German wind turbine maker Nordex booked 2,810 MW of new turbine orders in the third quarter of 2026, up 29.5% on a year earlier. Türkiye, Germany and the US were its strongest markets.
What was announced
Nordex SE, the onshore wind turbine manufacturer based in Hamburg and Rostock, reported third-quarter order intake on 12 October 2026. The Frankfurt-listed company is a member of the MDAX and TecDAX indices.
Order intake in the Projects segment was 2,810 MW in the three months to September, up from 2,170 MW in the third quarter of 2025. That is an increase of 640 MW, or 29.5%. The figures cover new turbine orders only and exclude the Service business.
The company said 427 wind turbines were ordered between July and September, for projects in 10 countries. It describes the product range as onshore turbines in the 4 MW to 7 MW-plus classes.
The numbers
For the first nine months of 2026, order intake was 7,733 MW, up 16.1% from 6,661 MW a year earlier, an increase of 1,072 MW. Orders in the first half of 2026 totalled 4,923 MW, so the third quarter accounted for about 36% of the nine-month total.
The average selling price (ASP) in the third quarter was €0.90m per MW, down from €0.93m a year earlier. For the nine months, the ASP was €0.93m per MW, up from €0.92m. Nordex said the movements came mainly from project scope and regional mix, and that pricing remained stable.
Third-quarter orders would be worth roughly €2.5bn, against about €2.0bn a year earlier. On the same basis, nine-month orders would be roughly €7.2bn.
The third-quarter orders work out at an average of about 6.6 MW per turbine.
Where the orders came from
Türkiye was the largest single contributor, with more than 900 MW of orders in the third quarter. That is about a third of the quarter's total. Germany and the US were also among the strongest markets. The company said US bookings exceed 1.3 GW so far this year, which is about 17% of nine-month order intake.
Chief executive José Luis Blanco said: "Our order intake is becoming more globally diversified, and the third quarter confirms this." He added: "We expect the international share to keep growing as we convert our pipeline in the coming quarters." He also said order momentum in Europe and Germany "remains strong".