Upland Resources Limited (LSE: UPL; OTCQB: UPLLF) has provided a drilling and pipeline update on its Wild Mustang gas development in Wyoming, United States, operated by Lost Soldier Oil and Gas (LSOG). The third well drilled on the Wild Mustang Federal Unit, designated GMF-5, has reached approximately 13,000 feet, with a planned total depth of around 19,700 feet. Meanwhile, construction of the five-mile gas sales pipeline is approximately 80% complete, with connection to existing infrastructure currently expected in December 2026, subject to remaining works and approvals.

Key Points

  • Upland Resources Limited (LSE: UPL; OTCQB: UPLLF) is a Southeast Asian-focused oil and gas company also active in the United States
  • GMF-5, the third well on the Wild Mustang Federal Unit in Wyoming, is currently at approximately 13,000 feet against a planned total depth of roughly 19,700 feet
  • Upland has invested approximately US$4.3 million in LSOG, with an option to invest a further US$9.5 million exercisable until 31 December 2030
  • Investors should watch for pipeline commissioning in December 2026 and further logging and testing results from GMF-5

GMF-5 Drilling Reaches 13,000 Feet With Unexpected Gas Shows in Fort Union and Upper Sussex Formations

Mud-log monitoring during GMF-5 drilling has recorded gas shows across two intervals that were not pre-drill targets. Five shows were recorded in the Fort Union Formation between approximately 5,500 and 6,500 feet, and eight shows were identified in the Upper Sussex between approximately 10,000 and 12,400 feet. LSOG reports that Upper Sussex shows averaged in excess of 750 total gas units. The company notes that neither interval is included in LSOG's existing estimates of gas initially in place for the Lost Soldier acreage. The announcement cautions that mud-log gas shows do not, on their own, establish recoverable resources or commercial productivity, and any contribution will be assessed following logging and testing.

Five-Mile Gas Sales Pipeline 80% Complete With December 2026 Infrastructure Connection Targeted

LSOG has advised that construction of the five-mile gas sales pipeline linking the Wild Mustang development to existing infrastructure is now approximately 80% complete. Connection is currently expected in December 2026, though the announcement states this remains subject to completion of remaining construction, commissioning works, and any required regulatory approvals. The timing of first commercial gas sales is therefore dependent on those activities concluding successfully. Investors may be watching this milestone closely, as pipeline connectivity is a prerequisite for the royalty income that Upland's Class C units are structured to receive from production on the Wild Mustang Federal Unit leases.

Upland's US$4.3 Million LSOG Investment Carries Royalty Interest Without Drilling Cost Exposure

Upland has committed approximately US$4.3 million into LSOG through its wholly owned subsidiary, Upland Resources (Wyoming) Ltd. The company also holds an option to invest a further US$9.5 million in LSOG at the same subscription price, exercisable until 31 December 2030. Upland's Class C units carry a royalty interest in production from the Wild Mustang Federal Unit leases without exposure to well drilling costs or operating liabilities — a structure that limits downside risk but means any royalty income remains contingent on achieving commercial production. The well continues advancing towards the primary Niobrara and Frontier formations, whose results are yet to be established.