ultra-fine grinding as a viable alternative to pressure oxidation at the 50%-owned Bibemi gold project
- Oxide samples returned greater than 90% gold recovery after 24 hours of leaching; ultra-fine grinding of sulphide flotation concentrate delivered downstream recoveries of 94–98%
- An updated Preliminary Economic Assessment including the ultra-fine grind flowsheet as an option is anticipated later this quarter
Bibemi Oxide and Sulphide Testwork Delivers 90%-Plus Gold Recovery at ALS Perth
The testwork, completed at ALS Perth, used two shallow near-surface oxide samples and two sulphide samples from the 177km² Bibemi orogenic gold project. Oxide samples confirmed amenability to conventional cyanidation, achieving greater than 90% gold recovery after 24 hours using a 75-micron grind — replicating results from earlier, smaller-scale work. Flotation testwork on the sulphide samples at a 75-micron grind returned 81% and 82% gold respectively, consistent with prior SGS South Africa results. Subsequent ultra-fine grinding of the flotation concentrate to 20 and 10 microns, followed by cyanidation, produced downstream gold recoveries of between 94% and 98% after 72 hours.
Ultra-Fine Grinding Offers Operational Advantages Over Pressure Oxidation at Bibemi
The announcement states that the ultra-fine grind flowsheet delivers overall gold recovery broadly comparable to the pressure oxidation route previously assumed in the existing PEA, which itself assumed 85% gold recovery. However, the alternative flowsheet carries distinct operational benefits: it simplifies the process plant, enabling faster project execution, commissioning and ramp-up; reduces the management and supervisory skills required; eliminates high-pressure equipment, lowering safety risk; and removes the need for specialised autoclave construction materials — a particular advantage given Bibemi's small-scale design targeting an optimised open-pit scenario of 89,000 ounces of gold over a seven-year mine life.
Stirling Process Engineering Trade-Off Study to Feed Bibemi's Updated PEA This Quarter
Stirling Process Engineering Ltd has been engaged to produce a detailed trade-off study examining capital and operating costs for the ultra-fine grind flowsheet. The company's provisional indication is that those costs will be broadly comparable to the existing POX-based flowsheet, though the final figures will be confirmed through Stirling's report. Once received, these findings will be incorporated into an updated PEA for Bibemi, with publication anticipated later this quarter. The Bibemi project holds a JORC Mineral Resource Estimate of 6.96 million tonnes at 2.06 grammes per tonne gold for 460,000 ounces of contained gold, of which 100,000 ounces is classified as Indicated.
Bibemi Exploitation Licence Application Progresses Alongside Flowsheet Optimisation
Oriole Resources has already submitted an Exploitation Licence Application for Bibemi, envisaging a small-scale open-pit mine targeting approximately 10,000 ounces of gold average annual production. BCM International completed its earn-in to acquire a 50% interest in Bibemi in November 2025 by meeting certain payment conditions, including spending US$4 million on exploration. The project features mineralisation across four main prospects — Bakassi Zone 1, Bakassi Zone 2, Lawa West and Lawa East — within an approximately 12-kilometre-long mineralised hydrothermal system. An additional Exploration Target of between 3.0 and 5.0 million tonnes at a grade of 1.50 to 2.50 grammes per tonne gold has also been reported across the project.