In August 2026, Aminex (LSE:AEX) formally challenged the operator of its main Tanzanian gas licence over delays. Within two weeks, a revised development programme had been agreed with the operator and the Tanzanian authorities. How did the small gas company move from a notice of dispute to an agreed plan, and what still needs to go right before Ntorya produces gas?
A carried partner in a Tanzanian gas field
Aminex is an oil and gas company whose principal asset is an interest, held through its Subsidiary Ndovu Resources, in the Ruvuma production sharing agreement in southern Tanzania, which contains the Ntorya gas field. The operator is ARA Petroleum Tanzania Limited (APT). Under a 2020 farm-out, Aminex says it is carried for its share of Ntorya development costs through to commercial production. It also holds an interest in Kiliwani North, which remains fully impaired. Its shares are listed in London, and its announcements refer to compliance with the UK Listing Rules.
From dispute to revised programme
On 21 August 2026, Aminex announced that Ndovu had issued a Notice of Dispute to APT and its parent, The Zubair Corporation. It said APT had repeatedly sought to replace the approved 2026 work programme with alternatives that would materially delay drilling of the CH-1 obligation well, and that this had resulted in "material further delay, limited expenditure and minimal substantive work" in 2026. The notice started a 90-day period for amicable resolution, with possible referral to the London Court of International Arbitration.
On 2 September 2026, the company reported that Tanzania's Ministry of Energy, the regulator PURA, TPDC, APT and Ndovu had agreed a revised implementation programme. According to Aminex, the ministry rejected the operator's proposal for an extension. Executive chairman Charles Santos said the focus was on "working together to implement the agreed programme and deliver first gas without further delay". Aminex described the agreement as important progress towards resolving the dispute.
The plan and the finances
An operations update on 23 September 2026 said the partners had approved budgets of about US$75 million for the rest of 2026 and 2027. The Ntorya-Madimba pipeline was about 95% complete, with completion scheduled for December 2026. The Ntorya-2 well is due to be tested in November, with production targeted for December. A Ntorya-Central well is expected to spud in December, with first gas in September 2027 if successful, and the CH-1 well is to be drilled at the end of the programme.
The half-year report published on 25 September showed a net loss of US$2.71 million for the six months to 30 June 2026, up from US$1.50 million, and cash of US$2.23 million, down from US$3.41 million. Current liabilities of US$7.88 million exceeded current Assets of US$3.76 million. The directors reported a material uncertainty over going concern, relying on Warrant and option exercises and potential Capital raises, though they said they reasonably expect further funding can be raised. Shareholders approved all resolutions, including allotment authorities, at the AGM on 1 October 2026.
Risks to watch
The schedule is tight, with several operations planned within three months. Any slippage at the pipeline or wells would delay revenue. The relationship with the operator has been strained, and the dispute was described as progressing rather than closed. Aminex's own cash is limited, so further funding may dilute shareholders. Well results and gas volumes remain uncertain until testing, and the Ntorya-1 well may need a rig workover that could push its production to December 2027.
Conclusion
Aminex reached a revised Ntorya plan by escalating its contractual dispute and then securing a government-convened agreement that set firm dates for first gas. Delivery of the December milestones will show whether that agreement holds, and will also bear on the funding uncertainty in its accounts.