Hot commissioning has begun at the Azteca processing plant at the Amapá Iron Ore Project in Brazil, where Cadence Minerals (LSE:KDNC) holds an indirect 36.2% interest. The plant is initially running at 25–50% of capacity. The eventual target is about 380,000 tonnes a year of 65% Fe concentrate, and first shipment is targeted for the end of 2026, subject to an Operating Licence.
What was announced
On 28 September 2026 AIM-quoted Cadence Minerals plc (LSE:KDNC) announced that DEV Mineração S.A., the project's operating company, has started hot commissioning of the Azteca processing plant, which forms part of the Amapá Iron Ore Project in Brazil. The step follows completion of cold and wet commissioning. It was made possible by technical consent from the Amapá State Environmental Secretariat (SEMA/AP).
The consent permits temporary commissioning tests for up to 45 days from when feeding starts. Management expects testing to finish within that period. The consent is not an Operating Licence. That licence is still required before any commercial sales or shipments can take place, and concentrate produced during testing has to stay on site.
The numbers
First feed has been introduced to the plant. At this stage it is running at 25% to 50% of capacity so that throughput, concentrate grade and recovery can be measured. The intended commercial production rate is about 380,000 tonnes per annum of concentrate grading around 65% Fe, subject to commissioning, licensing and ramp-up.
Cadence holds a 36.2% interest in Pedra Branca Alliance Pte Ltd, which owns 100% of DEV. At 31 May 2026 Cadence had invested about US$16.1m in total.
The wider project has a JORC Mineral Resource of 276.2 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe. An updated pre-feasibility study published in December 2024 considered a larger operation producing 5.5 million tonnes a year of 67.5% Fe direct reduction concentrate. It gave a post-tax net present value (at a 10% discount rate) of US$1.97bn over a 15-year life. That study covers a much larger development than the Azteca plant now being commissioned.
Funding and infrastructure
The company said all restart and refurbishment Capital for the plant has been advanced under existing arrangements. Initial operating Working Capital is available but depends on the Operating Licence being granted. Proceeds from Cadence's recent fundraise are funding bridge repairs, infrastructure works and optimisation studies. Work has started on repairing the timber deck of the Pedra Branca do Amapari bridge, with completion targeted before first shipment.
Chief executive Kiran Morzaria, who discussed the milestone in a CEO interview released with the announcement, said: "Credibility comes from delivery. Producing a consistent product and delivering it to customers would establish an operating record."
What to watch next
The company has set out several near-term steps. DEV is due to submit maintenance and environmental monitoring documentation during the week of the announcement. A final commissioning report will follow once testing is complete, and DEV must then obtain the Operating Licence. The company is targeting commercial production and first shipment by the end of 2026. A definitive feasibility study is planned for 2027, and work on port and railway licensing is to follow.
Each of these steps depends on regulatory decisions and on how the plant performs during testing. The announcement gives no production volumes from the tests so far and gives no detail on offtake arrangements or pricing. Commercial production has not started. Achieving the targeted grade and throughput, and securing the Operating Licence, are the main conditions the company has identified before any sales can take place.