Ceres Power's interim results on 23 September showed a much healthier balance sheet after a summer fundraising, alongside reduced losses and a push into on-site power for data centres.

Ceres Power Holdings plc (LSE:CWR) published interim results on 23 September 2026 for the six months to 30 June. The fuel cell and electrolysis technology licensor reported revenue of £22.8 million, up 8% on the £21.1 million reported a year earlier. Part of the increase came from one-off licence income under its agreement with Weichai. Gross profit fell 3% to £16.1 million and the gross margin narrowed to 71% from 79%, which the company attributed to a lower-margin revenue mix.

Cost reductions improved the bottom line. Operating costs before one-off items fell 14% to £30.7 million, with R&D spending down to £18.3 million from £25.6 million. The adjusted EBITDA loss narrowed to £6.8 million from £11.3 million. After a £3.0 million impairment on unfinished test equipment, the statutory operating loss was £16.7 million and the loss after tax was £16.9 million. Revenue remained concentrated: three customers accounted for about 59%, 18% and 16% of the total.

Funding in place

In June, Ceres (LSE:CWR) raised £102.6 million gross, or £99.1 million net, in an oversubscribed share placing. Cash and investments rose to £172.0 million at 30 June, from £83.3 million at the end of 2025. The directors said their cash forecasts to the end of 2027 show sufficient resources, including under stress-test scenarios.

The company said it had contracted revenue of about £45 million for 2026 before any new business. It is confident of signing a new licensee this year, and any revenue from such a deal in 2026 would be in addition to that figure. Management is aiming to cut operating costs by about 14% from 2025 levels by the end of the year.

Data centres and partner progress

Much of the outlook focused on demand for on-site power. Ceres estimates the global market for solid oxide fuel cells at around 22 gigawatts a year by 2030 and expects data centres to account for roughly half of it. It said delays in connecting to the grid are pushing operators towards generation equipment that can be installed within months. Chief executive Phil Caldwell said customers are finding it increasingly hard to secure new generation and grid capacity, and that early signs of downstream demand are emerging across the partner network.

Several partners reported progress. Doosan Fuel Cell signed a contract worth about KRW108.7 billion (around £60 million) with Reverion GmbH to supply fuel cell stacks for Germany and the rest of Europe, its first export order. Delta Electronics approved a factory investment of about £240 million in Taiwan, with first shipments expected in 2028. It also agreed in April to work with Centrica on off-grid power for data centres and heavy industry. Ceres signed its own strategic partnership with Centrica in March. Denso received about £165 million of Japanese government funding to test an electrolyser demonstrator with JERA, and Shell's 1 megawatt hydrogen demonstrator in Bangalore has performed ahead of expectations.

On 26 August, Ceres spun out its flow battery subsidiary, RFC Power, which has been renamed Certain Energy. The business raised £10 million in a Series A round led by the British Business Bank. Ceres invested £1 million in cash and received £1.5 million of shares in return for engineering services. It now holds about 37% of the business, which has a post-money valuation of around £12 million, and will also receive a share of future product revenues.

Shareholder register

A filing on 23 September showed that BlackRock's interest in the FTSE 250 company had risen from 5.85% to 6.78% of voting rights on 22 September, made up of shares and financial instruments.