LSE:KEFI - The AIM-listed developer says spades are in the ground at its Ethiopian gold project and a US$240m senior-debt Facility could be drawn from the fourth quarter. With gold above US$4,300, the prize has rarely looked bigger - or the execution risk sharper.
Boots on the ground, big money still to come
For the best part of a decade, KEFI Gold and Copper has been a story about what might happen at Tulu Kapi, a 1.7-million-ounce gold deposit in the highlands of western Ethiopia. In its 4 August operational update the company argued the story has changed tense. It is now in the fourth month of a 27-month development programme, with house-building for resettlement, an electrical substation and a new access road all under construction.
That is a meaningful shift from the years of feasibility studies and financing talks that preceded it. But investors should be precise about what has started. The work under way is early enabling and resettlement construction, not full mobilisation of the plant and open pit. The heavier lifting - and the bulk of the roughly US$355m Capital bill - is gated on the drawdown of senior project debt, guided to a trigger in the fourth quarter of 2026. Tulu Kapi has moved into construction mode, not yet full construction.
A US$355m jigsaw nears completion
The financing package is the pivot on which everything turns. KEFI puts the total project funding requirement at around US$355.6m, including a US$15m contingency reserve, and says committed funding now broadly matches that figure. The centrepiece is roughly US$240m of secured Debt underwritten by the Africa Finance Corporation and the Eastern and Southern African Trade and Development Bank, with secured lenders providing close to 70% of the total. KEFI shareholders have contributed the Equity slice - about US$85m, or a fifth of the package - with the balance filled by contractor and Royalty financing.
Recent housekeeping has tidied the edges. KEFI replaced a US$15m working-capital facility with US$10m of royalty financing and US$5m of Ethiopian preference shares, and won regulatory clarification allowing historical exploration spend to count as equity for gearing purposes - useful for the lenders' debt-to-equity tests. A US$400m mining-services agreement with contractor BCM covers the initial nine-year mine life, and BCM is mobilising its Caterpillar fleet. More than half of the major processing equipment - mills, crushers and plant components - is ordered or ready to order.
The remaining hurdles are procedural rather than commercial. At its June annual meeting the company flagged a resolution to lift the borrowing limit in its articles as a condition precedent to drawdown, which shareholders backed. But the point stands: until conditions precedent are satisfied and the first Tranche is actually drawn, the debt is committed rather than in the bank.
Resettlement is the critical path
The single biggest reason Tulu Kapi has taken so long is not geology or gold price - it is people. The project requires relocating communities living on the deposit, a process KEFI has run to World Bank IFC Performance Standards. That discipline reassures development-finance lenders, but it also lengthens the timetable and sits squarely on the critical path.
Here the update was genuinely encouraging. KEFI says Phase 1 resettlement is substantially complete, with 100% of compensation agreements with affected landholders now concluded, and the Phase 2 Resettlement Action Plan - covering the Mining and pit areas - has begun. A charitable endowment is funding community initiatives including plant nurseries and agricultural schemes. Delivering Phase 2 cleanly is what unlocks the pit; any slippage there would ripple straight through to first gold.
The wider Ethiopian backdrop remains the elephant in the room. Tulu Kapi lies in Oromia, a region that has seen episodes of insecurity in recent years, and Ethiopia carries an elevated country-risk profile for lenders and insurers. KEFI has structured the financing and security arrangements around those risks, but they are not eliminated. This is a frontier-jurisdiction development, and should be priced as one.
Saudi Arabia: the quieter second leg
Ethiopia dominates the narrative, but KEFI's 13.35% stake in Gold & Minerals Co (GMCO), its Saudi joint venture with ARTAR, is the optionality. Management has repeatedly argued that the aggregate gold-equivalent production potential of the Saudi Assets could exceed Tulu Kapi over time.
At Jibal Qutman, the definitive feasibility study is nearing completion and a mining-licence application has been submitted, with a possible first-stage development decision in 2026 on an open-pit, carbon-in-leach operation carrying an estimated US$100m capital cost. At the polymetallic Hawiah project, resources have grown to 36.2m tonnes spanning copper, gold, silver and zinc, and GMCO has expanded via a joint venture with Hancock Prospecting over the Al Hajar North belt. None of this is imminent for KEFI's cash flows, but it offers a second, lower-risk Jurisdiction and a pipeline beyond a single mine.
Gold tailwind, dilution headwind
The macro could hardly be more supportive. Gold traded around US$4,362 an ounce on 19 August, up roughly 30% over the past year. Against a Tulu Kapi ore reserve of 1.05m ounces at 2.7g/t, near-94% recovery and baseline output of about 166,000 ounces a year (rising toward 200,000 with a later underground phase), the Economics on paper are transformed versus the prices assumed at sanction.
The catch is the cost of getting there. KEFI ended 2025 with just £8.8m of cash and reported a £9.7m loss, and has leaned heavily on equity - including a £35.6m raise in April 2026 - to keep moving. The weighted-average share count runs to roughly 8.9bn, and the stock trades near a penny for a Market Value around £145m. Shareholders have been diluted repeatedly to reach the start line; the payoff crystallises only if debt drawdown, construction and ramp-up all land on schedule. The shares have roughly doubled over the past year, reflecting both the gold rally and rising conviction that the financing is real.
What to watch
The next few months are the most important in KEFI's history. The hard catalyst is the Q4 2026 senior-debt drawdown; clearing the remaining conditions precedent and drawing the first tranche would convert Tulu Kapi from a funded plan into a mine under full construction. Alongside it, watch for Phase 2 resettlement progress, further equipment orders and BCM's fleet mobilisation.
Two corporate items add colour: KEFI is targeting a move from AIM to the London Stock Exchange's Main Market by year-end 2026, and a GMCO development decision on Jibal Qutman is possible before then. Commissioning is targeted for late 2027 and first gold for mid-2028. Investors have heard timelines from KEFI before; this time the company insists the machines are being ordered and the money is committed. The market's willingness to keep backing it will hinge on whether that fourth-quarter drawdown arrives on cue.