The funding question
Pulsar (LSE:PLSR) Helium, which is exploring for primary helium at its Topaz project in Minnesota, has made no substantive announcement since a routine share issue on 4 November. Its October filings, however, set out a staged equipment contract and a financing plan for a proposed helium and carbon dioxide processing plant that could shape its Balance Sheet in 2027. This article examines how the company intends to pay, using disclosures dated 1 and 12 October 2026. Figures are in US dollars.
What Pulsar has committed to
On 1 October Pulsar said its Minnesota Subsidiary had accepted a binding proposal from Chart Energy & Chemicals, now part of Baker Hughes, to Supply equipment for a helium purification and liquefaction plant and a CO2 plant for an aggregate US$85.5m. The helium system has a nameplate capacity of 861 litres an hour, about 7.5 million litres of liquid helium a year at continuous operation, while the CO2 unit is rated at 300 tonnes a day.
The company stressed that the price is not the total installed cost. It excludes taxes, duties, installation, commissioning, site infrastructure and other owner costs, and CO2 storage and loading equipment will be addressed separately. No installed cost estimate has yet been published. Pulsar said some of the helium liquefaction equipment in the package has already been manufactured, and it is separately negotiating a prospective plant site in Lake County, Minnesota.
How the payments are staged
A first payment of $5.025m, including $750,000 under an earlier limited notice to proceed, falls due on signing and exchange approval and is to be met from existing cash. The second milestone, $8.55m, is scheduled for 31 January 2027 and would authorise Chart to begin procuring long-lead items; equipment manufacture is then expected to take about two years. Later payments are tied to engineering, ordering, readiness-to-ship and documentation milestones.
If the January payment is not made, the contract enters a suspension period of up to 180 days. Pulsar (LSE:PLSR) would owe nothing extra during suspension and the reserved liquefaction equipment would stay protected, after which the parties would decide whether to continue, amend or terminate. Cancellation charges scale with work completed, up to 70% of contract value at the final stage, but only for milestones already paid.
The preferred financing mix
On 12 October Pulsar said it would prefer to fund a substantial part of remaining costs through project-level Debt and public-sector finance, supplemented by its own cash, with the aim of limiting new shares. It is in discussions with University Bank, whose parent is a Pulsar shareholder, and with Minnesota's Department of Employment and Economic Development, Iron Range Resources & Rehabilitation and the US Department of Agriculture's rural Loan guarantee programme. The company said no binding commitment had been received from any of them.
Unaudited cash was about $24.6m on 12 October, against $25.2m reported on 1 October. Existing cash could cover the first two Chart payments, but not the full contract or the wider build without outside funding.
Factors to watch
The plan depends on securing a site, an EPC contractor, an installed cost estimate, permits, gas supply and offtake agreements before lenders commit. The company noted that helium and CO2 prices may change before commissioning. Using cash for the plant would also compete with exploration at Topaz and the Falcon project in Michigan. Share issuance cannot be ruled out despite the stated preference.
What to watch
The key date is 31 January 2027 for the second Chart milestone. Pulsar (LSE:PLSR) has said it will provide a first production target only once scope, permitting, financing and the EPC schedule are sufficiently defined, and will update shareholders as material financing arrangements are confirmed. Shares in issue totalled 214,788,383 after the November issue.