Hamak Strategy has moved its Akoko gold project in Ghana from drilling results to a formal resource and, in August 2026, to an independent economic study. The question this article addresses is why the company commissioned that study now, and what its recent funding and balance-sheet moves mean for a small explorer that also runs a Bitcoin treasury strategy.

Gold Explorer With a Digital Treasury

Hamak Strategy Limited (LSE:HAMA), whose shares trade on the Main Market of the London Stock Exchange and on the OTCQB in the United States, describes itself as combining gold exploration in West Africa with a "Digital Asset Treasury Management strategy". Its projects include the Nimba licence in Liberia and an exclusive option over the Akoko gold project in south-west Ghana. Alongside exploration, it holds Bitcoin and physical gold as treasury reserves, and it holds 6,500,000 shares in Vaultz Capital plc following a £1.0 million subscription. The company has also been through a strategic repositioning, having described 2025 as "a transformational year for Hamak" with new management and board members.

A Maiden Resource and a Study Mandate

On 29 July 2026, Hamak announced a maiden independent NI 43-101 mineral resource at Akoko of 210,430 ounces of gold at 0.76 g/t, using a 0.25 g/t cut-off. Measured and indicated resources totalled 103,200 ounces from 3,882,800 tonnes at 0.83 g/t, with a further 107,230 inferred ounces from 5,237,000 tonnes at 0.71 g/t. The company highlighted more than 120,000 ounces of free-digging oxide material within 50 metres of surface at 0.81 g/t, and reported oxide recoveries of 85% to 94% in metallurgical testing.

On 13 August 2026, Hamak said it had selected Snowden Optiro to prepare a Preliminary Economic Assessment focused on an open-pit, heap-leach operation on the upper oxide zones. The study is expected to take three months from start-up and to cover mining, processing, infrastructure, costs and financial modelling. The earlier resource announcement set a target of at least 20,000 ounces a year for a low-capital operation. Hamak's option allows it to acquire 100% of Akoko by December 2026 at US$15 per ounce of gold, including share consideration.

Balance Sheet and Funding

Results for the year to 31 December 2025, published on 5 May 2026 in US dollars, showed a loss of US$1.834 million, cash of US$3.110 million and total Equity of US$3.375 million. The company held 20 Bitcoin at the year end, rising to 26 after the period, and later bought 1.65kg of physical gold.

In July, Hamak agreed an amended £1.66 million non-convertible Loan with YA II PN Ltd, managed by Yorkville Advisors, carrying 4% annual interest and a ten-month Amortisation schedule, together with 165,767,123 warrants exercisable at 1p. It also announced a £200,000 subscription. A Warrant exchange offer then saw 179,906,090 warrants tendered for cancellation in return for 35,981,218 new shares, which the company said reduced potential dilution from those warrants.

Risks and Uncertainties

Akoko's grade is low, so project Economics will depend heavily on heap-leach costs, recoveries and the gold price. Roughly half the resource is inferred, which carries lower geological confidence. The option must be exercised by December 2026, and Hamak does not yet own the project outright. Loan repayments add pressure on cash, while Bitcoin holdings expose the Balance Sheet to crypto-asset volatility. Delivery of the Preliminary Economic Assessment, the option decision and any further financing are the main developments to watch.

Conclusion

Hamak commissioned the Akoko study because its maiden resource identified a shallow oxide component that could suit a low-cost heap-leach operation, and an economic assessment is the next step towards financing and development. The reported figures show a company with modest resources relying on external funding, so the study's findings and the option decision will largely determine the project's path.