Phoenix Copper Limited (AIM: PXC; OTCQX ADR: PXCLY) has published an updated Pre-Feasibility Study (PFS) for its proposed Empire Open-Pit copper, gold, and silver mine in Idaho, USA, reporting materially improved project economics compared with the 2024 study. The 2026 PFS presents two scenarios — a base case using new equipment and a used equipment case — both calculated using three-year trailing average metal prices. The update extends the mine life from eight years to 10.5 years and increases mineral reserves tonnage by 31.49%, metrics that investors in the AIM-listed base and precious metals company are likely to monitor closely.
Key Points
- Phoenix Copper Limited (AIM: PXC; OTCQX ADR: PXCLY) is an AIM-quoted USA-focused base and precious metals developer.
- The updated 2026 PFS for the Empire Open-Pit Mine in Idaho delivers a 38.8% increase in NPV, a 12.9% rise in IRR, and a 41.2% increase in cumulative net cashflow versus the 2024 PFS.
- Pre-tax NPV at 7.5% reaches US$98.36m (base case) or US$121.94m (used equipment case); mine life extended to 10.5 years processing 13.27 million tonnes of ore.
- Investors should watch progress toward final design engineering and submission of a Plan of Operations to the permitting authority as the next key milestones.
Empire Open-Pit PFS Base Case and Used Equipment Scenarios Compared
The 2026 PFS evaluates two distinct capital scenarios for the Empire Mine, located in the historic Alder Creek mining district near Mackay, Idaho, in which Phoenix holds an 80% ownership stake. The base case, assuming new equipment and an 18% capital contingency, produces a pre-tax NPV of US$98.36m, an IRR of 35.3%, and cumulative net cashflow of US$190m with a payback period of 1.88 years. The used equipment case, reflecting the company's existing procurement strategy and a 15% contingency, improves those figures to a pre-tax NPV of US$121.94m, an IRR of 52.40%, cumulative net cashflow of US$216.08m, and a payback period of 1.32 years, with initial capital reduced to US$71.65m versus US$98.41m for the new equipment scenario.
Life-of-Mine Production Increases Across Copper, Gold, and Silver
The updated study projects payable life-of-mine production of 96.8 million pounds of copper, representing an 8.6% increase on the 2024 PFS figure of 89.12 million pounds. Gold payable production rises by 30% to 52,200 ounces, while silver increases by 16.5% to 2.05 million ounces. The Empire deposit's proven and probable reserves stand at 13.27 million tonnes containing 118,781,100 pounds of copper, 134,600 ounces of gold, and 5,407,400 ounces of silver. Revenue is estimated at 65% from copper, 23% from gold, and 12% from silver, with the processing plan combining a mill and flotation circuit with a cementation circuit.
Metal Price Sensitivity Highlights Downside Risk at Lower Commodity Prices
The sensitivity analysis included in the announcement illustrates a range of outcomes tied to commodity price movements. At the base case prices of $4.75 per pound copper, $3,175 per ounce gold, and $41.75 per ounce silver, the after-tax NPV at 7.5% is $83.40m. The announcement notes that current metal prices have been approximately 30% higher than the base case, which the sensitivity table indicates would yield an after-tax NPV of $190m. Conversely, at a copper price of $3.33 per pound, the project produces a negative pre-tax NPV, underscoring the deposit's exposure to commodity price volatility as a material project-level risk.
Permitting and Final Engineering Are Phoenix Copper's Next Development Steps
Chief Executive Officer Ryan McDermott confirmed in the announcement that the company intends to continue utilising good-condition used equipment, consistent with purchases already made, including used ball mills, tailings filtration units, and assay laboratory equipment. The technical information was reviewed and verified by Qualified Person Dennis Thomas, a chartered mining engineer from the Camborne School of Mines. McDermott stated the next step is to complete final design engineering — encompassing metallurgical recovery enhancement and process design — before rolling the information into a Plan of Operations for submission to the relevant permitting authority.