Gresham House Energy Storage Fund plc (LSE:GRID) has spent recent months answering pressure from Shareholder PrimeStone Capital, which called for the fund to be sold. On 15 September 2026, the board rejected that approach. The question is why it chose to pursue its own growth plan instead, and what its latest reported figures show.
A listed battery storage fund
Gresham House Energy Storage Fund is a London-listed Investment company that owns utility-scale battery energy storage systems in Great Britain. Its manager is Gresham House Asset Management Ltd. The batteries earn income by trading electricity, providing grid balancing services and participating in capacity markets, so returns depend heavily on power price Volatility and grid demand.
According to its 2 September 2026 trading update, the operational portfolio totals 1,072MW. Three projects totalling 397MW have entered construction, and a further 777MW has been conditionally acquired, which the company said positions it to "more than double the operational capacity". The first three pipeline projects, Cockenzie, Monets Garden and Elland 2, secured £141m of senior project finance, and a Partnership with Summit Transition Partners acquired 25% stakes in them.
The PrimeStone question
PrimeStone publicly argued for an outright sale of the company. Specialist publication QuotedData reported that the activist claimed a sale could unlock value of 140p per share. When the board first acknowledged the letter on 1 July 2026, it noted a "constructive tone" and said it would consult shareholders before responding. In July, QuotedData reported MIGO's managers backed the call.
The board's formal response came on 15 September. As reported by QuotedData, chair John Leggate said "initiating a formal sale process for the company now would not be in the best interests of shareholders", and the board argued that "there is a lot more growth to come which is yet to be recognised in the NAV". The same report said the shares were trading around 24% below net asset value (NAV), a gap that underpinned the activist's case.
Half-year numbers
The fund published interim results on 23 September 2026. According to the trading update and Alliance News coverage of the results, NAV per share was 131.30p at 30 June 2026, up from 113.34p at the end of 2025. Around 14.33p of that increase came from revaluing the 397MW of projects that moved into construction. Revenue for the half-year was reported at £34.7m, up 9.5% on the prior year, and EBITDA at £23.5m, compared with £20.5m. Net Debt was reported at £171.4m, up from £159.3m.
Other initiatives support the growth argument. On 29 June 2026, the company announced a provisional award under Ofgem's long duration energy storage cap and floor scheme for Ocker Hill, configured as a 145MW / 1,160MWh eight-hour asset with 25 years of index-linked revenue support, with final awards expected in autumn 2026. The trading update also cited augmentations adding 150MWh at Glassenbury and Stairfoot and a trial alternative revenue arrangement.
Risks and what to watch
Battery revenues remain exposed to wholesale price spreads, competition from new storage capacity and changes in grid services markets. The construction programme adds execution and financing risk, and net debt has increased. Much of the recent NAV growth came from revaluations rather than cash earnings, so delivery of projects on time and budget will matter. The Ocker Hill award is provisional and not due to connect until October 2029. PrimeStone's next steps, and whether other shareholders support it, also remain open.
Conclusion
The board rejected a sale because, in its view, the fund's construction pipeline, augmentations and new revenue streams will create value not yet reflected in NAV. Reported half-year figures showed rising NAV, revenue and EBITDA, but the persistent discount, higher debt and execution risk explain why the activist debate continues.