Highlights
• Drax agreed to develop a strategic Partnership with Brookfield and Radiant for an AI data centre above 1GW.
• Phase 1 targets up to 100MW, backed by a £2.5bn initial Investment and commercial operations from early 2028.
• Brookfield estimates total potential investment, including semiconductor chips, could exceed £20bn if built in full.
• A planning application is being prepared, with public consultation on the scheme expected to begin in November 2026.
A power station that has kept Britain's lights on for half a century is lining up a new kind of customer. Drax (LSE:DRX) said on Tuesday it has signed an agreement to develop a strategic partnership with Brookfield and Radiant, Brookfield's UK-headquartered AI infrastructure platform, to build a data centre of more than 1GW on the Drax Power Station estate. The first phase alone carries a £2.5bn initial investment, and Brookfield estimates total spending could top £20bn once chips are included. For the FTSE 250 energy group, it marks a push to put its grid connection and generating fleet at the heart of the UK's AI build-out.
What Drax announced
The three partners plan to jointly develop, deliver and operate the data centre. Radiant brings AI infrastructure expertise, Drax supplies powered land and generation, and investment Capital and operating capabilities come through a Brookfield-Qai AI infrastructure joint venture announced in 2025.
Drax chief executive Will Gardiner said: "If constructed in full, this project could become one of the largest data centres in the UK with the potential to attract billions in inward investment, supporting the north's reindustrialisation and strengthening sovereign AI capability."
A three-phase build-out
The project is staged. Phase 1, running from 2026 to 2028, covers up to 100MW, with commercial operations targeted from early 2028 and power drawn directly from the grid under Drax's management. Radiant will lead design, customer engagement and commercialisation, aiming to secure anchor customers before construction, while Drax leads on land, power integration and planning.
Phase 2, between 2028 and 2031, carries an ambition to add up to 500MW using existing generation in a behind-the-meter arrangement, supplying around-the-clock power under a long-term power purchase agreement, subject to consents. Phase 3, after 2031, envisages further capacity on the same model.
Why the site matters
The estate spans more than 1,000 acres with about 4GW of grid access and 2.6GW of active dispatchable generation, sitting next to one of the country's largest substations. Phase 2 ties into the Contract for Difference Drax signed with the UK Government in November 2025, which includes a mechanism for Drax to request up to 500MW for a data centre, subject to agreement from the Government and the Low Carbon Contracts Company.
The company stressed that the station's role in supporting UK security of supply, providing low-carbon dispatchable power and critical system services, "will remain unchanged". Gardiner added that the site "is one of the few UK sites that can provide large-scale reliable power directly to data centre customers by utilising existing and underutilised generation capacity."
Brookfield's head of AI infrastructure, Sikander Rashid, said: "Teaming up with Drax and Qai for this project represents a major opportunity for our AI infrastructure strategy."
Conditions and risks
Nothing is locked in yet. Phase 1 depends on planning approvals, regulatory and network approvals from Government and relevant agencies, an acceptable tenant, the necessary commercial agreements and a final investment decision by each party. The announcement did not disclose ownership splits, payments to Drax or any change to financial guidance, and Phases 2 and 3 are framed as ambitions rather than commitments.
What investors may watch next
A planning application is being prepared, with public consultation expected to begin in November 2026. The partners also expect to set up a voluntary community benefits fund, separate from planning obligations and Drax's existing community initiatives. Signs of anchor tenants, progress on consents and any financial terms will be the next markers for LSE stocks tied to the data-centre theme.
Powering the next chapter
The deal gives Drax a route to turn its grid access into long-term digital infrastructure while keeping its generation role intact. Delivery now hinges on approvals, tenants and investment decisions over the next two years.