Ceres Power (LSE:CWR) is back in focus because the power problem facing data centres plays directly to the strengths of its solid oxide fuel cell technology. As artificial intelligence drives up electricity demand, operators face long waits for grid connections and new generation. Ceres' fuel cells can generate power on site from Natural Gas today, with a pathway to biogas and hydrogen, and its partners are now explicitly targeting data centres and other energy-hungry sites.
The company has turned that interest into Capital and partnerships. In June 2026 it completed an oversubscribed share placing with gross proceeds of £102.6 million, and its interim results on 23 September showed cash and short-term investments of £172.0 million at 30 June, up from £83.3 million at the end of 2025. Chief executive Phil Caldwell said the time needed to secure new generation and grid capacity was becoming an increasing challenge for customers.
The market reaction to those results was cooler. The shares fell about 4 per cent in early trading on 23 September, to around 414p, as investors focused on a lower gross margin.
A licensing model rather than a manufacturer
Ceres does not build fuel cells at scale itself. It develops solid oxide fuel cell (SOFC) and electrolysis (SOEC) technology and licenses it to large industrial partners, which invest in their own factories. It earns Revenue from licence fees, engineering services and development work, and in time from royalties on stacks and systems its partners sell.
The licensee network is central to the story. Doosan in South Korea started production and sales in 2025 and has now signed its first export contract, a KRW108.7 billion (about £60 million) agreement with Reverion to Supply SOFC stacks for Germany and Europe. Delta Electronics has installed demonstration systems with Taiwan Power Company and confirmed a NTD10.3 billion (about £240 million) factory Investment in Taiwan, with initial shipments expected in 2028. Weichai in China is targeting 200MW of capacity by the end of 2027, while its Subsidiary Baudouin has partnered with EODev on 600kW SOFC systems for Europe. DENSO in Japan has secured JPY35 billion (about £165 million) of government funding for a solid oxide electrolyser demonstrator.
Why data centres matter
The data centre case rests on speed and location. Ceres' SOFCs can be sited next to demand, avoiding years-long grid connection queues. The company also points to a technical advantage: data centre power architectures are moving towards high-voltage direct current systems of around 800V, and stationary SOFC systems generate DC natively. Ceres said this could remove conversion equipment and cut capital costs by $1 million to $3 million per megawatt.
Partnerships have followed. On 26 March 2026 Ceres and Centrica signed a strategic Partnership to deploy solid oxide on-site power for multi-gigawatt commercial and industrial Demand in the UK and Europe, with data centres and AI compute hubs named as key applications. Centrica plans a UK demonstration site for megawatt-scale deployment. In April, Delta Electronics and Centrica agreed an infrastructure partnership targeting data centres and energy-intensive industries. The same month Ceres launched Ceres Endura, its new stack platform designed for gigawatt-scale manufacturing, with a five-year stack life and a shared architecture for power and hydrogen.
Investor enthusiasm has been striking. By May 2026 the shares had risen about 240 per cent year to date and roughly 850 per cent over 12 months, though they remained about half their February 2021 peak.
Interim numbers show progress and pressure
For the six months to 30 June 2026, revenue rose 8 per cent to £22.8 million. Gross Profit slipped 3 per cent to £16.1 million as gross Margin fell to 71 per cent from 79 per cent. The adjusted EBITDA loss narrowed to £6.8 million from £11.3 million, and the operating loss before exceptional items was £13.7 million. The net loss was £16.9 million, against £19.6 million a year earlier.
Cost discipline helped. Ceres said operating costs were 14 per cent lower than in 2025 and R&D spending fell to £18.3 million from £25.6 million.
Management expects about £45 million of contracted revenue for 2026 before any new Business and remains confident of signing one new Manufacturing licensee this year. It said cash projections extend to December 2027, with stress testing showing sufficient reserves under various scenarios.
Ceres has also narrowed its focus. On 26 August it spun out RFC Power, its manganese flow battery business, via a £10 million Series A round led by the British Business Bank, with Centrica and Temasek Trust's Catalytic Capital also investing. The business, rebranded Certain Energy, will pay Ceres a share of future product revenues, and Ceres retains a stake of about 37 per cent.
Risks behind the enthusiasm
The opportunity is large but still mostly prospective. Data centre deployments via Centrica and Delta are at demonstration or early stages, and Delta's factory shipments are not expected until 2028. Revenue remains modest and Ceres is loss-making. The company depends on partners' decisions to build factories and win customers, and Royalty streams will take years to scale.
In May the shares traded on about 17.5 times forward sales, which leaves little room for disappointment. Fuel cells running on natural gas also face scrutiny over emissions until hydrogen or biogas supply is widely available, and competing technologies, including gas turbines, engines and rival fuel cells, are chasing the same data centre demand. The lower gross margin in the first half shows revenue mix can move results sharply.
What to watch
Key milestones include the signing of a new manufacturing licensee, which management has guided for 2026, progress on Centrica's UK demonstration site, Delta's factory build, Doosan's export shipments and Weichai's capacity expansion. No date has yet been set for 2026 full-year results; the 2025 results were published on 26 March 2026.
Final Thoughts
Ceres Power has moved from a hydrogen-era story to one centred on on-site power for data centres, and it now has the partners, product platform and Balance Sheet to pursue that market. The first half showed narrowing losses and a much stronger cash position, but also a lower margin and a business still some way from commercial scale. The next phase depends on converting partnerships and licensee interest into factories, orders and recurring royalties.