Aminex Plc (LSE:AEX) has spent two decades trying to turn its Tanzanian gas discoveries into cash flow, and 2026 was meant to be the year it finally happened. Instead, the summer brought a public falling-out with the operator of its flagship Ntorya project, a formal Notice of Dispute and the intervention of Tanzania's Ministry of Energy. On 2 September 2026 the company announced a revised implementation programme, with first gas now targeted for December 2026.
For a London-listed micro-cap that generated just US$0.05m of Revenue in 2025, the question is stark: is Aminex a carried gas developer months from its first meaningful income, or a minority partner whose timetable depends on a counterparty it has just threatened with arbitration?
Latest development: Ministry-brokered deal resets Ntorya timetable after Notice of Dispute
The 2 September 2026 announcement followed a meeting convened on 26 August by Tanzania's Ministry of Energy, attended by the Petroleum Upstream Regulatory Authority, the Tanzania Petroleum Development Corporation (TPDC), operator ARA Petroleum Tanzania Limited (APT) and Aminex's Subsidiary Ndovu Resources. The revised schedule provides for a workover of Ntorya-1 in October 2026, testing of Ntorya-2 in November, drilling of a new Ntorya-Central well and completion of the Ntorya to Madimba pipeline in December, and first gas from Ntorya-1 and Ntorya-2 in the same month. Chikumbi-1 is to be drilled after Ntorya-Central. APT confirmed it has "all necessary funds to carry out the revised programme".
The agreement caps a fraught seven weeks. On 14 July 2026 Aminex disclosed that APT, after management changes and a technical reappraisal, had sought material cuts to the approved 2026 work programme that would delay first gas and postpone Chikumbi-1. On 21 August Ndovu served a Notice of Dispute on APT and its parent, The Zubair Corporation, alleging that APT had failed to implement the approved programme and done minimal substantive work in 2026. The notice triggered a 90-day resolution period, after which Ndovu may go to the London Court of International Arbitration and call on Zubair's Parent Company guarantee.
Executive chairman Charles Santos called the revised programme "important progress towards resolving the matters that gave rise to the Notice of Dispute". The announcement did not say the notice had been withdrawn.
Business overview: a non-operated stake in Tanzania's next onshore gas field
Aminex is a Dublin-headquartered upstream gas company whose shares trade on the London Stock Exchange's Main Market as CREST depository interests. Its sole material asset is a 25% non-operated interest in the Ruvuma production sharing agreement in southern Tanzania, held through Ndovu Resources. APT operates the licence under a 2020 farm-out that gives Aminex a carry of up to US$35m net on development spending. At 31 December 2025, US$28.42m of that carry remained, which the company says should be sufficient to reach commercial production.
Ntorya holds a 25-year development licence and a gas sales agreement signed in 2024. The development plan envisages initial output of around 60 million cubic feet per day (MMcfd) from three wells, rising in phases to a 280 MMcfd plateau over more than 20 years, delivered via a 35km, 14-inch pipeline to the Madimba processing Facility for Tanzania's domestic market.
Aminex also holds a 63.83% operated interest in Kiliwani North and 100% of the Nyuni Area PSA, both fully impaired; any spending there depends on Ntorya revenues and a new partner.
Financial performance: losses narrow, Balance Sheet debt-free after October 2025 placing
Aminex reports in US dollars. For the year ended 31 December 2025, revenue was US$0.05m (2024: US$0.04m), from minor oilfield services rather than gas sales. The operating loss narrowed to US$2.89m from US$5.20m, while the loss after tax was US$4.98m against US$5.30m, including a non-cash US$1.56m accounting loss on warrants issued with the October 2025 fundraising. Administrative expenses were US$1.85m (2024: US$1.77m).
Cash at 31 December 2025 stood at US$3.41m, up from US$1.13m a year earlier, after the company raised US$3.94m gross by placing 249.3m new shares at 1.5 pence each in October 2025. A US$1.60m Loan from Eclipse was converted into Equity at the same time, leaving the group debt-free. Shares in issue totalled 4,468,501,044 at year end.
Management said the company was "fully funded through to anticipated revenues from first gas". However, the Annual Report also noted that current liabilities exceeded current assets, partly because of unresolved Tanzania Revenue Authority claims, for which provisions have been booked where an appeal was judged unlikely to succeed. No Dividend is paid.
What could drive the stock next?
The calendar is now unusually specific. Investors will look for confirmation that the Ntorya-1 workover starts in October, that Ntorya-2 testing follows in November, and that the Ntorya-Central spud and pipeline commissioning land in December. First gas in December 2026 would transform Aminex from a cash-consuming explorer into a carried recipient of production revenue.
Progress on Chikumbi-1, the mandatory obligation well under the farm-out, would remove the central point of contention with APT. Resolution of the Notice of Dispute, whether by withdrawal, settlement or a move to arbitration once the 90-day window closes in late November, will also shape sentiment. The 2026 half-year report, due in the autumn, should update cash and the remaining carry balance.
Risks investors should watch
Operator risk is now the dominant issue. Aminex does not control the pace of work at Ntorya, and the summer dispute showed how quickly a change of management at APT can upend an approved budget. The revised programme remains a schedule rather than a delivered outcome, and first gas has already slipped from late third-quarter 2026 to December.
Financial resilience is thin. Cash of US$3.41m at the end of 2025 against annual administrative costs of about US$1.85m gives limited headroom if first gas slips into 2027, and a further equity raise would dilute a share count already above 4.4bn, on top of the October 2025 warrants. Current liabilities exceeding current Assets and unquantified Tanzanian tax claims deserve scrutiny.
Arbitration, if it proceeds, would be lengthy and costly and could sour the relationship on which the project depends. Aminex also carries single-asset concentration in Tanzania, where fiscal terms, gas pricing and domestic Demand sit outside its control, and gas prices under the 2024 sales agreement have not been disclosed.
Outlook
Aminex enters the final third of 2026 with a clearer path than it had a fortnight ago, but with its credibility staked on a compressed, operator-led timetable. If the October to December milestones are met, the company will finally have production revenue, a remaining carry balance and no debt. If they are not, the Notice of Dispute and the parent company guarantee become the story instead.
The Ntorya-1 workover in October is the first checkpoint; the half-year report and the expiry of the 90-day dispute window in November are the next. Until gas flows, Aminex remains a high-risk, binary situation rather than a proven business.