Aminex PLC (LSE:AEX) said the Ntorya-Madimba gas pipeline in Tanzania is about 95% complete and first gas from the Ntorya field is expected in December 2026. The update came with half-year results showing a wider loss and a Going Concern material uncertainty.

What was announced

Aminex published its interim results for the six months to 30 June 2026 on 25 September 2026. The company holds a non-operated, Carried Interest in the Ntorya gas field under the Ruvuma Production Sharing Agreement (PSA). ARA Petroleum Tanzania Limited (APT) is the operator, and The Zubair Corporation LLC and the Tanzania Petroleum Development Corporation (TPDC) are also partners. Aminex is carried for US$35.0 million of development expenditure through to commercial production.

The Ntorya-Madimba pipeline, which is being built by the Government of Tanzania, will link the field to the Madimba Gas Processing Plant and the national gas transmission system. The company said the pipeline was about 95% complete and that first gas is targeted for December 2026. This is a target, and delivery depends on the operator and the pipeline.

The numbers

Revenue for the half was US$14,000, compared with US$17,000 a year earlier. It came from technical and administrative services to joint operations, and there was no gas production revenue. The loss for the period widened to US$2.71 million from US$1.50 million. Cash and cash equivalents were US$2.23 million at 30 June 2026, compared with US$3.41 million at 31 December 2025, and the company had net current liabilities of US$4.12 million.

The directors disclosed a material uncertainty over the company's ability to continue as a going concern. They cited the net current Liability position, continuing losses, contested Tanzanian tax assessments of about US$10.3 million and reliance on Warrant and share option exercises, which are expected in late 2026 or early 2027. The directors said they have "a reasonable expectation that additional funding can be raised", based on previous share fundraisings.

Dispute and revised well programme

The results set out a dispute over the 2026 work programme. APT proposed material changes, including drilling at Ntorya-Central (NT-C) in place of the obligatory Chikumbi-1 (CH-1) well. Aminex said these changes risked delaying first gas. On 21 August 2026, Aminex Subsidiary Ndovu Resources Limited issued a formal Notice of Dispute to APT and The Zubair Corporation, alleging breaches of the work programme and the Joint Operating Agreement.

On 26 August 2026, Dr James Mataragio, Permanent Secretary for Petroleum at the Ministry of Energy, convened a meeting in Dar es Salaam with the Ministry, the regulator PURA, TPDC, APT and Ndovu. According to Aminex (LSE:AEX), the government rejected the proposal to delay the project and the parties agreed a revised programme that keeps first gas in December 2026.

Under the revised plan, NT-1 is scheduled for wellhead maintenance and slickline operations in October 2026. NT-2 is due to be tested in November 2026, with first gas deliveries by the end of December. NT-3, at the location previously designated NT-C, is planned to spud before the end of 2026; if successful, gas delivery is scheduled for September 2027. NT-E and NT-W are optional follow-on locations, and CH-1 is confirmed as the commitment well at the end of the programme. Projected expenditure is up to US$75 million for the rest of 2026 and 2027.

What to watch next

Executive Chairman Charles Santos said the company's story had moved from "survival or restructuring" to "execution, production and growth". Management expects to enter 2027 debt-free and generating Revenue from Ntorya, but this is a company expectation. Principal risks include operator delays, licence commitments, drilling results, tax assessments, financing and political and fiscal uncertainty. The Kiliwani North, Nyuni Area and Kiliwani South Assets remain fully impaired.