Zephyr Energy plc (AIM: ZPHR), the AIM-listed oil and gas company focused on the Rocky Mountain region of the United States, has announced a significant uplift in its development ambitions for the Paradox project in Utah. The board has approved funding for additional engineering and well work targeting initial gas processing capacity of up to 15 million standard cubic feet per day (mmscf/d), a material increase from an earlier base case estimate of 5 mmscf/d. The work will be funded entirely from existing cash resources and is progressing in parallel with Enbridge's ongoing regulatory approval process for use of its 16-inch pipeline.

Key Points

  • Zephyr Energy plc (AIM: ZPHR) — AIM-listed, technology-led oil and gas company operating in the Rocky Mountain region
  • Board approves additional engineering and well work to target initial processing capacity of up to 15 mmscf/d at the Paradox project in Utah
  • Initial gas supply to come from the State 36-2R and Federal 28-11 wells; farm-out and a proposed US$15 million commodity purchase agreement continue to progress
  • Investors should watch for Enbridge's regulatory approval timeline, first gas confirmation, and updates on new well locations and permitting

Zephyr Board Approves Increased Processing Capacity Target of 15 mmscf/d for Paradox Project

Zephyr's board has elected to fund detailed engineering work for a modular gas processing system designed to handle up to 15 mmscf/d of production capacity at the Paradox project — a threefold increase over the previous base case estimate of 5 mmscf/d. The company states this decision reflects board confidence that regulatory approvals for up-rating the operating pressures of the Enbridge-operated 16-inch pipeline will be obtained. All associated engineering and well work costs will be met from the company's existing cash resources, with no new fundraising announced in connection with this programme.

State 36-2R and Federal 28-11 Wells Identified as Initial Gas Sources for Commercial Production

Initial gas volumes at the Paradox project are expected to be supplied by two wells. The State 36-2R was drilled and production-tested by Zephyr in 2025, achieving a peak flow rate of 2,848 barrels of oil equivalent per day without fracture stimulation, which the company states ranks the well in the top 6% of gas wells across the Lower 48 US states. The Federal 28-11 well was originally drilled in 2008 and acquired by Zephyr in 2022; prior to being shut in due to infrastructure constraints, it produced over 0.36 billion cubic feet of natural gas and approximately 93,000 barrels of oil.

Enbridge Pipeline Inspection Ongoing as Regulatory Approval Remains Critical Milestone

Enbridge's process to excavate and visually inspect four short sections of the existing 16-inch pipeline is ongoing, with the announcement stating no concerns or safety issues have been noted to date. A mandatory in-line inspection has already been completed. Regulatory approval for gas export through the Enbridge pipeline into the Williams-operated Northwest Pipeline system remains a critical requirement before Zephyr can achieve first gas and commercial production. The company acknowledges that the exact timing of regulatory approval remains uncertain, and investors may be watching closely for further updates on this process.

Farm-Out Discussions and US$15 Million Commodity Purchase Agreement Continue in Parallel

Alongside the engineering and well work programme, Zephyr states it continues to progress both a potential farm-out of the Paradox project and a proposed US$15 million commodity purchase agreement, which was first announced on 27 July 2026. The company's flagship Paradox project covers approximately 70,000 acres in Utah, with an independent 2025 Competent Persons Report confirming 2P reserves of 35.3 million barrels of oil equivalent within the 20,000-acre White Sands Unit. Further updates on the farm-out and commodity agreement are expected in due course.