Prospex Energy PLC (AIM: PXEN), the AIM-quoted European gas and power Investment company, has announced that its operator, Po Valley Operations Pty Limited, filed an Environmental Impact Assessment with Italy's Ministry of Environment and Energy Security on 26 June 2026, marking a significant regulatory milestone for the proposed four-well development programme at the Selva Malvezzi production concession in northern Italy. The filing covers plans to drill, develop and commission four new wells within the Po Valley Basin concession, where Prospex holds a 37% working interest. The development targets material gas resources at the concession and, if approved, could see the ambitious drilling programme commence in 2027, with potential benefits for regional energy security in Emilia Romagna. Investors are watching closely as the EIA filing represents a key step on the pathway towards unlocking what the company describes as the significant gas potential of the Selva Malvezzi concession.

Key Points

  • Prospex Energy PLC (AIM: PXEN) — AIM-quoted European gas and power investment company
  • Operator Po Valley Operations Pty Limited filed an Environmental Impact Assessment with Italy's Ministry of Environment and Energy Security (MASE) on 26 June 2026
  • EIA covers a proposed four-well drilling, development and commissioning programme at the Selva Malvezzi production concession in the Po Valley Basin, northern Italy
  • Prospex holds a 37% working interest; Po Valley Operations Pty Limited holds 63%
  • Existing Podere Maiar 1 well has been in continuous production for three years at approximately 80,000 Scm/day since July 2023
  • 3D seismic data processing across approximately 140 square kilometres expected to complete in July 2026, with interpretation commencing immediately thereafter
  • Concession holds independently verified 2P gross reserves of 13.4 Bcf (5.0 Bcf net to Prospex), gross 2C Contingent Resources of 14.1 Bcf (5.2 Bcf net), and 88.2 Bcf gross Best Estimate Prospective Resources (un-risked)
  • Investors should watch for Ministry approval of the EIA and progress on seismic interpretation, which will inform the drilling programme

EIA Filing at MASE: What the Regulatory Submission Covers

On 26 June 2026, Po Valley Operations Pty Limited — a Wholly Owned Subsidiary of ASX-listed Po Valley Energy Limited and the operator of the Selva Malvezzi production concession — formally lodged an Environmental Impact Assessment with Italy's Ministry of Environment and Energy Security, known by its Italian acronym MASE. The filing is a statutory requirement under Italian regulatory procedure and represents the primary formal gateway through which the proposed development programme must pass before any new drilling activity can be sanctioned.

The EIA covers the full scope of the four-well project: drilling, development and commissioning of four new wells within the Selva Malvezzi Production Concession. According to the company's announcement, the proposed wells are situated in relatively close proximity to the existing Podere Maiar 1 well. The Ministry will now assess the submission, and approval would clear the way for the next phase of operational activity. Prospex's chief executive, Tom Reynolds, stated in the announcement that the quality and comprehensiveness of the submission should allow the Ministry to assess the suitability of these projects promptly, though no formal timeline for regulatory determination has been disclosed.

Prospex's 37% Stake and the Joint Venture Structure at Selva Malvezzi

Prospex Energy holds a 37% working interest in the Selva Malvezzi Production Concession, structured through two wholly owned subsidiaries: PXOG Marshall Ltd, which holds 17% of the licence, and UOG Italia Srl, which holds 20%. The remaining 63% working interest is held by Po Valley Operations Pty Limited, which also acts as the concession operator. This joint venture structure means Prospex participates in the Economics of any development in proportion to its working interest but is not responsible for day-to-day operational decisions.

The announcement notes that Prospex's update follows a separate disclosure by Po Valley Energy Limited on the ASX, underlining the dual-listed nature of the broader project group and the fact that material operational developments are communicated across both exchanges. For investors in Prospex specifically, the company's 37% share of any future production uplift from the four-well programme would represent a meaningful addition to the company's existing Revenue stream, which currently flows from the producing Podere Maiar 1 well at approximately 80,000 standard cubic metres per day.

Three Years of Continuous Production at Podere Maiar 1 Provides Operational Context

The Podere Maiar 1 well has been in continuous production since July 2023, now representing three years of operational history at the Selva Malvezzi concession. The announcement states that the well produces at approximately 80,000 standard cubic metres per day, providing an established baseline of gas output that demonstrates the commercial viability of the concession's reservoir. This production record is material context for the four-well programme, as it validates the geological model underpinning the broader development thesis.

The Podere Maiar 1 well was originally completed in December 2017, when it successfully identified a commercial gas accumulation up-dip of previous wells on the Selva field. The concession was formally granted production status at first gas in July 2023, at which point it was converted from the Podere Gallina Licence into the Selva Malvezzi Production Concession. The existence of a producing well connected to the SNAM national pipeline network, which the announcement states is located in close proximity to the concession, provides existing infrastructure that could be utilised by any additional wells brought into production under the four-well programme.

Scale of the Gas Resource Base Underpinning the Four-Well Development Programme

The independently verified resource base at Selva Malvezzi is substantial in the context of a company of Prospex's scale. According to the company's announcement, the concession holds gross 2P proven reserves of 13.4 billion standard cubic feet, of which 5.0 Bcf is net to Prospex at its 37% working interest. These figures were prepared by CGG Services (UK) Limited in a Competent Person's Report dated July 2022.

