Phoenix Copper Limited (AIM: PXC; OTCQX ADR: PXCLY), the AIM-quoted USA-focused base and precious metals emerging producer, has published an updated mineral reserve statement for its Empire Open-Pit Mine in Idaho, USA. The 2 November 2026 announcement confirms Proven and Probable reserves of 13.27 million tonnes, representing a 31.49% increase in ore tonnes and a 26.31% rise in copper equivalent metal compared to the company's inaugural May 2024 reserve estimate. The update provides a revised foundation for an ongoing Pre-Feasibility Study refresh, which investors will be watching closely as Phoenix advances towards production.
Key Points
- Phoenix Copper Limited (AIM: PXC; OTCQX ADR: PXCLY)
- Updated Proven and Probable mineral reserves at the Empire Open-Pit Mine total 13.27 million tonnes, a 31.49% increase in ore tonnes versus the May 2024 inaugural estimate
- Contained metals: 118,781,100 lbs of copper, 134,600 oz of gold, 5,407,400 oz of silver, equating to 83,959 copper equivalent tonnes
- Investors should watch for the updated Pre-Feasibility Study, which consultants are currently preparing using this revised reserve as its basis
Empire Open-Pit Reserve Grows to 13.27 Million Tonnes Across Proven and Probable Classifications
The updated reserve, estimated by Hardrock Consulting and reported in accordance with NI 43-101 standards, comprises 9.688 million Proven tonnes grading 0.40% copper and 3.588 million Probable tonnes grading 0.41% copper. Combined, the Proven and Probable categories return an average grade of 0.41% copper, 0.32 grammes per tonne gold, and 12.67 grammes per tonne silver, at a Net Smelter Return cut-off of $19.83 per tonne. The Empire Mine is located in the Alder Creek mining district near Mackay, Idaho, where Phoenix holds an 80% ownership stake across an 8,434-acre land package.
26.31% Increase in Copper Equivalent Metal Compared to May 2024 Inaugural Reserve
Chief Executive Officer Ryan McDermott stated that the 2026 update represents a 31.49% increase in ore tonnes and a 26.31% increase in copper equivalent metal relative to the May 2024 inaugural mineral reserve, which was the company's first formal reserve declaration at Empire. The disclosure suggests meaningful resource growth from continued drilling and geological evaluation since Phoenix began extensive drilling initiatives in 2017. The company did not disclose updated project capital cost estimates or production schedule revisions in this announcement, with those details expected to emerge through the forthcoming updated Pre-Feasibility Study.
Consultants Preparing Updated Pre-Feasibility Study Using Revised Empire Reserve
The announcement states that the company's consultants are currently updating the 2024 Pre-Feasibility Study using the revised mineral reserve as its basis. The updated PFS will be published in due course, though no specific publication date was given. The technical content of the announcement has been reviewed and verified by Dennis Thomas, a chartered mining engineer from the Camborne School of Mines and co-founder of Phoenix Copper, acting as Qualified Person under the AIM Rules. Investors may be watching the PFS update for revised economics, including any changes to projected operating costs, capital requirements, or mine life.
Phoenix Copper's Broader Idaho Asset Base and ESG Commitments
Beyond the Empire Mine, Phoenix's Idaho holdings include the Horseshoe, White Knob, Blue Bird, and Red Star Mines, as well as the Navarre Creek gold exploration project first drilled in 2023. The company also owns two cobalt properties along the Idaho Cobalt Belt, one of which is subject to an Earn-In Agreement with Toronto-based Electra Battery Materials. Phoenix has recently published its inaugural Sustainability Report and maintains an ESG & Sustainability Committee, reflecting commitments the company states go beyond minimum legal environmental standards — a factor that may carry weight as permitting processes advance.



Please wait processing your request...