Key Takeaways
- CleanTech Lithium (LSE:CTL) announced on 24 July 2026 that it had produced approximately 330kg of high-purity lithium carbonate, with laboratory-confirmed purity of 99.68% to 99.91% across five batches, plus around 250kg retained in recycle fluids.
- The material was refined from 55,000 litres of pilot eluate processed by partner Empower EIT in Dallas, Texas, sourced from CleanTech's direct lithium extraction (DLE) pilot plant in Copiapó, Chile.
- Work streams feeding a planned definitive feasibility study (DFS) are running in parallel, including adsorbent benchmarking in France, process validation in Chile and brine reinjection studies.
- The company raised £4.77m at 6p per share in June 2026 to fund licence acquisition, engineering and a strategic-partner process; H1 2025 cash had fallen to roughly £143,000.
- Shares traded around 5.75p on 17 August 2026, for a Market Capitalisation of about £20.9m — well below the 52-week high.
CleanTech Lithium is a pre-revenue developer aiming to extract lithium from brines in Chile's mineral-rich Atacama region using direct lithium extraction rather than the water-intensive evaporation ponds that dominate the country's existing output. Its flagship Assets are Laguna Verde and Viento Andino, within the wider "lithium triangle". The Investment case rests on two propositions: that DLE can deliver battery-grade product with a lower environmental footprint, and that Chile's evolving licensing regime will grant a durable route to production. The 24 July 2026 announcement speaks to the first; the second remains a work in progress.
Latest Company Development
The catalyst is a Downstream processing result. CleanTech confirmed it had produced approximately 330kg of high-purity lithium carbonate by refining 55,000 litres of eluate — the lithium-bearing solution stripped from its adsorbent — at the Facility of US partner Empower EIT in Dallas. Independent laboratory testing put purity between 99.68% and 99.91% across five separate batches, with the highest figure recorded in the final campaign. A further 250kg or so of lithium remains locked in recycle fluids for later recovery, implying scope to lift yields as the flowsheet is tuned.
The processing drew on DuPont's FilmTec nanofiltration membranes and dedicated boron-removal technology, the latter important because boron is a stubborn contaminant in Andean brines and a potential by-product in its own right. Chief executive Ignacio Mehech, who took the helm in April 2025, called the results "a significant milestone" tied to progress towards undertaking a DFS.
Crucially, this is a validation exercise at pilot scale, not commercial production. The tonnage is measured in hundreds of kilograms, and the eluate was shipped abroad for refining. What the result demonstrates is that CleanTech's brine chemistry can be carried through adsorption, membrane treatment and carbonation to a purity comfortably above the roughly 99.5% battery-grade threshold — a proof point, not a Revenue event.
Financial and Operational Position
The financial backdrop demands attention. Interim results for the six months to 30 June 2025 showed cash and cash equivalents of just £143,225, against an operating loss of about £1.2m for the half — itself an improvement on £2.2m a year earlier after headcount cuts and tighter cost control. In other words, the company entered 2026 running on fumes.
That gap was addressed in June 2026, when CleanTech raised £4.77m through an oversubscribed placing, subscription and retail offer priced at 6p per share, issuing 79.51 million new shares. The raise was anchored by existing institutions alongside new investors, with Athos Capital committing to a portion of the conditional tranche; shareholders approved the resolutions on 1 July 2026. Management earmarked the proceeds for the Laguna Verde licence acquisition, environmental impact assessment work, DLE process and engineering, costs tied to a proposed ASX dual listing, the strategic-partner selection process and general working capital.
Operationally, several DFS-supporting work streams are running concurrently: DFS-level adsorbent testing in France, process validation trials in Chile with Lanshen, and spent-brine reinjection analysis by specialist Zelandez. A 5kg sample was being prepared for Chinese battery-grade qualification testing. On the permitting front, CleanTech has reported agreement on terms for a Special Lithium Operating Contract (CEOL) with Chile's Mining Ministry — a materially more constructive position than in mid-2025, when an initial CEOL application was rejected before the company expanded its licence coverage to more than 97% of the government's target polygon.
What Could Drive the Shares Next
Near-term catalysts cluster around de-risking. Confirmation of DFS commencement and, in time, credible economic parameters would give the market something concrete to value against the current sub-£21m capitalisation. Finalisation of the CEOL would remove a fundamental overhang on Laguna Verde's tenure. Perhaps most significant is the strategic-partner process: securing a well-capitalised backer could underwrite the far larger sums a commercial DLE operation requires, and validate the technology commercially. Positive Chinese battery-grade qualification and ASX-listing progress round out the list.
Risks Investors Should Watch
The risks are substantial. CleanTech is pre-revenue and has historically been thinly capitalised; even after the June raise, a multi-year development path implies further funding needs and potential dilution at a depressed share price. The shares sit well below their 52-week high, reflecting weak sentiment towards junior lithium names amid soft carbonate prices. Chile's lithium framework is state-directed and politically sensitive, and the CEOL, while advanced, is not yet a producing licence. DLE at scale remains commercially unproven for many developers, and pilot purity does not guarantee consistent battery-grade output from a full plant. Finally, the eventual Economics — capital intensity, operating costs and reinjection performance — will only crystallise with the DFS.
Outlook
The 330kg result is a genuine technical achievement that strengthens the case for CleanTech's flowsheet ahead of a DFS. But the company remains early-stage, capital-constrained and dependent on permitting and Partnership outcomes largely outside its control. The next twelve months should bring clarity on the CEOL, the strategic-partner process and the DFS itself — the trio that will determine whether Laguna Verde advances from promising pilot to fundable project.
Final Take
CleanTech has delivered on the metric within its direct control: producing high-purity lithium carbonate from its own brine at pilot scale. Converting that into a financed, permitted, commercially viable operation is the far harder task, and one that will test both the technology and the balance sheet. For investors, this is a high-risk, high-optionality story where execution over the coming year matters more than any single milestone.






Please wait processing your request...