Pan African Resources PLC (LSE/ASX: PAF; JSE: PAN) announced on 11 September 2026 that it has successfully completed the Definitive Feasibility Study (DFS) for its Soweto Tailings Retreatment (STR) project on the West Rand of Gauteng, South Africa. The STR project encompasses approximately 108 million tonnes of tailings at 0.28g/t, containing roughly 0.98 million ounces of gold acquired through the Mintails transaction. The DFS outlines a 600,000 tonnes per month retreatment operation with a 15-year project life, delivering an internal rate of return of approximately 29.55% at a gold price of US$3,550 per ounce. A Final Investment Decision is targeted for December 2026, subject to board approval, financing, and statutory authorisations.

Key Points

  • Pan African Resources PLC (LSE/ASX: PAF; JSE: PAN)
  • DFS completed for the Soweto Tailings Retreatment project adjacent to the existing Mogale Tailings Retreatment complex in Gauteng, South Africa
  • Post-tax NPV of approximately ZAR1.85 billion (US$109 million); project capital estimated at ZAR3.68 billion (US$216 million); LOM AISC of approximately US$1,750–1,800/oz; payback period of approximately three years post-commissioning
  • Investors should watch for receipt of principal environmental authorisations in FY27 and the targeted December 2026 Final Investment Decision

STR Project Mineral Reserves and 600ktpm Processing Circuit Design

The STR project is located adjacent to Pan African's existing Mogale Tailings Retreatment (MTR) operations and covers the Soweto Cluster tailings storage facilities acquired as part of the Mintails transaction. The project holds Mineral Reserves of approximately 108 million tonnes at 0.28g/t, containing approximately 0.98 million ounces of gold. The DFS evaluated constructing a dedicated 600,000 tonnes per month retreatment circuit, incorporating hydraulic mining infrastructure, pumping stations, and approximately 18 kilometres of overland slurry and water pipelines, alongside a new GISTM-compliant tailings deposition facility.

Capital Cost Reduced to ZAR3.68 Billion Following Value Engineering Programme

A comprehensive value engineering programme conducted after the base case DFS identified capital savings of approximately ZAR718 million, reducing the estimated project capital from approximately ZAR4.40 billion to ZAR3.68 billion (US$216 million at ZAR17.00 to the US dollar) while maintaining throughput and operational performance targets. The project has been designed to leverage MTR's existing elution, carbon regeneration, electrowinning, and smelting infrastructure, materially reducing capital intensity relative to a standalone development. At a gold price of US$3,550 per ounce, the project returns a post-tax NPV of approximately ZAR1.85 billion and a real ungeared IRR of approximately 29.55%.

Annual Production of 35,000–40,000oz from STR Lifting MTR Complex Toward 100,000oz Peak

The STR project is expected to produce between 35,000 and 40,000 ounces of gold annually, contributing to a Life of Mine total of approximately 561,000 ounces over roughly 15 years. Combined with existing MTR output, the announcement states that peak production from the MTR complex could reach approximately 100,000 ounces per year. The LOM all-in sustaining cost is estimated at approximately US$1,750–1,800 per ounce, excluding any savings from renewable energy supply, with a payback period of approximately three years post-commissioning and a construction period of approximately 28 months from the Final Investment Decision.

Environmental Authorisations Expected in FY27 Ahead of Targeted December 2026 FID

Pan African's Environmental Impact Assessment and permitting process is described as well advanced, with pipeline servitude approvals secured and a Water Use Licence application submitted. The company anticipates receipt of principal environmental authorisations during FY27. The Group intends to complete remaining permitting, optimisation, and financing workstreams during FY27, with a Final Investment Decision targeted for December 2026, subject to board approval, project financing, and receipt of required statutory authorisations. CEO Cobus Loots highlighted the project's potential to address historical environmental liabilities on the West Rand alongside delivering production growth.