Beyond the 2P reserves, the concession also holds gross Contingent 2C Resources of 14.1 Bcf (5.2 Bcf net to Prospex) and a further 88.2 Bcf of gross Best Estimate Prospective Resources on an un-risked basis, representing 32.6 Bcf net to Prospex. The prospective resource figure is particularly significant as it represents the upside case that the four-well programme and the concurrent 3D seismic interpretation are designed to evaluate and de-risk. Investors should note that prospective resources carry inherent geological risk and are not equivalent in certainty to proven reserves.

3D Seismic Processing to Deliver Subsurface Model for Drilling Planning

Alongside the EIA filing, the announcement provides an update on the ongoing 3D seismic data processing programme. Processing of the 3D seismic data, which covers approximately 140 square kilometres across the concession area, is expected to be completed during July 2026. Interpretation work is stated to commence immediately upon completion of processing, with the objective of producing a high-resolution, three-dimensional subsurface model.

This subsurface model is described in the announcement as the technical foundation that will inform the drilling programme once Ministry approval for the EIA has been received. The sequencing of these two workstreams — regulatory approval and subsurface interpretation — means that both processes are being advanced in parallel, which could reduce the overall timeline between EIA approval and the commencement of drilling. The announcement indicates the company anticipates the drilling programme could begin in 2027, subject to Ministry approval being granted.

Energy Security Rationale and the SNAM Pipeline Connection

The announcement explicitly frames the Selva Malvezzi development within the context of European energy security, stating that a successful development connected to the SNAM national pipeline network would contribute to the energy security of the Emilia Romagna region of Italy. This framing is consistent with a broader European regulatory and political environment that has placed renewed emphasis on domestic gas production as a means of reducing dependence on imported energy following the disruptions to European gas markets in recent years.

The proximity of the Selva Malvezzi concession to the SNAM national pipeline is an important commercial advantage. Direct pipeline connectivity removes the need for significant additional infrastructure investment to transport gas to market, which would otherwise represent a material cost and logistical barrier to new well development. The announcement does not provide detailed estimates of connection or development Capital Expenditure, and the company did not disclose these figures in the announcement.

CEO Tom Reynolds Comments on the Significance of the EIA Milestone

In the announcement, Prospex chief executive Tom Reynolds described the EIA filing as the result of months of diligent work by the operator, PVO, and praised the quality of the submission. Reynolds stated that the filing would allow the Ministry to assess the suitability of the projects promptly, and that approval of the EIA would allow Po Valley Energy to begin the ambitious drilling programme in 2027. He also highlighted the benefit to the Emilia Romagna region and to all Stakeholders of the joint venture.

Reynolds further commented that delivery of this milestone takes the company another step closer to delivering the full potential from the Selva Malvezzi concession. It should be noted that these are forward-looking statements contingent on regulatory approval and a range of operational and commercial factors. The company has not provided specific financial guidance in this announcement regarding the potential revenues or cash flows that might arise from a successful four-well development programme, and the company did not disclose this figure in the announcement.

Inside Information Designation and Market Abuse Regulation Compliance

Prospex has designated this announcement as containing inside information for the purposes of Article 7 of the Market Abuse Regulation, as incorporated into UK domestic law through the European Union (Withdrawal) Act 2018. The disclosure has been made in accordance with the company's obligations under Article 17 of MAR, which requires issuers to disclose inside information as soon as possible. This designation underscores the materiality of the EIA filing to the company's overall development plan and its potential significance to the investment case.

The MAR designation is a standard regulatory disclosure mechanism used by AIM-listed companies when announcing information that could have a meaningful impact on an informed investor's decision-making. The immediate share price impact of this announcement was not clear from available public information at the time of publication.

Prospex Energy's Broader European Gas Strategy and Investment Case

Prospex Energy positions itself as an AIM-quoted investing company focused on high-impact onshore and shallow offshore European gas and power projects, with a stated objective of acquiring undervalued projects with multiple value trigger points realisable within 12 months of Acquisition. The company's strategy emphasises rapid scaling of gas production to generate internal revenues that can then be deployed to develop its asset base further. The Selva Malvezzi concession, as the company's primary producing asset, sits at the centre of this strategy.

The filing of the EIA for the four-well programme represents a tangible step towards the expansion of production capacity at Selva Malvezzi beyond the current single-well output. Investors may be watching for further updates on the Ministry's assessment timeline, the outcome of the 3D seismic interpretation expected in the second half of 2026, and any announcements regarding the planning and costing of the 2027 drilling programme. Strand Hanson Limited acts as the company's nominated adviser, VSA Capital Limited as corporate broker, and Hannam & Partners provides additional financial advisory services.

Pathway to the 2027 Drilling Programme: Remaining Steps and Milestones

Following the lodging of the EIA on 26 June 2026, the immediate focus shifts to the Italian Ministry of Environment and Energy Security's review and approval process. The announcement does not specify a formal regulatory timeline for MASE's determination, and the duration of EIA reviews in Italy can vary depending on the complexity of the submission and the Ministry's workload. Investors should treat the 2027 drilling commencement target as conditional upon timely regulatory approval.

In parallel, the completion of 3D seismic processing in July 2026 and the subsequent interpretation phase will provide the technical basis for finalising well locations and the detailed drilling plan. The announcement suggests that the company and its operator are actively managing both regulatory and technical workstreams concurrently to minimise delay. The combination of a lodged EIA, ongoing seismic interpretation, and an established producing well connected to national infrastructure means that, subject to approvals, the four-well programme at Selva Malvezzi appears to be progressing through its pre-drill phase in a structured and orderly manner.