First gas is close, but the balance sheet is thin
Aminex matters now because its long-awaited Ntorya gas project in Tanzania is nearing first production, while its latest accounts carry a going-concern warning. The two announcements, three days apart in September 2026, together define the investment case.
On 23 September 2026 the company said the Ntorya-to-Madimba pipeline is scheduled for completion in December 2026, with first production from the Ntorya-2 well targeted for the same month. The 2026 half-yearly report followed on 25 September.
What the company does
Aminex is an upstream oil and gas company with operations in Tanzania. Through its subsidiary Ndovu Resources it holds a 25% non-operated interest in the Ruvuma production sharing agreement, a 63.83% operated interest in the Kiliwani North development and a 100% operated interest in the Nyuni Area licence, according to its website. Its shares are quoted on AIM, and its half-year report also refers to a Euronext Dublin listing.
Ntorya sits within the Ruvuma licence, where the operator is ARA Petroleum Tanzania (APT). Aminex says a carry arrangement covers development costs through to commercial production.
The Ntorya timetable
The joint venture has approved revised work programmes and budgets projecting gross expenditure of up to US$75 million across the remainder of 2026 and 2027. The state company TPDC has confirmed that about 95% of pipelaying and infilling work is complete, with connection and metering works at Madimba continuing.
The company's schedule runs as follows:
October 2026: wellhead maintenance on Ntorya-1.
November 2026: bridge plug removal and testing of Ntorya-2.
December 2026: Ntorya-2 production, pipeline completion and the start of drilling at Ntorya-Central.
September 2027: potential first gas from Ntorya-Central.
Executive Chairman Charles Santos said the company was pleased to have reached agreement with APT on the revised 2026 work programme and budget.
The significance is straightforward. Until gas flows and is sold, Aminex has essentially no operating income, so the pipeline and the Ntorya-2 well are the events that could change the company's revenue profile. The revised budget also confirms that the partners are committing capital to a further development phase beyond the first well.
The financial position
The half-year report shows a business still awaiting revenue. The net loss for the first half of 2026 was US$2.71 million, against US$1.50 million a year earlier. Revenue was only US$14,000, from technical services, and administrative expenses were US$1.00 million.
Cash fell to US$2.23 million from US$3.41 million at the end of 2025, and operating cash outflow was US$1.14 million. The group reported a net current liability of US$4.12 million.
Directors acknowledged a material uncertainty over the company's ability to continue as a going concern. They pointed to previous success in raising funds from shareholders and to anticipated warrant and option exercises in late 2026 and early 2027 as grounds for confidence.
In plain terms, near-term funding depends on shareholders and warrant holders rather than operating cash flow, which is why the timing matters.
Risks and what to monitor
The principal risks disclosed include operator implementation delays, exploration and drilling outcomes, and the availability of financing. Aminex also flagged a dispute with Tanzanian tax authorities over an assessment of US$10.3 million that the company contests.
Investors should watch four things: whether the pipeline is completed and metered in December 2026; whether Ntorya-2 flows as planned after testing; the timing of the Ntorya-Central well; and how the company covers its working capital, including any share placing or warrant exercises. Slippage in any of these would matter given the modest cash balance.
Figures are from company disclosures to 25 September 2026.