LSE:TUN - After eight years idle and a receivership that humbled its first owners, the Devon mine that holds one of the world's largest tungsten deposits is being switched back on. The question now is whether the money lasts until it pays.

A Devon mine wakes up

On the western edge of Dartmoor, the machinery at Hemerdon is turning again. Tungsten West, the Aim-quoted owner of the mine near Plymouth, told the market on 8 July that the first phase of recommissioning had begun and that a phased production ramp-up would start later in the month. It is the most concrete signal yet that a project written off as a cautionary tale is genuinely coming back to life.

The history weighs heavily. Hemerdon, the second-largest tungsten resource in the world, produced between 2015 and 2018 under previous owner Wolf Minerals before running out of cash and collapsing into receivership. Tungsten West, incorporated in 2019, bought the asset and spent years re-engineering the processing flowsheet that had defeated its predecessor. The restart is, in effect, the second attempt to make one of Britain's few strategic-metal mines pay.

According to the company's guidance, the sequence runs through the rest of 2026: the fines gravity circuit and Downstream facilities are being recommissioned in the third quarter, the coarse gravity circuit follows in the fourth, and full project commissioning is targeted for the first quarter of 2027. Management says the work remains on track and within budget, though those are guidance markers rather than delivered milestones.

The prize: tungsten and tin at scale

The reason investors keep circling Hemerdon is the sheer size of the orebody. Tungsten West describes a resource capable of an operating life measured in decades, producing an average of roughly 2,900 tonnes of tungsten and 310 tonnes of tin a year once the plant reaches its designed 500-tonnes-per-hour throughput. That would, on the company's own framing, make Hemerdon the largest tungsten producer in the Western world.

The metal itself is unglamorous but strategically loaded. Tungsten's extreme hardness and the highest melting point of any metal make it essential to cutting tools, armaments, aerospace and electronics. There is almost no meaningful Western primary production, which is precisely why governments in London, Brussels and Washington list it as a critical raw material. A working mine in Devon is therefore as much a supply-security story as a Mining one.

The Economics were re-cut in an August 2025 feasibility study that assumed a tungsten price of US$400 per metric tonne unit and tin at US$32,500 a tonne. In its subsequent updates the company said prevailing prices had moved well above those assumptions, a tailwind that, if it holds, materially improves the Margin on every tonne processed. Commodity prices, of course, do not stand still, and the plant has to run before any of it is banked.

China's grip and the security premium

Hemerdon's revival cannot be separated from what has happened to the tungsten market. China accounts for the overwhelming majority of global mined tungsten and refined output, and Beijing's tightening of export licensing on tungsten and other strategic minerals through 2025 sent Western buyers scrambling for non-Chinese units. Prices climbed and, more importantly for a developer, so did the willingness of industrial and defence customers to pay for security of supply.

That backdrop is the strongest part of the Investment case. A tonne of concentrate mined in Devon, outside Chinese Jurisdiction and inside a friendly permitting regime, carries a premium that a comparable tonne from a lower-cost jurisdiction may not. UK planning and environmental permits for Hemerdon are already in place, removing a category of risk that sinks many mining projects before they start. A fully cash-funded £13.2m restoration bond underpins the environmental commitments.

Funding: bridged, but not yet finished

The harder question is money. Restarting a mothballed plant is capital-hungry, and Tungsten West has leaned on a mix of Equity and Debt to get there. In February the company raised roughly £44.4m gross through a placing, subscription and heavily oversubscribed retail offer priced at 18p a share, taking its issued share count past a billion ordinary shares. For existing holders that was meaningful dilution, the recurring cost of keeping a pre-revenue developer alive.

On the debt side, the group secured about £22.3m of mining-equipment finance for its Komatsu fleet and, in May, arranged a US$25m short-term bridging Loan from an entity controlled by substantial Shareholder Gregory Coffey. That Facility is unsecured, repayable without penalty and priced at roughly 8% and rising, buying time while a larger package is finalised. The company said a longer-term debt facility of up to US$85m had cleared Due Diligence and was being documented, with proceeds earmarked to repay the bridge and fund the remaining works.

Cash stood at £25.5m at the end of March on an unaudited basis, against early tungsten sales of just £0.6m. The arithmetic is straightforward and unforgiving: the equity and bridging money must carry the project until the larger facility closes and, ultimately, until concentrate sales generate real cash. Any slip in the commissioning timetable, or a delay in signing the US$85m package, would tighten that runway quickly.

What to watch next

The near-term catalysts are unusually clear-cut. First is confirmation that the fines gravity circuit is producing saleable concentrate on schedule this quarter; first, sustained output is the event that turns a promise into a business. Second is the closing of the up-to-US$85m debt facility, which would remove the most immediate financing overhang and refinance the Coffey bridge. Third is evidence that throughput is climbing toward nameplate without the process bottlenecks that undid the previous owner.

Recruitment offers a rough gauge of intent: the company said it had already taken on more than 100 people and is aiming for around 350 by early 2027, drawn largely from the local labour market. A senior operating team, including a chief operating officer with decades of mining experience, has been assembled to run the ramp-up.

For all the strategic tailwinds, this remains a high-risk, binary situation. The shares, which changed hands in the high-30s pence recently for a Market Value of roughly £470m, already price in a successful restart against a backdrop of elevated tungsten prices. If commissioning proceeds and the debt lands, Hemerdon could become the West's benchmark tungsten mine and a rare example of a British critical-minerals project reaching production. If the plant stumbles or the financing stalls, shareholders have seen how this story can end. After eight years of silence, the machinery is running again; the next two quarters will show whether it can keep running.