Drilling timetable slips into 2027

Synergia Energy (LSE:SYN), the AIM-quoted oil and gas company focused on India's Cambay field, told shareholders on 4 November 2026 that the next well on its flagship licence would be drilled later than planned. The spud of the C-79 well, previously expected in late November 2026, has been pushed back to February or March 2027 because the drilling rig remains committed elsewhere. The announcement followed the company's audited annual report, published on 30 October, which set out the statutory result for the year.

What the company does

Synergia holds a 50% working interest in the Cambay production sharing contract in India, where it produces oil and gas from existing wells. Until recently it was also pursuing the Camelot carbon capture and storage project. In its annual report, the company said it was relinquishing the CS019 licence for Camelot because two legacy wells without abandonment data could block a storage permit, and that it would incur no further costs on the project.

Latest developments

According to the November update, the partners at Cambay are in broad agreement on the C-79 target in the Eocene formation, the well programme and the fracking programme. The rig, supplied by DEEP Industries, has been assigned to ONGC in Assam and no firm mobilisation date exists, so the company will provide timing updates once the operator confirms. A planned sale of Synergia's 50% interest to Selan, also referred to as Antelopus Selan Energy, fell through, so Synergia retains its stake. According to the annual report, Selan has agreed to drill the C-79 vertical well and is obliged to drill two further Eocene wells, with a horizontal well, C-80, expected in 2027.

Operationally, four workovers at Cambay added about 180 barrels of oil per day in total, with individual wells delivering varied results. Associated gas from three wells is now being sold, lifting gas output to about 140,000 standard cubic feet per day. The C-78 Oligocene well has been paused.

Financial picture

Figures in the Annual Report are in Australian dollars. For the year to 30 June 2026, Revenue rose 268% to about A$1.08 million, helped by higher production and prices. The company recorded a loss after tax of A$10.83 million, compared with a profit of A$4.99 million a year earlier, largely because of a A$6.9 million Impairment against a Carried Interest receivable. Excluding one-off items, the loss was about A$3.2 million. Cash was A$1.12 million at the year end. Synergia has a US$0.7 million Loan Facility from its largest shareholder, Republic Investment Management, of which US$225,000 had been drawn, and directors have deferred A$0.63 million of fees and salaries. The company does not pay a dividend.

Sector and index context

Synergia is one of the smallest energy companies within the FTSE AIM All Share Index. Its value is closely tied to a single asset, and the ability of its partner to deliver drilling commitments at Cambay is central to its prospects.

Business Model in Context

Synergia Energy (LSE:SYN) holds a 50% working interest in the Cambay production sharing contract in India, where it produces oil and gas from existing wells. Its value is closely tied to this single asset, so its partner's ability to deliver drilling commitments is central. In its annual report the company said it is relinquishing the CS019 licence for the Camelot carbon capture project because two legacy wells without abandonment data could block a storage permit, with no further costs on that project.

The partners at Cambay are in broad agreement on the C-79 target in the Eocene formation, the well programme and the fracking programme. Selan has agreed to drill the C-79 vertical well and is obliged to drill two further Eocene wells, with a horizontal well, C-80, expected in 2027. A planned sale of Synergia's 50% interest did not proceed, so the company retains its stake.

Reading the Figures and the Sector Backdrop

The spud of C-79, previously expected in late November 2026, is now expected in February or March 2027 because the rig supplied by DEEP Industries is committed to ONGC in Assam, and the company will give timing updates once the operator confirms. Four workovers added about 180 barrels of oil per day, associated gas from three wells is now being sold, lifting gas output to about 140,000 standard cubic feet per day, and the C-78 Oligocene well has been paused.

Figures are in Australian dollars: for the year to 30 June 2026, revenue rose 268% to about A$1.08 million, helped by higher production and prices. The loss after tax was A$10.83 million, compared with a profit of A$4.99 million, largely reflecting a A$6.9 million impairment against a carried interest receivable, and excluding one-off items the loss was about A$3.2 million. Cash was A$1.12 million, a US$0.7 million loan facility from largest Shareholder Republic Investment Management had US$225,000 drawn and directors deferred A$0.63 million of fees and salaries. No Dividend is paid.

Outlook and Key Considerations

The outlook for Synergia Energy (LSE:SYN) depends on the rig and drilling timetable at Cambay, where the partners are in broad agreement on the C-79 target, the well programme and the fracking programme. Four workovers added about 180 barrels of oil per day, and oil prices and the support of its largest shareholder shape the pace of development.

What to watch next

Investors are likely to watch for confirmation of the rig mobilisation date and the C-79 spud, results from that well, progress towards the C-80 Horizontal Well in 2027, the outcome of the Annual General Meeting and any new funding arrangements.