LSE:HWG - Harworth Group grew out of the remains of British Coal. For years it took collieries, spoil heaps and old power station sites across the North and the Midlands, cleaned them up and got them through planning. It then sold serviced land to housebuilders and built warehouses for its own rental portfolio. It now manages about 14,000 to 15,000 acres across roughly 100 sites, and that landbank is why it faces a hostile bid.
In 2026 Harworth's most valuable asset has become access to electricity. It has around 0.8GW of accepted grid connection offers, and data centre operators pay a lot for powered land. In September management said it would leave housing altogether and focus on powered land and industrial and logistics (I&L) property. Weeks earlier Peel Holdings, which already owned close to 30% of the shares, had made an unsolicited cash offer. The board rejected it.
Investors now have to choose between a cash price today and a data centre pipeline that has not yet paid out.
How the Business makes money
Harworth earns money in three ways. The first is land sales. It buys or Options large, messy sites, sorts out remediation, infrastructure and planning, and sells serviced plots at a profit. The second is development. It builds I&L units, often pre-let, which it either keeps or sells. The third is rent from its Investment Portfolio, which was valued at £301.4m at 30 June 2026 and produced £15.5m of annualised rent.
Most of the value is made at the planning stage, when a derelict site is consented and connected to the grid. That is why EPRA net disposal value (NDV) matters more than yearly earnings, which come in lumps as deals complete.
Recent performance
In the year to 31 December 2025, Revenue fell to £129.8m from £181.6m, profit before tax dropped from £69.4m to £17.4m and basic EPS fell from 16.86p to 2.81p. EPRA NDV per share still edged up to 224.4p and the total Dividend rose 10% to 1.775p. Net Debt rose to £145.9m, a net loan-to-value of 15.6%.
The six months to 30 June 2026 were harder. Revenue fell to £41.3m and there was a pre-tax loss of £31.4m, against a £7.4m profit a year earlier, with a basic loss per share of 7.8p. EPRA NDV per share fell 4.3% to 214.8p. Net debt reached £190.0m (LTV 20.3%) and Liquidity fell to £99.5m. The Interim Dividend still rose 10% to 0.592p.
Leasing was stronger. Three pre-lets totalling 319,300 sq ft, completed or in legals, will bring in £3.7m of annualised rent, 17% above estimated rental value. A further 1.5m sq ft is under negotiation.
Strategy and catalysts
Data centres are now the main theme. In 2024 Harworth agreed a £106m two-plot powered land sale to Microsoft at Skelton Grange in Leeds, where councillors resolved in April 2026 to grant planning for a hyperscale campus of about 500,000 sq ft. Harworth expects £53.2m when the second plot completes. After the period end it entered exclusivity with a data centre provider on a second site and is aiming for a conditional exchange in the fourth quarter of 2026. Management has identified up to six hyperscale sites and cites a JLL estimate of £293m of potential future profits, which assumes planning, power and ownership are all secured.
A programme announced on 15 September 2026 targets £7.4m of annual run-rate savings by the end of 2028. That is about a fifth of 2025 administrative expenses, at a one-off cost of £3.85m. The residential exit should release capital, and the board has said surplus cash could be returned. In September 2026 it also sold a strategic site in St Helens to Tritax Big Box Developments at book value.
The bid is the most immediate catalyst. Peel offered 172.5p a share on 6 August 2026 and raised it to 177.5p on 16 September. That values Harworth at about £600m, a 40% premium to the three-month volume-weighted average price of 126.8p, according to Peel. Peel's stake reached 30% on 17 September, which made the bid a mandatory offer. Acceptances close on 25 October 2026.
Valuation talking points
The main argument is about the discount to NDV. Harworth's board says 177.5p is 17.4% below June's NDV of 214.8p per share and "significantly undervalues" the company. Peel says the market valued the shares well below NDV for months before the bid. It points to falling NAV, higher borrowing and a capital-constrained balance sheet, and it calls the new strategy not credible. Peel's 30% stake would make a rival bid difficult. Shareholders who reject the offer also need to consider where the shares might trade if it lapses.
The bull case
- 0.8GW of accepted power offers is scarce in the UK, and one hyperscale deal can move NDV noticeably.
- The Microsoft plot 2 completion (£53.2m) and a possible Site 2 exchange are specific, dated catalysts.
- Leaving residential and cutting £7.4m of costs should simplify the group and free Capital that could be returned.
- Pre-lets above estimated rental value suggest Demand for northern I&L space is firm.
- Peel's bid shows a well-informed rival values the landbank.
The bear case
- NDV per share fell in the first half and there was a statutory loss, so value is not compounding at present.
- Borrowing is rising, with LTV at 20.3% in June and liquidity lower.
- Data centre profits depend on planning, power, contracts and timing. The JLL figure is a scenario, not a forecast.
- Earnings depend on when lumpy deals complete, and a slower market could keep the shares at a discount.
- If the offer lapses, the shares could fall back towards their pre-bid level.
The bottom line
Harworth still makes money by fixing old industrial land and selling or developing it. The difference is that the buyer is now more often a data centre operator than a housebuilder. The first half of 2026 showed the cost of that shift, with falling NDV, higher debt and a loss. It also pointed to the upside, with Microsoft, a second hyperscale counterparty and up to six powered sites.
Peel is offering a certain 177.5p, below book value, now. The board believes waiting for the pipeline is worth more. The things to watch are whether Site 2 exchanges in the fourth quarter, whether the Skelton Grange money arrives, and how much of the register rejects Peel before 25 October.