First gas from the Ntorya field in Tanzania, targeted for December 2026, would mark Aminex's move from a company with almost no revenue towards one with a producing asset, but the timetable is operator-led, has been disputed and still faces funding and execution risks.
Aminex PLC (LSE:AEX) holds a 25% interest in the Ruvuma Production Sharing Agreement in Tanzania, which contains the Ntorya gas field. Under a programme agreed with the operator, ARA Petroleum Tanzania Limited (APT), the NT-2 well is planned to be tested from November 2026 and to deliver first gas into the Ntorya–Madimba pipeline in December 2026. For a company that reported revenue of just US$14,000 in the first half of 2026, that would represent a significant change in its business. The company has not published a forecast of what Ntorya production would mean for its revenue or cash flow.
Aminex is one of the most-discussed UK stocks among investors today. However, there is no new company announcement on 14 October 2026; the most recent was published on 7 October 2026. The shares were unchanged on the day at 1.85p, so there is no move to explain, and the discussion centres on the planned operations rather than fresh news.
The planned Ntorya timetable
The operator's revised programme, set out in the "Ntorya Operations Update" of 23 September 2026, includes the following month targets:
- October 2026: NT-1 wellhead maintenance and slickline operations; a rig contract for NT-C (Ntorya-3) expected
- November 2026: NT-2 bridge plug removal and testing
- December 2026: NT-2 production into the Ntorya–Madimba pipeline; pipeline completion; NT-C spud
- September 2027: first gas from NT-3, if successful
These are planned months rather than fixed dates. If NT-1 needs a rig workover, that work would follow NT-C, delaying NT-1 gas to December 2027. Up to two more wells, NT-E and NT-W, may follow depending on NT-3 results, and the CH-1 obligation well is to be drilled at the end of the programme.
The pipeline is a key dependency. It is scheduled for completion in December 2026, and TPDC reports that about 95% of pipelaying and infilling is done.
Executive Chairman Charles Santos said: "We remain focused on maintaining the current momentum and delivering first gas in December." He added: "The coming months will see a significant increase in operational activity at Ntorya."
What first gas could mean for Aminex
The most immediate effect would be a shift in what Aminex is: from a company dependent on option and warrant exercises for funding towards one with an interest in producing gas. Several features of its position are relevant:
- Carried interest: Aminex is carried for its share of Ruvuma development spending up to US$35.0 million, equivalent to US$140.0 million of gross field expenditure. The carry balance remaining at 30 June 2026 was US$28.1 million.
- Spending plans: projected gross expenditure is up to US$75 million for the rest of 2026 and 2027 under the revised work programme and the provisional 2027 programme.
- Non-operator role: APT holds a 50% interest and operatorship, so Aminex does not control the pace of work.
The carry matters because it limits how much Aminex itself must fund while the programme progresses. The company has not said when the remaining carry balance might be used up, and no gas price, volume or revenue figures for Ntorya were provided in the disclosures reviewed. Any assessment of how much first gas would add to Aminex's income therefore remains open until the company provides more detail.
From dispute to an agreed programme
The current timetable came after a period of friction with the operator. On 21 August 2026 Aminex announced that its wholly owned subsidiary Ndovu Resources Limited had issued a Notice of Dispute against APT and The Zubair Corporation LLC, alleging breaches of the Farmout Agreement and Joint Operating Agreement over the 2026 Work Programme and Budget, including delay to the CH-1 well. The notice started a 90-day resolution period, after which Ndovu may refer the matter to the London Court of International Arbitration.
At a meeting on 26 August 2026 convened by Tanzania's Ministry of Energy, with PURA, TPDC, APT and Ndovu present, the government rejected the operator's proposal to extend and delay the timetable and confirmed a revised schedule. APT confirmed it has all the funds needed for the revised programme. Aminex called this important progress towards resolving the issues behind the notice. Mr Santos said: "Our focus now is on working together to implement the agreed programme and deliver first gas without further delay."
No announcement has formally withdrawn or resolved the Notice of Dispute.
Financial position
The 2026 Half-Yearly Financial Report, published on 25 September 2026, showed:
- Revenue of US$14,000 (H1 2025: US$17,000)
- A loss of US$2.71 million (H1 2025: US$1.50 million)
- Cash of US$2.23 million at 30 June 2026, down from US$3.41 million at 31 December 2025
- No borrowings drawn in the period
The report states: "There is material uncertainty as to its ability to raise such additional funding". Its funding assumptions rely on warrant and share-option exercises expected in late 2026 and early 2027. There are 249,334,020 warrants from the October 2025 placing, exercisable at 2.50p, and 196,911,000 share options were in issue at 30 June 2026. The directors nonetheless "have a reasonable expectation that the Group will continue in operational existence."
On 7 October 2026 a former director exercised options over 17,000,000 shares, raising £238,000 for working capital. Total voting rights afterwards were 4,502,001,044.
Risks to weigh
- Going concern: the half-year report flags material uncertainty over raising additional funding.
- Dilution: funding relies on warrant and option exercises, which would add to the share count.
- Operator and timetable: Aminex is not the operator, the schedule has been disputed, and the planned months could slip.
- Country and market: Tanzania regulatory and political risk, plus gas pricing and offtake risk, apply.
- Minimal revenue: until gas flows, the company has almost no income.
The market value is shown at £82.97m, with a 52-week range of 1.00p to 2.81p.
What to watch next
- Completion of NT-1 work and the NT-C rig contract during October 2026
- NT-2 testing in November 2026
- Pipeline completion and first gas in December 2026
- Any formal update on the Notice of Dispute
- Warrant and option exercises supporting funding
First gas would be a milestone for Aminex (LSE:AEX), but the company has yet to show what it means in revenue terms. The coming months will test whether the agreed programme holds.