Highlights
• The TSXV has given final acceptance to Pulsar Helium's equipment-supply agreement with Chart for two plants.
• The agreement covers a helium liquefaction plant and a CO2 capture plant for an aggregate US$85.5m.
• Pulsar has paid US$5,025,000 from cash so far, covering the initial milestone and an LNTP payment.
• Milestone 2, worth US$8.55m, falls due on 31 January 2027 and will come from existing cash.
Two plants, one supplier and a US$85.5m price tag. Pulsar Helium (LSE:PLSR) has received final acceptance from the TSXV for its equipment-supply agreement with Chart, and attention now moves to the next payment on the schedule and the Manufacturing period that follows it.
What the agreement covers
The agreement between Pulsar Helium (LSE:PLSR) and Chart covers two pieces of equipment. The first is a helium liquefaction plant with a capacity of 861 litres per hour, equal to about 7.5 million litres of liquid helium a year, or about 200 million standard cubic feet annually.
The second is a CO2 capture plant rated at 300 tonnes per day. That is equivalent to more than 100,000 tonnes of liquid CO2 a year.
Price and staged payments
The aggregate price is US$85.5m, payable in stages. The figure excludes installation, taxes and site costs.
So far, Pulsar Helium (LSE:PLSR) has paid US$5,025,000 from cash. This comprises the 5% initial milestone of US$4,275,000 plus an LNTP payment of US$750,000. The total LNTP amount credited stands at US$1,000,000.
The next step: Milestone 2
The next payment is Milestone 2, set at US$8.55m and due on 31 January 2027. Pulsar intends to fund it from existing cash. A calculation based on the disclosed figures shows that this payment equals 10% of the aggregate price.
Manufacturing timeline and contract terms
Manufacture of the equipment is expected to take about two years after Milestone 2 is paid. The agreement also includes cancellation charges of up to 70%.
Understanding the Equipment
The agreement with Chart covers a helium liquefaction plant and a CO2 capture plant. Liquefaction cools helium gas until it becomes a liquid, which makes it easier to store and transport, and the plant's capacity of 861 litres per hour equals about 7.5 million litres of liquid helium a year, or about 200 million standard cubic feet annually. The CO2 capture plant is rated at 300 tonnes per day, equivalent to more than 100,000 tonnes of liquid CO2 a year. Capacity figures describe the rated output of the equipment rather than actual production.
How the Payments Work
The aggregate price of US$85.5m is payable in stages and excludes installation, taxes and site costs. Staged payments, often called milestones, tie portions of the price to defined points in the manufacturing and delivery process. Pulsar has paid US$5,025,000 from cash, made up of the 5% initial milestone of US$4,275,000 and an LNTP payment of US$750,000, and the total LNTP amount credited stands at US$1,000,000. Milestone 2 is set at US$8.55m and is due on 31 January 2027, which equals 10% of the aggregate price, a calculation based on the disclosed figures. Pulsar intends to fund it from existing cash.
Timeline and Contract Terms
Manufacture of the equipment is expected to take about two years after Milestone 2 is paid. The agreement also includes cancellation charges of up to 70%, which describe the amounts payable if the contract were cancelled, a term that is common in equipment-supply agreements where manufacturers commit resources to a custom order. The TSXV, the venture exchange on which the company's securities are also listed, has given final acceptance of the agreement, which is why the announcement describes it as a milestone. For readers following Pulsar Helium, the main dates and amounts are now set out clearly: the 31 January 2027 payment of US$8.55m and a manufacturing period of about two years after that. The announcement does not describe installation timing or site costs, so those details remain to be provided in later updates. Further information about the company's project and plans is published through its other announcements.
Further announcements are expected to describe progress on payments and manufacture.