Anglo Asian Mining PLC (LSE:AAZ) has spent the past year transforming from a small Azerbaijani gold producer into a copper-led, multi-mine operator, and the numbers are catching up with the narrative. Half-year copper output to 30 June 2026 was more than seven times the prior-year figure, net cash reached $57.6m, and a US 4 cent final Dividend for 2025 was paid on 27 August 2026.
The question now is whether the next leg of the story comes from the ground rather than the mill. A 90,000-metre drilling programme announced on 22 June 2026, alongside feasibility studies at the Xarxar and Garadag copper deposits, sets up a pipeline of potential resource news from late 2026 into 2028.
Q2 and H1 2026 update: copper output surges as net cash builds
The most recent material announcement came on 15 July 2026 with the Q2 and H1 2026 production and sales update. Second-quarter copper production reached 5,129 tonnes, against 654 tonnes in Q2 2025, with 3,250 tonnes from the new Demirli open pit and 1,879 tonnes from Gedabek. Gold output was 6,272 ounces (Q2 2025: 6,086 ounces) and silver 50,059 ounces (32,033 ounces).
For the half year, copper production was 8,840 tonnes (H1 2025: 1,188 tonnes), gold 12,329 ounces (12,114 ounces) and silver 92,855 ounces (62,348 ounces). Concentrate sales totalled $125.9m, split $71.4m from Demirli and $54.5m from Gedabek, and 7,126 ounces of bullion were sold at an average $4,664 per ounce. Six months of concentrate sales alone exceeded the group's entire FY2025 revenue.
Cash at 30 June 2026 stood at $69.8m, up from $37.2m three months earlier, while Debt fell to $12.2m from $19.5m, leaving net cash of $57.6m, plus $28.9m of unsold inventory. Chief executive Reza Vaziri said: "The ramp-up at Demirli continues to progress in line with our expectations, and will be completed during this quarter." Full-year 2026 guidance of 20,000 to 25,000 tonnes of copper, 28,000 to 33,000 ounces of gold and 170,000 to 210,000 ounces of silver was reiterated.
From single-mine gold producer to Azerbaijan's copper developer
Anglo Asian Mining is an AIM-quoted gold, copper and silver producer operating exclusively in Azerbaijan under a production sharing agreement (PSA) with the government, first signed in 1997 and most recently amended in June 2024. It holds eight contract areas covering 2,544 square kilometres in the west of the country, including Gedabek, Demirli, Xarxar and Garadag.
Revenue comes from two streams: gold and silver doré from the Gedabek contract area, sold as bullion, and copper concentrate from Gedabek's flotation plant and from Demirli, sold to offtakers. The Gilar underground mine at Gedabek began production in May 2025, and the Demirli open pit in the Karabakh region, leased from state-owned AzerGold CJSC at a base rent of $24m a year on a three-year renewable term, started up in July 2025.
The state's effective Royalty under the PSA is 12.75% for both mines through 2026, with the Gedabek rate expected to rise to about 18% thereafter. The group employs roughly 1,400 people.
FY2025 results: Revenue triples and the dividend returns
Full-year results for the twelve months to 31 December 2025, published on 26 May 2026, showed revenue of $122.8m, up from $39.6m in FY2024, with bullion contributing $68.3m ($37.1m) and copper concentrate $54.5m ($2.5m). Profit before tax was $25.8m, reversing a $21.3m loss, and Operating Cash Flow rose to $46.7m from $8.6m. Net cash at 31 December 2025 was $2.6m, against net debt of $14.7m a year earlier.
Production for 2025 was 25,061 ounces of gold (FY2024: 15,073 ounces), 7,915 tonnes of copper (377 tonnes) and 153,333 ounces of silver. All-in sustaining costs were not reported because both new mines began mid-year; 2026 guidance is $1,500 to $1,800 per ounce for gold and $6,800 to $7,800 per tonne for copper, excluding Demirli Lease costs of roughly $1,000 per tonne.
The board declared a final dividend of US 4 cents per share, paid on 27 August 2026 at a sterling equivalent of 2.9956 pence. Mr Vaziri described 2025 as "a historic year" in which the company "achieved the first milestone of our growth strategy, becoming a multi-asset producer".
What could drive the stock next?
The resources angle is the most tangible catalyst. Of the 90,000 metres of core drilling planned for 2026 and 2027, around 55,000 metres is exploration, targeting extensions at Xarxar, Garadag and Demirli, follow-up work across the Gedabek contract area and underground drilling at Gilar. Demirli's 56.35 million tonne estimate at 0.41% copper, dated 1 January 2026, is a non-JORC internal figure, so any independently verified update would be a notable milestone. Xarxar drilling has started with two rigs and Garadag drilling is due to begin in Q3 2026.
Worley Europe is conducting feasibility studies on Xarxar (due mid-2027) and Garadag (due H1 2028), assessing heap leach and SX-EW technology to produce copper cathode on site. Together with Zafar, these underpin a strategy targeting 50,000 to 55,000 tonnes of copper a year by 2030.
Nearer term, completion of the Demirli ramp-up and the Gedabek flotation upgrade will determine whether 2026 guidance is met, and interim results for the six months to 30 June 2026 should give the first full profit read-across from the new production base. Copper and gold prices remain a lever in both directions.
Risks investors should watch
Country concentration is the defining risk: every asset sits in Azerbaijan, including Demirli in the Karabakh region, and the group depends on the PSA and its relationship with the state and AzerGold. The Demirli lease is a fixed $24m annual cost, and the rising Gedabek royalty from end-2026 will trim margins there.
The growth plan is capital-intensive and rests on feasibility studies that will not conclude until 2027 and 2028; no Capital cost estimates for Xarxar or Garadag have been published, so the funding need for three new mines is unknown. Tailings capacity at Gedabek also needs watching: the final raise of the existing dam gives only two to three years of headroom and a second dam still needs government approval.
The shares were suspended for a day in November 2025 after bulletin-board speculation about ACG Metals, which later confirmed it would not bid; that episode and a 52-week range of 177p to 435p underline the stock's volatility. Metal price swings and FX on dollar-declared dividends are further considerations.
Outlook
At around 407.5p and a Market Capitalisation of about £476m in early September 2026, Anglo Asian now trades as a copper growth story rather than a marginal gold miner. The half-year data suggest the operating base is in place; the next test is converting it into reported profit at the interims and delivering 2026 guidance.
Beyond that, watch for the first assays from Xarxar, the start of Garadag drilling, any move to bring Demirli's resource onto a JORC-compliant footing, and the tailings and royalty developments at Gedabek. Whether a fresh resources catalyst is around the corner will depend on how quickly the drill bit turns into published numbers.