A battery project moves centre stage

Ampeak Energy Limited (LSE:AMP), the renewable energy developer formerly known as SAE Renewables, published unaudited interim results for the six months to 30 June 2026 on 23 September 2026. The results showed lower revenue from its MeyGen tidal array while turbines were serviced, but the company highlighted progress at its AW1 battery storage project and a new £7.8m investment into that scheme. The chairman described the company as entering the second half with "significant momentum", while management acknowledged that funding markets remain challenging.

What the company does

Ampeak, incorporated in Singapore with its operational head office in Edinburgh, began life as tidal turbine developer Atlantis Resources and floated on AIM in February 2014. It later became SIMEC Atlantis Energy and then SAE Renewables, before adopting the Ampeak Energy name with effect from 21 August 2025. Its assets include the MeyGen tidal array in the Pentland Firth, Scotland, the AW1 battery energy storage system at the former Uskmouth power station site in Wales, and a pipeline of further storage projects. It also holds a 21% stake in Proteus Marine Renewables, its former turbine engineering arm.

Latest developments

Construction of AW1 progressed during the half, and the company said it was working to deliver the project on time and on budget. After the period end, JB Energy agreed to acquire a 24.7% stake in AW1 Storage Holdings for £7.8m, with Ampeak retaining a controlling 50.6% interest; the transaction was expected to complete in September 2026. Ampeak plans to extend AW1 from two hours to four hours of storage once the current build is finished. Other projects, AW2 and Mey BESS, continue through development, although National Grid's connection reforms have added uncertainty to timelines.

At MeyGen, generation was lower following planned offshore works and the return of one turbine to shore for servicing. Three turbines operated throughout the period, and the team aims to redeploy the serviced unit.

Financial picture

Revenue fell to £2.2m from £3.5m, mainly because of reduced MeyGen output. The loss before tax was £4.7m, broadly in line with the prior period. Operating costs fell to £3.7m from £4.6m, although the earlier figure included a one-off £0.8m adjustment linked to the AW1 land sale. Cash and equivalents stood at £3.6m at 30 June 2026. No dividend is paid, and the company said securing further funding remains a priority.

Sector and index context

Ampeak is one of the renewable energy developers in the FTSE AIM All Share Index. Grid-scale battery storage has attracted solid investor interest in the UK as more intermittent wind and solar capacity comes onto the system, while tidal power remains a smaller, more specialised technology that has historically needed government support.

Key risks

The company is loss-making and reliant on external funding, which management describes as difficult to secure. Construction delays or cost overruns at AW1 would be significant. Grid connection reform may push back other projects, and the development of further MeyGen phases has been described by management as challenging.

What to watch next

Investors will look for confirmation that the JB Energy investment has completed, AW1 construction milestones, MeyGen turbine redeployment and any news on additional funding initiatives. Clarity on grid connection dates for AW2 and Mey BESS would also help indicate how quickly the storage pipeline can be turned into operating, revenue-generating assets, and how much further capital the company may need to raise.