A self-funded build

James Latham (LSE:LTHM) has made no announcements since a directors' dealing notice on 4 September 2026, and its interim results are due on 26 November. Its latest trading information is the AGM statement of 19 August, and its latest audited figures are the preliminary results of 2 July for the year to 31 March 2026. Rather than revisit margins or pricing, this article examines the single largest call on the group's money: the National Distribution Centre, which the company is paying for from its own cash rather than borrowing.

What the accounts show

In the year to March 2026, purchases of property, plant and equipment almost doubled to £26.3m from £13.5m, and the carrying value of property, plant and equipment rose to £72.2m from £49.9m. Net cash from operations was £19.3m, up from £17.0m, which did not cover that spending once dividends of £7.1m and Lease payments of £1.8m were included.

As a result, cash and cash equivalents fell by £14.3m to £51.2m, as reported in the cash flow statement. The group (LSE:LTHM) carries virtually no bank debt: interest-bearing borrowings were £0.4m at the year end, after a £3.6m short-term Facility from the previous year was cleared. Net Assets increased to £232.3m from £220.5m.

Lower cash dividends helped: £7.1m was paid in the year compared with £15.9m in the prior year. The board nonetheless raised the ordinary payout, declaring a final Dividend of 28.6p, which absorbed about £5.8m when paid on 21 August, for a total of 36.70p against 35.25p.

The cost of spending cash

A smaller cash balance earns less. Finance income fell to £3.45m from £4.44m, which helps explain why pre-tax profit rose only to £25.1m from £24.3m even though operating profit improved to £22.0m from £20.2m. Finance income still contributed about 14% of pre-tax profit, so further reductions in cash would weigh on reported Earnings unless operating profit keeps rising.

Working capital also absorbed funds. Inventories increased to £72.9m from £65.7m, and receivables rose with sales, although the company (LSE:LTHM) said debtor days were unchanged and Bad Debts remained low at 0.10% of revenue.

Progress on the project

At the AGM in August, the chair said construction was progressing according to plan and within budget, with completion still expected by the end of 2026 and full operation by the end of 2027. The company has not disclosed the total budget in the announcements reviewed. Alongside the build, Latham is extending its Warehouse management system: after Thurrock and Hemel Hempstead, it planned to add the Purfleet timber site later this year, before embedding the software in the new centre, with every depot covered within three years.

Trading has supported the spending. Revenue for the four months to 31 July 2026 was £146m, up 9.8%, with volumes up 5.6%, and the company said net profit was in line with market expectations.

Factors to watch

Without a disclosed budget, investors cannot judge how much spending remains, though the timetable implies that a material part of the build falls in the current financial year. The chair has acknowledged the need to bed in activities at the new site before chasing new opportunities, so the benefits may arrive gradually. Customer confidence was described as slightly softer than a year earlier, and price increases linked to energy and oil costs have levelled out, removing one support to revenue growth.

What to watch on 26 November

The interim results for the six months to 30 September 2026 should show the half-year capital expenditure, the cash balance and finance income. They may also show whether the 36.70p annual dividend, covered 2.5 times by earnings last year, remains comfortably funded alongside the build. Any update on the completion date for the new building would also be closely watched.