Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY; Investegate reference: 0OGK) has announced the award of a substantial contract by Aker BP for the Lyra field development project in the northern North Sea, approximately 44 kilometres from the Gjøa platform offshore Norway. The contract, which Subsea 7 defines as valued between $150 million and $300 million, covers full engineering, procurement, construction and installation (EPCI) of gas lift and production pipelines and associated subsea infrastructure. Offshore operations are scheduled across 2026, 2027 and 2028, with first oil targeted in 2028 — just three years after discovery — making Lyra a fast-track development of notable scale for the Norwegian Continental Shelf.

Key Points

  • Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY; reference: 0OGK) is a global offshore energy services group listed in Luxembourg and Oslo
  • Aker BP has awarded Subsea 7 a substantial EPCI contract for the Lyra field development, formerly known as Kjøttkake, in the North Sea
  • Contract value is between $150 million and $300 million; offshore installation scheduled for 2026–2028 with first oil targeted in 2028
  • Investors should watch progress at Subsea 7's Stavanger engineering office and Vigra spool base as fabrication and offshore mobilisation advance

Lyra Field Scope: Pipe-in-Pipe Pipelines, Gjøa Tie-Back and Subsea 7's EPCI Role

The Lyra field will be tied back to the existing Gjøa platform through the NOVA field infrastructure, reducing the need for standalone topside facilities. Subsea 7's scope encompasses engineering, procurement, construction and installation of gas lift and production pipelines alongside associated subsea infrastructure. The production pipeline will feature a pipe-in-pipe design, a technically demanding configuration typically used to preserve flow assurance in deepwater or long-distance tie-back applications. Offshore installation activities will be executed using vessels drawn from Subsea 7's own fleet, giving the company control over a key execution variable and potentially supporting schedule certainty across the multi-year programme.

Stavanger Engineering and Vigra Spool Base Central to Lyra Delivery

Project management and engineering activities commenced immediately at Subsea 7's office in Stavanger, Norway, following the contract announcement. Pipeline fabrication will take place at the company's dedicated spool base at Vigra, Norway, an established facility that supports the group's broader North Sea pipeline business. To enable the accelerated three-year development schedule, Subsea 7 received a pre-commitment for critical long-lead items in December 2025, ahead of formal contract award. This early procurement commitment is central to achieving the 2028 first oil target and reflects the operational planning discipline required within the Aker BP Subsea Alliance, a partnership comprising Aker BP, Subsea 7 and OneSubsea.

Contract Scale and North Sea Execution Risk Investors Should Monitor

Subsea 7 formally defines a substantial contract as one valued between $150 million and $300 million, placing the Lyra award at a meaningful level within its project portfolio. As a fixed-price EPCI contract executed across three offshore seasons, the programme carries execution risks including adverse weather, equipment performance and supply chain delivery timelines — factors Subsea 7 acknowledges in its standard risk disclosures. The Norwegian Continental Shelf remains a core operating region for the group, and the Lyra award reinforces its position within the Aker BP alliance structure at a time when North Sea operators continue sanctioning subsea tie-back developments.