Predator's MOU-6 well in onshore Morocco has reached its planned 950-metre total depth and will now be tested, but no test results have yet been released.

Predator Oil & Gas Holdings Plc (LSE:PRD) told the market on 14 October 2026 that its MOU-6 gas appraisal well on the Guercif Licence in onshore Morocco had reached its planned total depth of 950 metres, within the previously announced 20-day guidance. The well encountered the top of the TGB-6 Submarine Fan interval ("TGB-6 Fan") 600 metres northwest of MOU-3, with a gross upper interval of 21.2 metres, compared with approximately 13.2 metres in MOU-3. The company says this matches its pre-drill forecast.

In practical terms, reaching total depth means the drilling phase is complete and the well can move to testing. It does not yet show whether the interval will flow gas. The announcement does not report gas shows, net pay or flow results, and test operations are only "expected to commence shortly". The stock was one of the most-discussed UK stocks among investors today, on a day when Predator (LSE:PRD) also held its AGM and its shares fell to a 52-week low.

Inside the MOU-6 update

MOU-6 began drilling on 19 September 2026, with well operations planned to last up to 20 days. According to the 14 October 2026 announcement:

  • Wireline logs, including spectral gamma ray and FMI, were acquired.
  • The well is being completed for perforating over the 21.2-metre interval using 4.5" TCP guns.
  • A single well test will be performed, with operations "expected to commence shortly".
  • After the test, MOU-6 data will be integrated to update the biogenic gas potential of the MOU-1, MOU-3 and MOU-6 area.
  • Romanian firm Geo Line Solution S.R.L. has signed a Confidentiality Agreement to help find analogues for the 800–1,100 metre section.

Chief Executive Officer Paul Griffiths said: "We are pleased to have successfully completed the drilling phase of MOU-6". He added that this "has resulted in much improved well cutting samples and wireline logs compared to previous data".

It is important to keep the pre-drill target in context. In its interim financial statements, the company described MOU-6 as targeting 72.4 BCF of net recoverable gas. That is a company estimate made before drilling, not a proven resource, and the 21.2-metre interval has not yet been flow tested. MOU-6 is also described as the only Moroccan well to be drilled in 2026.

Attention turns to Trinidad

The same announcement confirmed that regulatory approval to drill Snowcap-3 in the Cory Moruga Licence, onshore Trinidad, has been received. A further update on progress and timing will follow completion of the Moroccan operations. Mr Griffiths said: "Operational focus will now shift to Trinidad."

The interim financial statements, published on 30 September 2026, describe Snowcap-3 as a development/appraisal well targeting 2P unrisked net recoverable oil of 8.73 MM barrels. Initial production guidance is 300 bopd, potentially rising to 459 bopd. Drilling is planned for Q4 2026 and expected to take up to 20 days, and the company targets first oil sales from the well in early Q1 2027. Non-Executive Chairman Stephen Boldy said: "The highlight of operations in Trinidad this year will be the drilling of the Snowcap-3 development/appraisal well".

Predator already has production in Trinidad. Gross sales oil was 52,310 barrels in H1 2026, and monthly production was 9,429 barrels in June 2026 from an active base of 100 wells. The group also holds an Irish interest through Corrib South, Licensing Option 16/26.

AGM results and share price

Predator held its AGM at 9.30 a.m. on 14 October 2026 in St Helier, Jersey. All four resolutions passed, including the directors' authority to allot ordinary shares, with 94.24% of votes in favour, and the re-election of Carl Kindinger, with 94.92% in favour.

The shares had a difficult session. Trading figures on 14 October 2026 (prices in pence):

  • Price 2.35, down 0.50 (17.54%), from a previous close of 2.85
  • Open 2.70; day high 3.05; day low 2.35
  • Volume 11,012,509
  • Market cap £21.25m
  • 52-week high 5.25 (19-Jan-2026); 52-week low 2.35 (14-Oct-2026)

The current price is below the May 2026 placing price of 3.5 pence.

The financial position

For the six months to 30 June 2026, the interim financial statements reported:

  • Sales income of £1,522,877 (H1 2025: £66,815)
  • Gross profit of £283,041
  • Operating loss of £934,088 (H1 2025: £1,931,397)
  • Loss after tax of £962,249
  • Cash of £6,648,192 at 30 June 2026 (31 December 2025: £1,518,874)
  • Net assets of £29,910,149

The group has no interest-bearing debt, although about £1.5m is restricted cash for bank guarantees and performance bonds. The directors said the Group "should have sufficient resources to continue as a going concern in a minimum committed expenditure case."

Cash has been supported by share placings. A placing to raise £4.5 Million was announced on 20 January 2026, followed by a £3,000,000 placing at 3.5 pence per share on 15 May 2026. That placing issued 85,714,286 new shares plus 6,000,000 warrants at 3.5p, with AlbR Capital Limited and OAK Securities acting as joint brokers. On 19 August 2026, 3,866,090 shares were issued at 3.35 pence to Mr Griffiths, settling 40% (£129,514) of a £323,785 liability. Total voting rights were 904,438,190 ordinary shares as at 28 August 2026.

Risks to weigh

  • Appraisal risk: MOU-6 has not been tested, and there is no certainty the interval will flow gas at commercial rates.
  • Dilution: placings in January 2026 and May 2026, and the renewed authority to allot shares, mean further issuance is possible.
  • Licence risk: the interims said a further Guercif Licence extension to 5 February 2027 was expected to be approved before the end of 2026, but it had not been granted at that point. Monetising Moroccan gas depends on MOU-6 results and approvals.
  • Timing risk: Snowcap-3 timing depends on completing operations in Morocco.
  • Commodity risk: Trinidad oil sales are exposed to oil price movements.

What to watch next

The key near-term item is the MOU-6 single well test, which the company expects to start shortly but has not dated. Investors will then look for the updated assessment of the MOU-1, MOU-3 and MOU-6 area, any decision on the Guercif Licence extension, the timing update for Snowcap-3 in Q4 2026, and progress towards the company's target of first oil sales from that well in early Q1 2027. Until test data is published, reaching total depth is an operational milestone rather than evidence of a commercial gas result.