Savannah Resources Plc (AIM: SAV), the developer of Europe's largest spodumene lithium deposit in northern Portugal, has published a pre-construction project update confirming several material milestones. The company has initiated tendering for bulk earthworks and mining contracts, received a critical powerline licence from Portuguese regulator DGEG, and made five new hires including a Project Director with 30 years of industry experience. The update also confirms ongoing offtake discussions, with term-sheets already signed and a second offtake agreement targeted before year end.
Key Points
- Savannah Resources Plc (AIM: SAV) is the sole developer of the Barroso Lithium Project in northern Portugal, classified as a Strategic Project under the European Critical Raw Materials Act.
- Tender packages for bulk earthworks and contract mining have been issued to leading national and international companies, with contractor selections expected in Q1 2027.
- E-REDES has received the DGEG licence to re-route the existing 60kV overhead powerline and build a new 15kV supply line, with Savannah targeting 100% renewable power for the project.
- Investors should watch for the second offtake agreement signing, conclusion of the RECAPE process, and the eventual Final Investment Decision.
Earthworks and Mining Contractor Tenders Issued Ahead of Q1 2027 Selection
Savannah has issued tender packages to a number of leading national and international engineering and contract mining companies for the bulk earthworks and mining contract at the Barroso Lithium Project. The announcement states that contractor representatives are already visiting the site to support preparation of their proposals. The company expects strong interest in the contracts and plans to make its final selections in the first quarter of 2027. This milestone moves the project meaningfully closer to construction-readiness and signals confidence in the project's development timeline, particularly given its Strategic Project status under the European Critical Raw Materials Act.
DGEG Issues Powerline Re-Routing Licence, Enabling Grid Connection Plans
A significant regulatory achievement has been confirmed with E-REDES, Portugal's electricity distribution operator, receiving a licence from DGEG to re-route the existing 60kV overhead powerline that currently crosses the project site and to construct a new 15kV line to supply power from the national grid. The power infrastructure package also includes a switching station, whose licence was previously approved, and a new on-site substation subject to approval under the ongoing RECAPE process. Savannah is targeting 100% renewable electricity supply for the project, noting that approximately 80% of electrical power generated in Portugal in 2025 came from renewable sources, according to Associação de Energias Renováveis.
Five New Recruits Join Barroso Team as Savannah Targets Around 30 Additional Hires
Savannah confirmed five recent hires spanning its technical, finance, communities and HR functions, with all new employees originating from or residing in the project region or northern Portugal. The intake includes a Project Director with 30 years of experience in the global mining industry, who is set to join in December. The company is targeting approximately 30 further roles across mine development, environmental, finance and treasury disciplines. Chief Executive Emanuel Proença stated in the announcement that recruitment is central to the company's progress as it moves towards key upcoming milestones including project finance and a Final Investment Decision.
Offtake Discussions Progress with Second Agreement Targeted Before Year End
The announcement confirms that reciprocal site visits with short-listed potential offtake partners have taken place in recent weeks and that term-sheets have been signed. Savannah is working towards executing an agreement with its second offtake partner before the end of 2026. The Barroso Lithium Project is designed to produce approximately 183,000 tonnes per annum of spodumene concentrate, sufficient to supply battery packs for around half a million electric vehicles annually. Securing offtake agreements remains a critical commercial milestone for the project as the company progresses towards financing and an eventual investment decision. The company did not disclose specific terms of the offtake discussions in the announcement.