LSE:NG. - Britain's grid was built for coal power stations, not North Sea wind farms and data centres. Moving power to where it is needed means new pylons, cables and substations, and National Grid owns much of the high-voltage network that has to carry it. It is now in the middle of the largest Investment programme in its history.

In March 2026 the group set out a five-year framework of at least £70bn of Capital Investment to 2030/31, around £31bn of it in UK electricity transmission. It also accepted Ofgem's RIIO-T3 price control for April 2026 to March 2031, which management says should nearly double its transmission capacity. For a regulated utility, profits follow the size of the asset base, so every pound spent on approved projects should earn a return set by the regulator.

The harder question is whether it can build all of this on time and on budget while keeping its Balance Sheet in good shape.

How the Business makes money

In the UK, National Grid owns the high-voltage transmission system in England and Wales and runs National Grid Electricity Distribution, which serves nearly 8 million customers in the Midlands, the South West and Wales. Ofgem sets allowed revenues based on the regulated asset base, an allowed return and efficiency incentives.

In the US it is the largest Utility in New York State and the second largest in Massachusetts, with around 4.2 million and 3.2 million customers respectively. Revenue is set through state rate cases, with transmission returns overseen by the Federal Energy Regulatory Commission (FERC). National Grid Ventures holds interconnectors and other non-regulated infrastructure.

Recent performance

In the year to 31 March 2026, underlying operating profit came in at £5,680m, up 6% at constant currency. Underlying Earnings Per Share rose about 8% to 78.0p. On a statutory basis, operating profit was £5,431m (up 10%) and EPS was 65.5p. The full-year Dividend was lifted 3.8% to 48.49p.

Capital spending rose 18% to £11.6bn, including £4.4bn in UK transmission, £3.4bn in New York, £2.0bn in New England and £1.6bn in UK distribution. Regulated asset growth reached 11.7%.

The group sold National Grid Renewables in May 2025 and the Grain LNG terminal in November 2025, booking a £489m exceptional gain on Grain. Net Debt rose to £44.2bn at 31 March 2026 from £41.4bn, and funds from operations to net debt slipped to 13.0% from 13.7%, while regulatory gearing held at 61%.

Strategy and catalysts

For 2026/27, management expects underlying EPS to grow 13–15%, helped by higher allowed revenue under RIIO-T3, with capital investment of about £13bn. To 2030/31 it targets around 10% annual asset growth and 8–10% compound underlying EPS growth from the 78.0p base, with the dividend growing in line with UK CPIH. The framework assumes 25% scrip take-up and no new Equity issuance.

Delivery is now the priority. In August 2026 chief executive Zoë Yujnovich announced a simpler operating model from 1 September, cutting the executive committee from 13 members to 8. A Global Capital Delivery team was created under Carl Trowell, with single presidents for the UK (Cordi O'Hara) and the US (Sally Librera, on an interim basis).

In July 2026 National Grid Ventures agreed to invest $1.75bn for a 35% stake in Joulent, a US developer of power for data centres. Its first project, Kilby, is a 2.67GW Facility in West Texas developed with Chevron, with Microsoft as a 20-year offtaker. The investment sits outside the £70bn plan, with a final investment decision expected by the end of 2026.

Upcoming milestones include a Massachusetts gas rate case order expected in November 2026, the UK distribution (ED3) price control, and National Grid's challenge to a March 2026 FERC order on base returns.

Valuation talking points

On 23 September 2026 the shares traded at around 1,148p, according to Google Finance, a Market Value of roughly £58bn and a Dividend Yield of about 4.2%. That is just under 15 times 2025/26 underlying EPS, and below the 52-week high of about 1,429p.

Investors are weighing a fast-growing, inflation-linked asset base against the cost of funding it. Net debt is expected to climb by around £6bn in 2026/27 to about £50bn, and regulatory gearing is heading towards the high-60% range by 2030/31. Gilt and Treasury yields will shape how the market prices that trade-off.

The bull case

  • A clearly signposted £70bn-plus plan with about 10% annual asset growth, much of it already backed by regulatory settlements such as RIIO-T3 and the three-year Niagara Mohawk rate deal.
  • Guidance for 13–15% underlying EPS growth in 2026/27 and 8–10% a year to 2030/31, which is unusually fast for a utility.
  • A dividend policy linked to CPIH, which offers some protection against inflation.
  • Structural Demand from electrification and data centres, with the Joulent deal adding contracted exposure outside the regulated returns.

The bear case

  • Projects of this size risk delays, supply-chain bottlenecks, planning objections and cost overruns.
  • Net debt heading towards £50bn and rising gearing leave less room if returns disappoint or interest rates rise.
  • Scrip dividends and a dividend growing only with Inflation mean per-share income growth may trail earnings growth.
  • Regulatory and political risk in both countries, from the FERC return dispute to affordability pressures in US rate cases and UK bills.
  • The Joulent investment adds exposure to US power generation, which is different from the group's core network business.

The bottom line

National Grid is spending billions to rewire Britain because the energy transition needs new network capacity, and because regulated capital spending is how a networks business grows. The 2025/26 results and the RIIO-T3 settlement give the plan a credible base.

The thing to watch is execution. Projects must land on time and on budget, Credit metrics must hold as debt rises, and regulators must keep allowing fair returns. If they do, the asset base should compound steadily; if not, the debt will get more attention than the growth.