Cornish Metals has opened a new workshop and stores building at its South Crofty tin project in Cornwall, and mine dewatering has now passed 400 metres below surface. The company is targeting the 400-level, about 730 metres down, in the first half of 2027.
What was announced
AIM-quoted Cornish Metals plc published an operations update for the South Crofty tin project on 12 October 2026. The main item is the opening of the Bartles Foundry facility on 22 September 2026. The building provides maintenance, engineering, storage and office space.
The numbers
Bartles Foundry cost about £6.8 million. A grant of up to £4.2 million came from the UK Shared Prosperity Fund, managed by Cornwall Council. The grant could cover up to about 62% of the building's cost.
Underground, dewatering has passed 400 metres below surface and refurbishment of the NCK shaft is speeding up. The company is targeting the 400-level, about 730 metres below surface, in the first half of 2027. On 25-level, 260 metres of development has been completed across the Conveyor Drive and Bunker Drive.
At surface, the single-drum service winder has been delivered and mounted on its new foundation at the NCK shaft. The double-drum production winder is on site, and mechanical installation is under way in the completed winder house. Bulk excavation for the process plant is substantially complete and civil works have started. Ausenco is leading detailed engineering. Key engineering packages are expected to go to tender by the end of 2026, and most purchase orders for mechanical equipment are expected to be placed by year-end.
The Roskear West surface drilling programme totalled 2,330 metres in two holes and is now complete. Hole SDD26_001A returned 0.79 metres at 4.18% tin at Roskear 1 South. Hole SDD26_002 returned 1.51 metres at 1.46% tin, including 0.33 metres at 5.71% tin, at Roskear South. The same hole intersected a new high-grade tungsten zone of 8.58 metres at 1.41% tungsten (1.78% WO3), including 0.52 metres at 15.15% tungsten (19.10% WO3). High-grade copper was found at shallower depths. All intervals are downhole lengths, and true widths have not been calculated. Tin mineralisation continues west of the current Mineral Resource Estimate (MRE) and remains open in that direction. Tungsten and copper were not targets of the programme and are not part of the current MRE or production guidance.
Background
South Crofty is a historic underground tin mine with existing shafts and infrastructure. It is permitted for underground mining until 2071, as well as for a new processing facility and site infrastructure. The company expects output of about 4,700 tonnes of tin-in-concentrate a year in the first five years of full production, at what it describes as lowest-quartile all-in sustaining costs, over an initial 14-year mine life. It says the operation would have no surface tailings and could become Europe's or North America's first primary tin producer. It estimates the project will create more than 300 direct jobs.
Chief executive Don Turvey said: "The opening of Bartles Foundry is an important moment for South Crofty." He said the work at the NCK shaft is moving from preparation into construction, and that the Roskear results point to potential growth beyond the current resource. He added that tin remains the company's focus and that the next phase of exploration will build on what the programme has shown.